• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

DOD States Contractor Profit Not a Target, While Targeting Contractor Profit

E-mail Print PDF
Okay, this one is going to touch on a few seemingly unrelated topics.  Bear with us and we’ll try to tie it all together by the end.Let’s start with the issuance of a DOD policy memo, on November 10, 2011, by Shay Assad (formerly Director, Defense Procurement and Acquisition Policy, and now Director, Defense Pricing, under the Under Secretary of Defense, Acquisition, Technology and Logistics).  Mr. Assad’s memo was entitled, “Direct and Indirect Charging of Contractor Proposal Preparation and Negotiation Support Costs.”  (You can read the memo here.)

We don’t think that the substance of the memo is particularly controversial.  It offered very little novelty in its interpretation of existing regulations.  Its guidance was (in our view) entirely consistent with the requirements of the B&P/IR&D cost principle at 31.205-18.  It was consistent with the requirements of CAS 402, Interpretation No. 1 as we understand them.  It was consistent with the requirements of CAS 420 as we understand them.  In most circumstances, the memo would be unremarkable and we’d let it pass without comment.

What makes Mr. Assad’s memo worth commenting on is its expressed bias against the direct-charging of proposal preparation costs.  The memo stated—

As a matter of policy, contracting officers should minimize the situations where a contractor will be required to prepare proposals for new requirements or to definitize unpriced contractual actions. … If a contracting officer requires a proposal for a follow-on contract or for new requirements, or determines it is necessary to award undefinitized contractual actions, the Department will often be placed in the position of paying for the proposal and negotiation costs on a reimbursable basis with little or no competitive control over the costs incurred.  Contracting officers should avoid placing the Government in that position.

 

Well, isn’t that special. The obvious problem with that policy position, of course, is that the proposal preparation costs that are not charged directly to contracts have to be charged somewhere else.  If not direct, then they must be indirect.  Thus, if the policy position in the memo is adhered to, then proposal prep costs that might have been legitimate direct contract charges will instead be accumulated in indirect B&P projects, to be allocated back to contracts on the same base as is used for allocating G&A expenses.  Instead of being direct contract costs that actually absorb G&A, they will essentially add to contractors’ G&A expense pools.  In other words, the expressed bias against direct-charging of proposal prep costs will inevitably lead to increases in contractors’ indirect costs—specifically, their G&A expense indirect cost rates. 

But perhaps Mr. Assad was less worried about indirect costs than he was about direct contract costs.  If so, that would be a 180 degree turn from DOD’s traditional position, which was that contract cost performance reports and similar Earned Value Management information provided insight into individual contract costs, whereas indirect rates were largely a mystery, denoted by rates/percentages and guarded by DCAA auditors against the prying eyes of DCMA contracting officers.

If we’re correct in our assessment, then Mr. Assad’s implied policy position—that the DOD has more visibility and control regarding contractors’ overhead costs than it does regarding contractors’ direct costs—would not be inconsistent with past positions Mr. Assad has taken.  In fact, Mr. Assad has, in the past, promised increased DOD scrutiny on contractor indirect costs.  For example, in June, 2011, when Mr. Assad departed his previous post to accept his current position, we reported his remarks on contractor indirect costs, which, at the time, we thought portended some important changes in DCMA focus.  Among other sources, our article linked to an Aviation Week & Space Technology story that included the following Assad quote---

‘The reality is we need to step up our game across the board, and so that’s what we’re doing,’ Assad told reporters. He said unlike profit margins, overhead costs would be fair game. ‘That’s cost. How do we get that out?’ …

 

So it’s quite possible that Mr. Assad feels his new DCMA pricing team can better control indirect costs than they can direct costs.  We are skeptical of DCMA success in that quest; but it is certainly a quest that can be reasonably pursued by Mr. Assad’s team.Assisting Mr. Assad on his quest to rein-in contractor overhead (and presumably other indirect costs) will be a revitalized and repurposed acquisition workforce, according to November 16, 2011, report on Federal News Radio.  The report stated—

The Defense Department says it's taking several new steps designed to drive toward better business deals. They involve not only rebuilding the acquisition workforce, but also making sure that workforce has the tools to make good decisions. …     Shay Assad, the Pentagon's director of Defense pricing, said the steps are a ‘revolutionary approach’ to making sure DoD's acquisition professionals get much more skilled in understanding the business deals they make with industry. They center on giving acquisition staff a better view of what's happening across DoD itself. …

 

The changes will be led by the Defense Contract Management Agency, the DoD entity that handles administration of contracts, Assad told attendees at a conference of the Government Contract Management Conference in Bethesda, Md.

 

Assad said DoD is starting by bringing all of DCMA's administrative contracting officers (ACOs) back into one place after a period of decentralization.

 

‘We're going to have a uniform approach to how we deal with our peers in industry,’ he said. ‘That change is taking place right now. It should lead to a more consistent understanding of what the government's position is. It should lead to an improved ability for forward pricing rate agreements to come about. We're establishing a fundamental position in the department that says that these corporate ACOs who are responsible for rates will be the contracting officers' central repository of information with regard to rates.’

 

Second, DoD is piloting a new system called the Contractor Business Analysis Repository (CBAR). The tool is designed to give contracting officers much more insight into DoD's past and ongoing relationships with a particular company they may be dealing with.

 

‘They'll be able to log in and get access to every business deal over $10 million with that company,’ Assad said. ‘The ability for contracting officers to have much more awareness of what's happening throughout this very large organization will be provided to them almost instantaneously and in real time. In addition to that, they'll have access to all of the rates that have been proposed, what DCMA's position has been and what the contactor's position has been over time. Our contractors are really excited about having this kind of capability.’ …

 

A third initiative is tied to the regrowing of DoD's acquisition workforce. Assad said DCMA has hired 300 price analysts and engineers for one specific purpose, to populate a new effort called ICAT — or Integrated Contractor Analysis Teams. The groups will be able to offer immediate technical and pricing assistance to contracting officers. Similarly, new regional pricing teams will be stood up to help with smaller contracting projects. They'll focus on contracts that are smaller than $100 million and be available as a resource to help contracting officers who need expertise in figuring out pricing. …

 

In a future blog article, we will discuss a recent GAO report assessing DOD’s efforts to enhance its acquisition workforce.  So stay tuned for that.One additional point from the Assad memo on proposal prep costs.  Those who read the entire memo (and if you didn’t read it, shame on you) would have noticed a couple of sentences at the very end, which said—

… we will soon be issuing a proposed DFARS rule (Case No. 2011-D042), that will provide a check-list to help gauge the adequacy of a contractor proposal.  Such controls like this checklist, once finalized, will help prevent the Department from being billed for a substandard proposal package that will not adequately support negotiation of a reasonable price.

 

That’s an interesting comment on a number of levels.   First, we note that DCAA already has such a checklist.  (It’s called the “Forward Pricing Adequacy Checklist” and is available at the DCAA website).  So either the current DCAA checklist is inadequate—or perhaps it’s so useful that the DAR Council thinks it should be given the authority of a regulation! The introduction to the DCAA proposal adequacy checklist includes the following statement—

When the proposal is based on information other than certified cost or pricing data, the contracting officer is responsible for obtaining information that is adequate for evaluating price reasonableness. Inadequacies exist when the offeror does not comply with the contracting officer’s requirements. The following criteria, while specifically not applicable to information other than certified cost or pricing data, may provide a guideline to the auditor in reaching an opinion as to the adequacy of the proposal (CAM 9-208). Consideration should also be given to any specific requirements in the request for proposal (RFP).

 

We highlighted in italics an interesting sentence; to wit, that DCAA admits its proposal adequacy checklist is not applicable when TINA applies to a proposal…but auditors should feel free to use on non-qualifying proposals anyway---since it may be a useful “guideline” for auditors.
 Yeah, we know how that’s going to turn-out, don’t we?

Further, we note that DCAA apparently is misinterpreting the requirements of FAR 15.404-2 when it defines an inadequate proposal one that “does not comply with the contracting officer’s requirements.”  In our view, a fair reading of that FAR rule would be that the contracting officer requests “field pricing assistance” (which includes DCAA audit of the contractor’s cost proposal) only when that contracting officer concludes that the contractor proposal, as submitted, is “inadequate to determine a fair and reasonable price.”  Thus, by regulatory rule, DCAA would be involved in a cost proposal audit only when the offeror’s proposal had been determined to be inadequate by the contracting officer. In other words, every single proposal that DCAA audited would be, by definition, inadequate under its definition of adequacy.
Second—and as we’ve opined before—the recent emphasis on contractor proposal adequacy is misplaced, or perhaps we should say that it places focus on a symptom rather than the real problem.  
We wrote (and reiterated similar thoughts in a subsequent blog article)—

... we wonder if the foregoing Air Force and DCAA direction might not be avoiding addressing the real problem—which is insufficient identification of Government requirements, and subsequent changes to those requirements—which prevents contractors from submitting timely and comprehensive proposals.  (See the GAO reports linked above, which show the lack of defined requirements is a much a problem as any lack of cost or pricing data.)  Focusing on enforcing timely contractor provision of requested data to support fact-finding and negotiations seems to be a fundamentally misplaced management emphasis...

 

So we wonder just how important to DOD buying efficiency this soon-to-be-proposed DFARS rule really will be, and how much money DOD really will save from requiring, by DFARS rule, that contractor proposals be “adequate”.  Keep your eyes on that DFARS Case and, when it’s issued, then see if you agree with us that it’s likely to turn-out to be a cure in search of a disease.

Mr. Assad has emphasized several times that he’s not looking to impact contractor profitability—just their costs.  He’s fine with contractors making a reasonable profit (as he should be, given that it’s official Government policy).  He reiterated this position again, quite recently, and the MSM and others who follow the defense industry picked-up on his words and reported them (again) as if they were some kind of promise of safe-harbor in the upcoming storm of sequestered DOD budgets.
Here’s one example of such “gosh, what wonderful news!” reporting—

Even with the Pentagon looking to make widespread cuts and improve efficiency, profitability is not a target and it may increase, the Defense Department's director of procurement and acquisition policy told an audience of investors Wednesday.

Speaking at the Credit Suisse 2011 Aerospace & Defense Conference, Shay Assad said that the Pentagon is concerned with cost reduction, not margin reduction, and that he would be surprised if profitability went down even as spending is decreased.

 

‘It wouldn't bother us at all if operating margins go up, so long as we're paying less,’ he said. ‘We want to spend 90 and have them make 15, we don't want to spend 105 and have them make 15.’

 

Despite Mr. Assad’s assertions, it’s become apparent that not everybody in DOD shares his point of view.  In April, 2011, DPAP issued policy guidance discussing use of Performance-Based Payments (PBPs).  We wrote about our disappointment with the DOD policy position here.  Readers should remember that Mr. Assad was still Director of DPAP when this particular piece of pathetic policy was issued.  The policy memo asserted that contractors should offer the DOD “consideration” in return for permission to use PBPs—conveniently forgetting that previous DOD policy acknowledged that consideration had already been provided through DOD’s lower administrative costs.  In any case, the policy memo also directed contracting officers to utilize an Excel-based spreadsheet that determined “a win-win price that equitably accounts for the cost, benefits and potential risk associated with PBPs.”  That tool can be found at the DPAP website, right here.

The defense industrial base was, quite rightly, concerned with DOD’s new PBP policy.  The Aerospace Industries Association (AIA) went so far as to send a letter to DPAP in September, 2011, expressing its concerns.  As one commenter summarized AIA’s concerns as follows—

Basically the [DPAP cash flow] tool compares the net present values of the cash flows under progress payments and those with performance based payments. The aim is to assure that the discounted outlay is not higher under performance based payments than under progress payments. The discount rate for the government cash flows (out) differs from the discount rate used for the contractors’ cash flows. The tool splits that delta (arriving at the win-win) and calculates a rate of profit that achieves that win-win outlay. The contracting community’s major concern has been the discount rate selected and the fact that the tool appears to fly in the face of the preference for performance based payments by making them less attractive.

 

Clearly, that commenter was far more diplomatic that we have been on this topic.On November 10, 2011, AIA (and other industry associations) met with a DPAP representative to discuss industry’s concerns.  In that meeting, attendees (and now our readers) learned the following—
  • DFARS Case 2011-D045 will reference the cash flow tool and include a cost limitation clause, and guidance for use of the tool.  Why this needs to be a DFARS rule and not a revision to DOD’s PGI remains to be seen.
  • The cost limitation contract clause noted above will limit the value of PBPs to the contractor’s actual incurred costs.
  • DOD does not like PBPs and feels that they provide no incentive for on-schedule performance.
  • DOD does not intend that PBPs be used with competitive awards, because of the expense and delay associated with conducting two negotiations (one for customary progress payments and the other for the price difference associated with use of PBPs).
  • DOD believes that use of PBPs requires additional reviews prior to payment, whereas those reviews need not be present to process customary progress payments.
  • DOD intends that contractors receive a lower profit rate when PBPs are utilized, notwithstanding the current Weighted Guidelines direction that PBPs are riskier to the contractor than are progress payments.
We are going to gloss-over the level of ignorance and wrong-headedness displayed by the DPAP representative in the foregoing.  We are going to gloss-over the fact that progress payments require adequate contractor accounting systems and periodic DCAA audits.  We are going to gloss-over the fact that PBPs were imposed by Congress (via FASA) and DOD is clearly violating the will of the Legislative Branch in its recent actions.  No, we’re simply going to note that, while Mr. Assad is assuring industry and media that DOD is looking to reduce contractor cost— but not contractor profits—the words and deeds of his former Directorate demonstrate otherwise.

So let’s wrap-up this perhaps overly long survey of recent DOD activities that impact its industrial base.  What have we learned?
  • DOD is focused on reducing contractors’ indirect costs, while at the same time it issues policy guidance that will tend to increase contractor’s indirect cost.
  • DOD blames contractors for inadequate proposals, while failing to address its own shortcomings that create those inadequate proposals.
  • DOD is reorganizing and hiring-up, to provide more opportunities to drive down contractor costs.
  • DOD is actively seeking to overturn the will of Congress and, through its actions, reduce contractor profits while creating more workload for DCAA.
And if you don’t care for what you’ve learned, you can point to Mr. Assad as the instigator of most of it.
 

Apogee Update

E-mail Print PDF

To our loyal readers,


As we mentioned in passing a couple of weeks ago, we have been extraordinarily busy.  That's a good thing!  Unfortunately, it also means that some things have to be moved to the back-burner.  After all, there are only so many hours in one day!  So our blog posts have dwindled in frequency and, over the past couple of weeks, have died altogether.  Rest assured, this is a short-term phenomenon. 


We've received several emails inquiring about the blog articles.  Thanks for your interest!  We promise be back with new blog articles before Thanksgiving.
Until then, we ask for your patience.


Sincerely,


Nick SandersPrincipal Consultant

Apogee Consulting, Inc.

 

DCMA Issues Guidance on Disapproving Contractor Business Systems

E-mail Print PDF

On September 21, 2011, DCMA issued policy guidance to Contracting Officers addressing the process for making final determinations regarding Contractor Business Systems.  As readers should be aware, in May 2011 the DAR Council published an interim rule on Contractor Business Systems, defining six (6) Business Systems and establishing a process for those systems to be reviewed, for “significant deficiencies” to be reported to a DCMA Contracting Officer, and for that Contracting Officer to make a determination that the Business System in question is either “adequate” or “inadequate”.  If the Business System is determined to be inadequate, then the new rule requires a mandatory payment withhold on covered contracts (ranging from five to ten percent of total contract costs).

Industry bitterly fought the proposed rule but, ultimately, lost the battle and the new oversight/enforcement regime was established.  (Even Apogee Consulting, Inc. submitted comments to the DAR Council.)  One of the biggest concerns expressed by those opposed to the rule was in regard to the process, which seemed ill-defined and prone to subjectivity and inconsistency.  The DCMA policy established by the memo goes a long way to address those concerns.

The policy memo establishes a Contractor Business Systems Review Panel for the purpose of performing “a higher-level review of the COs final determination to disapprove a Contractor’s Business System, prior to notifying the Contractor in writing that the system is disapproved.”  The memo states that the Panel will “fully evaluate and discuss” all significant deficiencies identified by DCAA, and will ensure “consistent application of the Business System criteria and policy requirements.”

According to the policy memo, the process is as follows—
  1.  When a CACO/DACO/ACO network exists, the CO responsible for making the final determination must obtain concurrence from all network COs prior to notifying the Contractor of the final (negative) determination.
  2.  All final determinations must be approved by the CMO Contracts Director or the Director of the Pricing Center prior to issuance to the Contractor.
  3.  Prior to notifying the Contractor, the cognizant CO must submit a review package to the Business System Review Panel.  The package must include (a) a copy of the audit report, (b) the Contractor’s response to that audit report, and (c) a proposed final determination written notice.
  4. The intent is to convene the Panel within three days to review the CO’s determination.
Importantly, the Panel’s recommendations and opinions “are advisory” (“for most cases”) but “shall be considered” by the CO prior to disapproving a Contractor’s Business System.

We have gone on record as disapproving—quite stridently—of the DCMA’s recent predilection for convening Review Boards.  We think that such Boards undercut the FAR-mandated discretion of Contracting Officers, intimidate personnel and stop them from disagreeing with DCAA audit findings, and (in general) unreasonably slow down the procurement system.  That being said, we think this particular Review Board is a good interim step to ensuring an equitable application of an inequitable rule.

In the long run, however, we think the better approach is to properly train Contracting Officers, reinforce their discretion and authority, and then hold them accountable for their decisions.
 

SAIC Back in the News, Not in a Good Way

E-mail Print PDF
In past articles, we’ve noted that SAIC has had a few compliance challenges.  For example, in this article we wrote about allegations of bid rigging, and in this article we wrote about allegations of subcontractor kick-backs and timekeeping “irregularities” by an SAIC project manager.  In the latter article, we wondered aloud whether SAIC’s “notoriously decentralized and entrepreneurial” corporate culture may have contributed to the alleged issues caused by its rogue employees. Now comes another recent story involving yet another rogue SAIC employee.  This time it may end up costing the company millions of dollars.

When this story first came to our attention, we frankly didn’t think too much about it.  Apparently, in September 2011, an SAIC employee had his car broken-into in San Antonio, Texas.  His laptop was stolen.  The laptop contained personal information (including healthcare information) of millions of military service members enrolled in the DOD’s TRICARE program.  TRICARE itself downplayed the risk, stating—

‘The risk of harm to patients is judged to be low despite the data elements involved since retrieving the data on the tapes would require knowledge of and access to specific hardware and software and knowledge of the system and data structure.’

Ho hum.  Just another data theft story.  Or so we thought.But just a few weeks later, we ran across this story at NextGov.com.  It reminded us that SAIC may be facing some rather large financial repercussions related to the data theft.  The story reported—

Austin Camacho, a TRICARE Management Activity spokesman, said in a statement emailed to Nextgov that SAIC is ‘contractually bound to mitigate the harmful effects of such disclosure. …’

Readers, reportedly 4.9 million people were affected by the data theft. According to the TRICARE spokesperson, SAIC is contractually bound to mitigate the damages suffered by those 4.9 million people, including  the generation of 4.9 million individual data breach notifications and the operation of call centers to address the questions and concerns of those affected.  According to the NextGov article— 

Larry Ponemon, chairman of Ponemon Institute, a research organization that specializes in privacy and data protection, estimated mail notification could run as high $7 per person, which means SAIC could face a bill of $34.7 million to notify all 4.9 million TRICARE beneficiaries.

But that’s not all.  In addition to the $34.7 million cost of notifying the affected people, SAIC may also be liable under statute for the data breach.  The NextGov story reports—

The 2009 Health Information Technology for Economic and Clinical Health Act, enacted as part of the 2009 American Recovery and Reinvestment Act, specifies fines as high as $1.5 million for what it calls a breach of health care data.

Camacho said, ‘The Department of Health and Human Services has the discretion to investigate the conduct of both the TRICARE Management Activity and SAIC and assuming it does so will ultimately make the determination as to whether and against whom it seeks to levy any penalties.’

So this rogue employee may end up costing SAIC at least $36 million.  But that’s not all.Just a few days later, the Department of Defense was served with a $4.9 billion class action lawsuit related to the data breach.  According to NextGov (link in previous sentence)—

The suit … seeks $1,000 in damages for all 4.9 million TRICARE beneficiaries whose records were on the computer tape stolen Sept. 13 from the SAIC employee's car in San Antonio. TRICARE and Defense Secretary Leon Panetta are named as defendants. …

The suit …charges that TRICARE ‘flagrantly disregarded’ the privacy rights of TRICARE beneficiaries by failing to take the necessary precautions to protect their identity. The complaint said data on the stolen computer tape was ‘unprotected, easily copied . . . [and TRICARE] inexplicably failed to encrypt the information.’

TRICARE ‘compounded its dereliction of duty by authorizing an untrained or improperly trained individual to take the highly confidential information off of government premises and to leave unencrypted information in an unguarded car in a public location, from which it was stolen by an unknown party or parties,’ the suit alleged.

The ‘intentional, willful and reckless disregard of plaintiffs' privacy rights caused one of the largest unauthorized disclosures of Social Security numbers, medical records and other private information in recent history,’ the complaint charged.

But that’s not all.  Just a few days later, SAIC was itself served with a similar lawsuit, also seeking $4.9 billion in damages plus free credit monitoring.

But that’s not all.  On November 7, 2011, NextGov reported that—

The TRICARE Management Activity on Friday directed Science Applications International Corp. to provide credit monitoring services for up to 4.9 million beneficiaries whose health information was stored on backup computer tapes stolen from an SAIC employee's car in San Antonio. …  [TRICARE] directed SAIC provide one year of credit monitoring to patients who want it. SAIC will also analyze all available data to help TMA determine if identity theft occurs due to the data breach …

Providing credit monitoring services is not cheap.  According to NextGov—

This could hit SAIC with a hefty bill if all 4.9 million beneficiaries whose data was on the stolen tapes ask for credit monitoring. When the Veterans Affairs Department experiences a loss, theft or exposure of this kind, it routinely offers credit monitoring services and up to $1 million annually in identity theft protection at a cost per veteran of $29.95 a year. If SAIC provided such monitoring and protection at the same rate, it would cost $146.8 million to cover 4.9 million people.

So, let’s see now.  We were at about $36 million or so.  Plus $4.9 billion in potential legal damages.  Plus $147 million in credit monitoring services. Hey SAIC, might want to rein in those rogue employees of yours.  You know, the ones who can’t be bothered to encrypt their laptop hard drives?  
 

Boeing’s Innovative Plan to Reduce Medical Plan Costs Shot-Down by FBI

E-mail Print PDF
Drug_Bust

On September 28, 2011, the FBI stopped Boeing’s unique and innovative attempt to reduce out-of-control medical plan costs. See the news story here.

According to the story, FBI agents raided Boeing’s Ridley Park, Pennsylvania facility and arrested “approximately three dozen people” on charges of running a “prescription drug ring” at the facility. The story reported that, “the accused are a variety of workers, from line workers at the plant to office personnel, along with former employees and outside folks.” Another story, on Reuters, reported that, “23 people were charged with selling the prescription painkiller Oxycontin and other illegal drugs and 14 were charged with attempted possession of various drugs for trying to buy them.”

Boeing produces helicopters at the plant, including both the Chinook and parts of the V-22 Osprey. Roughly 6,000 are employed at the facility. There is no indication that any military hardware was compromised by the druggies at the site.

Boeing, of course, is now going to face some difficult questions, including:

  • How effective is its plant security at the facility?
  • How does the facility ensure compliance with the Drug-Free Workplace Act of 1988, which requires (among other things) that the company make a “good-faith effort to maintain a drug-free workplace”?
  • Where did the employees charge their time when engaging in the (alleged) illegal activities?

The bottom-line is that the company is going to have to divert resources from other activities to address the foregoing questions. This is going to be a problem for some time to come.

  

 


Page 196 of 278

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.