• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

Auditor Wins Battle Against NASA in $279 Million Breach of Contract Case

E-mail Print PDF

NASA
On March 21, 2012, the U.S. Court of Federal Claims granted a motion for partial summary judgment, ruling for the CPA firm of Horn & Associates in its $279 Million breach of contract suit against NASA. Details are sketchy, but Law360 (subscription required) reported the case as follows—

NASA contracted Horn & Associates Inc. in 2004 to look at its books and determine whether the agency had overpaid for various services over a 10-year period. After Horn began work, NASA began to dispute what exactly it had contracted the firm to do.

From what we can gather, NASA issued an RFP for firms to assist in auditing contracts for improper payments. The RFP specified that the auditors would review only firm fixed-price contract types. When Horn & Associates submitted its proposal it “recommended” that NASA review all contract types. Law360 reported—

When NASA awarded the contract to Horn & Associates, it included a clause stating ‘[t]he contractor shall perform a primary audit recovery on all contract payments for the period beginning Oct. 1, 1997 through Sept. 30, 2003, identifying overpayments and/or underpayments.’

Accordingly, the dispute between the contracting parties centered on whether NASA had, or had not, hired Horn & Associates to audit all contract types, or just firm fixed-price contract types. NASA itself was confused about what it had hired the auditors to audit. The Law360 story stated—

Evidence of NASA’s confusion about what was required under the contract was evident by emails that went back and forth with different language about it, according to the judge’s opinion. NASA eventually provided Horn & Associates with some information about contracts other than fixed ones.

Judge Horn of the COFC (no relation to the plaintiff) found that the language in the contract superseded the language in the RFP. The Judge found, further, that if there was any ambiguity, the doctrine of contra proferentum would dictate that the ambiguity be construed against the drafter (i.e., NASA).

Law360 quoted Judge Horn’s decision as follows—

‘In this case, the contracting officer, with authority to do so, issued and signed the order, with its attached statement of work to audit all contracts,’ the judge said. ‘The contracting officer personally put the order number on the upper right hand corner of each page of the order, including the statement of work identifying the scope of work as encompassing all contracts, signifying the contracting officer’s review and approval of the language of the order and the statement of work attached thereto.’

Being interested in this David vs. Goliath victory, we contacted Mr. Horn, who told us—

“We think we have a good case and we won the first of a series of battles that we are expecting. We just hope we win the war! You never know in these situations until the check clears the bank.”

It is important to remember, in the words of Mr. Horn, that this represents one battle in a long campaign. But should Horn & Associates prove victorious at the end of the war, they will cash a whopping $279 Million check. We wish them the best of luck.

 

DCAA Issues Audit Guidance Concerning Proper Charging of B&P and IR&D Costs

E-mail Print PDF

On March 22, 2012, the Defense Contract Audit Agency (DCAA) issued audit guidance concerning the proper charging of Bids & Proposals (B&P) and Independent Research & Development (IR&D) costs. This topic is not new to readers of this blog. Indeed, in December, 2011, we told you about the policy memo from Shay Assad (Director, Defense Pricing) that addressed this very topic. In fact, the bulk of this particular DCAA Memorandum for Regional Directors (MRD) is essentially a letter of transmittal of that Assad policy memo. (Why it took DCAA four months to pass the memo to its auditors remains a mystery.)

We already reported on the Assad memo (link above) but DCAA has added some additional pointers to assist its auditors. (When do they not?) The MRD states—

Auditors should examine disclosed practices and report a noncompliance with CAS 402 and CAS 420 if disclosed practices allow the contractor to charge proposal costs directly, absent a specific contractual provision for the effort. Auditors should be alert for vague and misleading wording in the disclosure statement that could lead to direct charging proposal costs that are not specifically required by an existing contract. If the examination is not within the scope of a current assignment, a focused audit of the specific cost accounting practice should be initiated under the 19100 activity code. Identified noncompliances should be reported immediately under the 19200 activity code. In addition, auditors should test proposal preparation costs identified in forward pricing and incurred cost audits for compliance with CAS 402 and 420.

Why do we take issue with the foregoing audit guidance?

First of all, our experience with this issue (and we have lots of experience with this issue) tells us that the “specific contractual provision” is not a clear as the audit guidance would presuppose. By way of explanation, let’s discuss a hypothetical example. Suppose you have a contract and the contract is silent regarding submission of a follow-on proposal. Then one day you receive a phone call from your authorized Contracting Officer, telling you to prepare a follow-on proposal and charge proposal preparation costs to the existing contract. What do you do?

In our view, if you have explicit direction from a Government representative with authority to direct you, then you follow that direction. (Unless, of course, if following the direction would lead you into a cost accounting practice that would be inconsistent with your disclosed or established cost accounting practices. Contracting Officers do not have authority to direct a contractor to violate a statute.) In this case, the CO’s direction essentially added the follow-on proposal to the list of contract deliverables (CDRLs). Since the proposal was a contract deliverable, the costs of preparing that proposal should be treated as direct costs of the benefiting contract.

So that’s what the DCAA audit guidance missed.

Second, we are apprehensive that DCAA auditors will have little if any idea exactly what “vague and misleading wording in the disclosure statement” might look like. In our experience, Disclosure Statement language is, by necessity, general and somewhat vague regarding specifics, since the language has to cover all situations. So we think that bit of direction will lead nowhere good.

Finally, readers of this blog may have familiarity with our views on DCAA audit quality and timeliness. (How could you not? We cram it down your throat every week.) This guidance directs auditor to “test proposal preparation costs” in contractors’ new business cost proposals, as well as in Final Incurred Cost Proposals (FICP) for compliance with CAS 402 and 420. (Add to that also testing within Forward Pricing Rate Agreements.) It’s not that we object to CAS compliance testing within those assignments—we have no problem with that, assuming that DCAA can perform its work timely. But the problem is that the audit agency cannot perform its work timely right now. Adding to the workload will only add to the duration of the audits. And that serves nobody.

If DCAA wants to evaluate contractors’ compliance with the Cost Accounting Standards, then have at it. But don’t try to cram in yet another tasking within the already high priority and high stress forward pricing and FICP audits.

 

 

Lockheed Martin Agrees to $15.8 Million FCA Settlement

E-mail Print PDF

On March 23, 2012, Lockheed Martin agreed to pay $15.8 million to settle allegations that the company mischarged the U.S. government for “perishable tools” used on major aircraft programs, including the F-22 and the F-35. What caught our eye was not necessarily the size of the settlement (it’s rather small as such things go) but, instead, it was the fact that it was LockMart’s subcontractor (Tools & Metals, Inc., or TMI), that did the actual mischarging. LockMart just added burden and fee to the subcontractor’s costs, and invoiced the government. Normally, it’s rather difficult to establish liability under the civil False Claims Act (FCA) for (presumably unknowingly) passing on improper costs to the government.

As many readers are likely aware, the civil False Claims Act was amended in 1986 to establish defendant liability for “deliberate ignorance” and for “reckless disregard” of the truth. So to prove that LockMart was liable, the government needed to show that it acted in deliberate ignorance or with reckless disregard for the accuracy of TMI’s invoices. That is not as difficult as showing scienter (i.e., knowing intent), but it’s not especially easy to do either.

Readers also need to understand that the government typically holds the Prime accountable for the actions of its subcontractors. Accordingly, if the subcontractor commits “defective pricing” then the government’s remedy is to assess the pricing impact at the Prime level, and leave it up to the Prime to recover the price adjustment through legal action against the subcontractor. That’s called “privity of contract” and it basically means that the contract is between the Prime and the government, so the government has no means of reaching the subcontractor.

Now, privity of contract is not always in play. For example, many times the cost impact(s) of CAS noncompliances will be assessed against the subcontractor and not the Prime—particularly if the subcontractor is a large company. (We note legal precedents that say this should not be the case, but in our experience it is the case, regardless of legal opinions to the contrary.)

In this particular instance, it seems that the government went after the subcontractor (TMI) first, then came after the Prime (Lockheed Martin) separately. (We caution readers that our interpretation of the situation may be wrong; we have no inside information and have only the tidbits in published news stories to guide us in our analysis. So caveat emptor.)

The news story (link in first sentence, above) reported—

In March 2006, Todd B. Loftis, a former TMI president, was sentenced in federal court in Fort Worth, Texas, to 87 months in prison and ordered to pay $20 million in restitution after his December 2005 guilty plea in connection with his role in the scheme.

Loftis had waived an indictment and pleaded guilty to a one-count information charging conspiracy to defraud the government with false and fraudulent claims. He admitted that from 1998 through 2004, as president and chief operating officer at TMI, he, along with others, conspired to defraud the Defense Department and Lockheed Martin Aeronautics by obtaining payments from both through false and fraudulent billings. …

In order to cover up this activity, the government said, Loftis and others under his direction created false invoices using a computer scanner to remove actual pricing data and substitute fictitious data to give the appearance of legitimate pricing. Loftis was able to control the audit sample of invoices as well so as to limit the possibility that a fraudulently priced part would be found. After the audits, Loftis ordered the fraudulently created documents and computer files to be destroyed.

TMI and Loftis realized approximately $20 million in profits on these fraudulent sales to the government, prosecutors said.

The foregoing provides details regarding how TMI perpetrated its fraud, but it doesn’t address LockMart’s culpability. Where was the deliberate ignorance or reckless disregard?

The first thing we noticed in the story was the following sentences—

In 1998, TMI … obtained a sole-source integrated supply contract with Lockheed Martin Aeronautics to supply all of Lockheed’s perishable tools for the manufacture of airplanes including the Defense Department’s F-16, F-22 and other military needs in Fort Worth, San Diego and Marietta, Ga. Perishable tools are the drill bits, router bits and other small tools that are used in the manufacturing process.

We wonder why TMI was able to win the subcontract award. Now, perhaps TMI had some kind of proprietary technology that made its “drill bits, router bits and other small tools” the only ones that met LockMart’s requirements. That kind of technology certainly would justify a sole-source subcontract award. But we are skeptical that would have been the case. In fact, we bet that more than one company in the USA offered such perishable tools, and would have been willing to submit bids on the subcontract, had LockMart opened up the opportunity to competition.

The story reported that the government was “accusing the firm of contributing to the inflated amounts paid by the government by failing to adequately oversee TMI’s charging practices and by mishandling information revealing these practices.” Thus, according to the story, it was not so much a matter of inappropriately awarding the subcontract, as it was a matter of failing to ensure that TMI was submitting accurate invoices. We have reported on DCAA’s concerns with similar matters before. In that article, we quoted DCAA Director Pat Fitzgerald as follows—

During our review of prime contractor billings and incurred cost audits, DCAA has identified situations where the prime contractor has not awarded its fixed-price subcontracts based on fair and reasonable prices leading to unreasonable or unallowable costs being paid by the Government. … in those cases where the subcontract is sole source, it is often difficult to obtain cost data to ascertain the reasonable costs without access to the subcontractor’s books and records. DCAA access to subcontractor books and records is generally limited and dependent on the flow down by prime contractor to the subcontractor of the appropriate FAR clauses, and in instances of fixed price subcontracts, virtually nonexistent. … Since DCAA does not have access to the subcontractor’s books and records, we were unable to determine through other processes the reasonableness of the prices being paid to the subcontractor and subsequently passed on to the Government for reimbursement. … The FAR audit access clause does not provide for Government access to the subcontractor’s costs records when the subcontract is firm-fixed-price.

Because DCAA was not able to verify the “reasonableness” of the subcontractors’ prices, they questioned the entire amount paid to the subcontractor as being “unreasonable.”

Now, we are not saying that LockMart’s situation with TMI is the same as the one that Mr. Fitzgerald reported to the Commission on Wartime Contracting back in July 2010, but we don’t think it’s too dissimilar either. In both cases, the Prime contractor was held responsible for proving adequate oversight of its subcontractors. That oversight responsibility was considered to encompass more than just technical performance; it was also considered to encompass monitoring the accuracy and appropriateness of the original negotiated prices as well as the accuracy and appropriateness of invoices.

Lockheed Martin settled and it’s unclear why the company chose to do so. Clearly, there’s more to the story than was reported in the media.

The lesson here, if one can be taken from such scanty information, is that Primes need to focus on subcontractor management. (Long-time readers may recall that this is a familiar theme on this blog.) More importantly, Primes need to perform sufficient due diligence to ensure the appropriateness of the initial subcontract award pricing, and to perform some limited audits/reviews of subcontractor invoices. In this particular case, we would start with trying to gain an understanding as to why a sole-source subcontract award was thought to be justified and how pricing reasonableness was established.

 

 

Government Loses Yet Another Statute of Limitations Case

E-mail Print PDF

insanity-einstein_22
In December, 2009, we reported to our readers that McDonnell Douglas (Boeing) had won a victory in a defective pricing dispute, because the government failed to assert its claim within the Contract Dispute Act’s six-year statute of limitations. In that ASBCA case, it took DCAA more than 3 years to complete its post-award audit of McDonnell Douglas’ subcontractor and to issue its draft report to DCMA. It took another fourteen months for DCMA to send a letter to Boeing, “seeking comments” on the matter in order to finalize the audit report. (The final audit report was issued about a month later—nearly 52 months after DCAA commenced its audit.

It took another six years for the cognizant DCMA Contracting Officer to issue a final decision.

The ASBCA was quick to find for Boeing. The Judge wrote—

Because the government’s defective pricing claim upon which the COs’ decisions were based is time-barred and not cognizable under the CDA, the COs’ decisions asserting the claim were not valid. If there is no valid CDA claim, any purported CO’s decision on the matter is a nullity and we do not have jurisdiction to entertain an appeal from the purported decision.

In January, 2012, we reported to our readers that Boeing had won another victory at the ASBCA. In that dispute, which concerned a disclosed change in cost accounting practice, Boeing submitted a revised Disclosure Statement in October 2000. DCAA issued an audit report concerned the cost impact associated with the change in June 2002. In September, 2003, the cognizant ACO began negotiations with Boeing. Between December 2003 and April 2005, the parties attempted to resolve the dispute through negotiation. The parties continued to discuss the matter “intermittently” until 2010. Ultimately, negotiations proved unsuccessful and, in October, 2010, the ACO issued a Final Decision—and Boeing appealed that Final Decision to the ASBCA.

The Judge wrote—

Because the government's 25 October 2010 final decision claiming the accounting revision costs was untimely, it is not valid. Given that it is invalid, it is a nullity and we lack jurisdiction to entertain an appeal from it. Accordingly, we dismiss the appeal for lack of jurisdiction.

The maxim, “Insanity is doing the same thing over and over again, and expecting different results,” is generally attributed to Albert Einstein. A more reasonable litigant (or perhaps one who was spending his own money instead of the taxpayer’s money) might give up on the issue and stop litigating disputes that were over six years old. But not the U.S. Government. No, indeed. Instead, they keep litigating the same CDA statute of limitations issue over and over again, expecting different results.

In the latest defeat for the Government, the U.S. Court of Federal Claims threw out the case against Raytheon Company. The matter concerned an Advance Agreement between Raytheon and the Department of Defense, covering some retirement obligations the company had inherited in its acquisition of certain parts of Hughes Aircraft Company. The Advance Agreement was executed in 1999, and included a provision that made the allowability of retirement costs subject to DCAA audit. Raytheon claimed $106 million pursuant to that agreement, but in 2003 DCAA asserted that $4.75 million of that amount was unallowable. Raytheon shrugged and credited the Government for the allegedly unallowable amount. And that’s where the parties stood until 2007.

In 2007, the DOD Inspector General issued a report that criticized the 2003 DCAA audit. In response, DCAA issued a “supplemental report” in August 2008—asserting in that second report that $25 million of Raytheon’s costs were unallowable. In December 2008, the cognizant DCMA Contracting Officer issued a Final Decision. Raytheon filed suit.

Raytheon sued for a “declaratory judgment” that the Contracting Officer’s Final Decision was “void and of no effect.” The COFC decision was quite short, as these things go. It was eight pages long. Although the Court discussed a number of Government theories, they were not persuasive. The Judges wrote—

Defendant had been aware of all the information on which it based the $25 million government claim for nine years before the contracting officer issued his decision in 2008. The decision conflicted dramatically with results of the first audit, issued in 2004, which used information identical to that employed by the second set of auditors in 2007. The only event occurring after defendant signed the Advance Agreement in 1999, and before the 2008 contracting officer’s final decision, was the Inspector General’s report criticizing DCAA’s $5 million first audit.

The $25 million government claim in this proceeding is barred by the Contract Disputes Act’s six-year statute of limitations. Plaintiff’s motion for judgment declaring that the contracting officer issued his final decision beyond the statute of limitations of the Contract Disputes Act is GRANTED. All other pending motions are moot and therefore DENIED.

Boeing has won twice at the ASBCA; now Raytheon has won at the Court of Federal Claims. When will the Government get the message that the CDA’s statute of limitations will be strictly enforced by the Courts?

Or, perhaps, they will keep litigating the same issue over and over, expecting different results.

 

 

Should DCAA Be Disbanded? The Clock is Ticking …

E-mail Print PDF

“Should DCAA be disbanded?” This is a question we examine from time to time on this blog—the most recent example being this article. In the article, published about a year ago, we surveyed a number of commenters—some with more knowledge than others—and concluded with the following assessment:

So where does the DOD’s premier audit agency go from here? It has a growing backlog of unfinished audits, a demoralized workforce, and customers who are turning to outside audit firms (and paying more) in hopes of getting more timely audit reports. What should be done?

Look, we make our living dealing with DCAA auditors and helping contractors successfully pass DCAA audits. The status quo keeps us busy and puts money in our pockets. But in all intellectual honesty, we are forced to say, this agency needs to immediately turn a 90 degree course correction. If it can’t do that, then we think another agency needs to take its place.

Since then, we’ve been nibbling around the edges of the question, asserting from time to time that the new DOD Pricing Center has, as its primary goal, the objective of eliminating the need for DCMA Contracting Officers to rely on DCAA “forwarding pricing” audits. We think—and we’ve heard our supposition confirmed by senior DCMA leadership in so many words (without anybody expressly saying so)—that DCMA wants to be able to evaluate and negotiate contractors' cost proposals and forward pricing rate proposals without DCAA’s involvement.

We told our readers about Section 805 of the FY2012 National Defense Authorization Act, which requires the DCAA Director to submit a (new) annual report to Congress. That new report will contain a considerable amount of metrics and statistics, the kind of stuff that we subsequently opined “could be very useful for those assessing DCAA’s management direction.”

We also spent considerable word count acquainting readers with the recent report issued by the House Armed Service Committee’s Panel on Business Challenges within the Defense Industry. That report contained quite a few recommendations based on input from a number of sources (including defense contractors themselves). Many of the recommendations seemed designed to address perceived DCAA and DCMA shortcomings. For example—

  • Congress should direct the Secretary of Defense to increase oversight of the management, functionality, and operations of DCAA and DCMA to reduce the backlog of audits, and to improve the audit agencies’ relationship with the industrial base.

  • Congress should direct the Secretary of Defense to examine the Department’s organizational structure and assess the feasibility and advisability of reorganizing the Department to realign DCAA and DCMA to improve communications, audit performance, oversight, and management.

That’s pretty heady stuff. But perhaps the more telling recommendation is the following—

  • Congress should examine other alternatives, to include the establishment of a self-regulatory option, to providing auditing, accounting and advisory services regarding contracts and subcontracts and examine the feasibility of using such alternatives for the DIB to potentially reduce or eliminate many of DOD’s internal audit organizations while ensuring compliance with statutory, regulatory, and contractual requirements.

But that’s not all. We have seen several other, related, articles and op-ed pieces that suggest policymakers are considering a significant restructuring to DCAA.

This National Defense Magazine blog reviews the HASC report and reports—

Burdensome regulations and arcane auditing requirements are driving many companies to quit the defense market, and are deterring new suppliers, the report said. As a result, the panel will be asking the Pentagon to study options for outsourcing auditing responsibilities to independent agencies. …

The auditing reforms that [Representatives] Shuster and Larsen propose are likely to spark controversy, as they are a radical departure from the way the Defense Contracts Auditing Agency does business. But Shuster said he believes a FINRA-like model — where a financial industry-funded agency is in charge of enforcing regulations — could be applied to defense in order to relieve an overstretched DCAA work force. This approach would still allow for high-level government has oversight, he said. An outside group can ‘do things more efficiently,” said Shuster. ‘We are going to have to study this.’

Larsen cautioned that outsourcing auditing functions does not mean backing off anti-fraud initiatives. But when he heard that a company four years ago spent three days tracking down $58 he knew something was wrong. ‘That’s the other extreme,’ he said. ‘Perhaps there’s a happy medium.’ …

The defense contracting and auditing environment is as bad or worse than it was 10 years ago, said Shuster. ‘Program managers are more risk-averse than they were 10 years ago,’ he said. ‘And I don’t know that we can legislate that.’

The foregoing blog is published by an defense-related industry association (the NDIA) and its anti-DCAA reportage might be discounted on that basis. But we found another source, the Center for American Progress, whose progressive (and presumably liberal) credentials are above reproach. Here’s what they had to say about this issue—

Three years ago, as many as 30,000 audits of government contracts a year were conducted annually. That number has now plunged to 10,000 audits per year despite the fact that the dollar value of contracts issued has remained steady. The time taken to check up on proposed prices before a contract is awarded now stands at 72 days, up from 28 days only two years ago. …

DCAA responded to [GAO’s] criticisms by emphasizing additional work documentation, but now questions are being raised if the agency isn’t placing too much emphasis on following questionable practices that add little to the quality of audits, to the detriment of conducting hard hitting audits. ‘In a time of scarce government resources and an inadequate contracting workforce, the government must evaluate where it is most vulnerable and focus resources where they can most effectively protect taxpayer dollars,’ said Sen. Claire McCaskill (D-MO) at a recent congressional hearing on fixing the existing auditing system.

In response to the critical GAO report and Congressional hearings, the Defense Contract Audit Agency has attempted difficult shifts in its bureaucratic culture over the past three years. However, many believe that these changes have not been for the better, but have actually lessened oversight of government contractors. In particular, DCAA now seems to be focusing on fewer contracts, and this is clearly not good enough.

The foregoing was essentially a preface to the report on DCAA issued by the Center. The report “profile[s] the different reasons audits by the Defense Contract Audit Agency sometimes fail, and what’s been done to correct these failures in the past.” One of the recommendations contained in the report is to “evaluat[e] whether the Defense Contract Audit Agency should report directly to Congress rather than to the Pentagon as is presently the case.”

You can find the Center’s report right here. It contains little that’s new, but does provide some fascinating behind-the-scene details. For example—

Shortly before he retired, Bill Reed was fond of showing his staff a PowerPoint slide that claimed that the cost of a DCAA audit was $116.24 per hour in 2006 compared to the Big Four audit firms such as KPMG and Price Waterhouse, which billed an average of $162.81. But in reality, DCAA’s costs were lower for one simple reason—it had far fewer qualified auditors than the Big Four allowing it to pay lower salary costs. In 2011 Patrick Fitzgerald, the director of DCAA, estimated that just 28 percent of his staff were qualified CPA’s compared to a Big Four rate of closer to 50 percent.

The Defense Contract Audit Agency is also unusual in that many of its managers and supervisors are not qualified CPAs, yet they are required to sign off on audits, a practice that would be illegal in the commercial world. This practice has caused dissent in the ranks of the staff that are qualified to sign off on audits in public practice but prohibited at the agency, sending a signal that loyalty was promoted over competence.

‘By permitting non-CPAs to manage CPAs in audit work, DCAA culture has turned the established auditing profession on its head,’ a 20-year veteran of DCAA in northern California says. ‘It is the equivalent of a novice directing a journeyman on how to build a house or conduct any other trade or profession that has developed and refined its purposes and standards over the centuries.’ He estimated that in one year audits of $2.8 billion of the $4 billion were put under the responsibility of non-CPAs supervisors at the Peninsula branch office just south of San Francisco.

The report concludes—

Three years ago the Defense Contract Audit Agency came under fire for an obsession with getting through too many audits, too quickly. ‘We’re talking about serious sirens, bells and whistles all going off at the same time,’ said Sen. McCaskill at a 2008 hearing in Congress. ‘I think the system is failing. The culture is broken, the performance metrics are broken, and the oversight is broken.’

Today the opposite is true—contractors are now complaining about the auditors taking too long to determine prices. It is clear that the federal government needs more professionally qualified auditors to get the job done. ‘DCAA cannot always accommodate non-Department of Defense requests for audit support,’ said Thomas Skelly, the director of budget services at the U.S. Department of Education, in a recent congressional testimony. ‘Obtaining audit support from a non-governmental firm can be costly and time-consuming.’

While we do not agree with all (or even with many) of the report’s recommendations, we think it supports our assertion that DCAA is coming under scrutiny from many diverse stakeholders. We think it supports our assertion that DCAA is moving into the cross-hairs of a number of powerful parties, who may well seek to significantly restructure or even eliminate the audit agency altogether.

As if to reiterate and strengthen our assertions, Government Executive published this story on the testimony of Pratap Chatterjee (the author of the Center’s report) before the Senate Homeland Security and Governmental Affairs Ad hoc Subcommittee on Contracting Oversight. The story quoted Chatterjee’s testimony as follows—

Additionally, Chatterjee said, because most contracts come from Defense, the Defense Contract Audit Agency handles the lion’s share of all federal contracting audits. Since DCAA is nestled within the Pentagon, it is unable to maintain proper independence when making decisions about the fiscal responsibility of military contractors, he said.

Chatterjee would instead like to see a new Federal Contract Audit Agency, which would reside outside the Pentagon, allowing it to maintain independence when attempting to recover taxpayer dollars contractors spent improperly. However, he did not formally recommend such an agency in his report.

We think we’ve made our point.

 

 


Page 184 of 278

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.