• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

Too Much Time on Their Hands

E-mail Print PDF
We had hardly finished typing the last article on timekeeping “challenges” and associated legal settlements when we learned that our old friend, the Department of Energy’s Hanford Site, had generated yet another legal settlement. The DoJ press release reported that—

Bechtel National Inc., Bechtel Corporation (Bechtel), AECOM Energy & Construction, Inc. (AECOM), and their subsidiary Waste Treatment Completion Company, LLC (WTCC), agreed to pay $57,750,000 to the U.S. Department of Justice (DOJ) to resolve claims that Bechtel and AECOM fraudulently overcharged the U.S. Department of Energy (DOE) in connection with its operation of the Hanford Waste Treatment Plant (WTP) project.

Yep, that was a nearly $58 million settlement.

The latest settlement is in addition to a 2016 settlement of $125 million, in which the DoJ reported

Bechtel National Inc., Bechtel Corp., URS Corp. (predecessor in interest to AECOM Global II LLC) and URS Energy and Construction Inc. (now known as AECOM Energy and Construction Inc.) have agreed to pay $125 million to resolve allegations under the False Claims Act that they made false statements and claims to the Department of Energy (DOE) by charging DOE for deficient nuclear quality materials, services, and testing that was provided at the Waste Treatment Plant (WTP) at DOE’s Hanford Site near Richland, Washington. The settlement also resolves allegations that Bechtel National Inc. and Bechtel Corp. improperly used federal contract funds to pay for a comprehensive, multi-year lobbying campaign of Congress and other federal officials for continued funding at the WTP.

So $58 + $125 = $183 million in WTP-related legal settlements, and that figure excludes such additional costs as unallowable legal fees and the time and expense of internal resources being focused on non-value-added activities such as defending themselves. That’s obviously a lot of money, and where does it come from? It comes from the corporate shareholders, of course. And at the same time, the Bechtel team received $5 million in award fees associated with its 2019 performance—“the best performance evaluation in three years,” according to this news article. We suspect that big award fee payout didn't make up for the costs of the legal challenges.

Anyway, back to the current settlement. This one is a bit harder to understand; it’s not black and white as most timekeeping “challenges” are. In this case, the government alleged that “Bechtel and AECOM management were aware of and failed to prevent inflated labor hours being charged to DOE, and for falsely billing DOE for work not actually performed.” But when you dig a bit deeper, those “inflated labor hours” and the “work not actually performed” were related to craft employees’ “idle time.”

Idle time is time spent not working. Often, it’s for legitimate reasons, such as waiting for paint to dry or for a weld to cure. Maybe somebody is waiting for an inspector to show up before moving on to the next operation. Most construction contractors (including shipbuilders) have some amount of idle time. It’s a known and accepted thing. Obviously, from a schedule management perspective it should be minimized, but there is really no way to get it to zero.

In this case, the government alleged that—

Between 2009 and 2019, Bechtel and AECOM admitted to overcharging DOE for unreasonable and unallowable idle time experienced by craft personnel. Bechtel and AECOM further admitted to failing to schedule and carry out adequate work to keep craft personnel sufficiently occupied and productive, resulting in excessive idle time. Bechtel and AECOM also admitted that Bechtel and AECOM management knew that craft personnel were experiencing idle time due to management’s failure to assign sufficient work, and that this idle time could, at times, last ‘several hours.’ Finally, Bechtel and AECOM admitted that they improperly billed DOE labor costs for the unreasonable idle time and continued doing so for years, even after Bechtel and AECOM knew they were under investigation for the improper billing practices.

Based on the foregoing, we can see that the basis of the allegations was that the cost of idle time was “unreasonable.” Costs that are unreasonable are unallowable. The concept of “reasonableness” is discussed in the FAR at 31.201-3. It’s a bit long-winded and nuanced; but it has to be, because it’s inherently a subjective standard. Despite the subjective nature of the evaluation, the FAR states that “no presumption of reasonableness shall be attached to the incurrence of costs by a contractor. If an initial review of the facts results in a challenge of a specific cost by the contracting officer or the contracting officer’s representative, the burden of proof shall be upon the contractor to establish that such cost is reasonable.”

Thus, when challenged, the burden was on the Bechtel team to show why the incurrence (and amount) of idle time was reasonable and normal for the type of project. Apparently, the Bechtel team couldn’t make a case for the idle time or else couldn’t show that they were actively trying to minimize it. Because the team couldn’t meet their burden of proof, the “unreasonable” idle time costs became unallowable labor costs, and the team was then on the hook for having invoiced unallowable costs to DOE, which led to the allegations that the False Claims Act was violated.

A critical point was that (allegedly) the Bechtel WTP team was on notice that the DOE considered the idle time costs to be unreasonable and unallowable, but kept billing the idle time anyway. The DoJ announcement quoted the DOE Inspector General as saying “[the Bechtel team] engaged in a massive scheme to submit tens of millions of dollars of false claims to the U.S. Government for unallowable and unjustified costs over a period of years – a pattern of conduct that continued even after U.S. authorities notified the defendants that these costs were unallowable.” There is a way to continue to claim disputed costs but, apparently, the Bechtel team didn’t follow it. (See FAR 31.201-6(b).)

In addition to the $58 million settlement, the DoJ reported that—

Bechtel and AECOM also entered into a 3-year independent corporate monitor agreement, which requires Bechtel and AECOM to pay for a full-time independent monitor and assistant monitor selected by the USAO. These monitors will enjoy broad access to Bechtel’s and AECOM’s systems, meetings, personnel, and other information pertaining to labor charging. The monitors will also report directly to the United States. Bechtel and AECOM face additional liquidated damages of up to $10 million if they violate the terms of the monitoring agreement, provide false information, or fail to immediately correct any identified DOE contract issues.

As with many False Claims Act settlements, this one started with qui tam relators filing suit on behalf of the U.S. Government. In this particular matter, the four relators will split $13,750,000—which is about 23 percent of the total amount of the Bechtel team’s settlement.

 

 

Another Timekeeping Issue

E-mail Print PDF

Charge what you work; work what you charge.

If you follow that simple piece of government contracting folk wisdom, it’s tough to get into too much trouble.

Still, too many contractors end up the subject of Department of Justice press releases, announcing multi-million-dollar settlements related to timekeeping “challenges” and related issues.

Recently, the DCAA published a notice of SAIC’s nearly $6 million settlement with DoJ. That published report was a bit of “old news,” as the DoJ published its settlement announcement in June, roughly three months ago. What was the deal?

According to the DoJ announcement—

The United States contended that SAIC employees misused administrative leave by working on contract requirements for a certain project before funding was available and then later clearing those charges by adding extra billing hours that were not worked to a separate project. The United States also contended that SAIC employees were provided charge codes for their hours to be recorded to projects with available funding, while they continued to work on tasks that were not funded. Once the new funding arrived, the employees working on a project that provided the original funding would then charge their hours to the new project.

People who know SAIC and its commitment to internal controls were a bit shocked at the news. There was a decent discussion thread on LinkedIn by those who wondered what went wrong. SAIC, of course, used to be headquartered in San Diego, but now calls Reston, Virginia, home.

More recently, another San Diego entity settled with the DoJ for its own timekeeping “challenges.” According to this DoJ press release, The Scripps Research Institute (TSRI), located in LaJolla, California, agreed to settle false claims allegations by paying $10 million. According to the announcement—

The settlement resolves allegations that between 2008 and 2016, TSRI failed to have a system in place for its faculty to properly account for time spent on activities that cannot be charged directly to NIH-funded projects or are unrelated to the research activities of the NIH-funded project. Consequently, the U.S. contended that TSRI improperly charged time spent by faculty on developing, preparing, and writing new grant applications directly to existing NIH-funded projects, rather than allocating such charges as indirect costs. The U.S. also alleged that TSRI improperly charged NIH-funded projects for time spent by its faculty on other activities unrelated to the funded projects, such as teaching, TSRI committee work, and other administrative tasks.

Let’s unpack paragraph a little bit.

The government alleged that TSRI permitted its faculty to charge non-project efforts to NIH-funded projects. Those non-project efforts included:

  • Efforts to prepare new grant applications (equivalent to Bid & Proposal efforts)

  • Time spent teaching classes

  • Time spent attending committee meetings

  • Time spent on other (non-project) administrative tasks

If the allegations were true, then TSRI had challenges in helping its faculty determine the difference between “direct” and “indirect” time. Direct time, of course, is the time spent on project activities; whereas, indirect time is the time spent on everything else that is not a project activity.

Title 2 of the Code of Federal Regulations, Chapter 200, discusses the cost principles applicable to educational institutions such as TSRI. 2 CFR § 200.413 (Direct costs) states—

Direct costs are those costs that can be identified specifically with a particular final cost objective, such as a Federal award, or other internally or externally funded activity, or that can be directly assigned to such activities relatively easily with a high degree of accuracy. … Identification with the Federal award rather than the nature of the goods and services involved is the determining factor in distinguishing direct from indirect (F&A) costs of Federal awards.

Obviously, TSRI had challenges in complying with the requirements/guidance quoted above. One would think a contractor (or grant recipient) would have the whole direct versus indirect thing figured out before submitting the first proposal. Moreover, it would appear that timekeeping training was lacking as well. Faculty should have received training in how to distinguish direct from indirect labor. If they had questions, TSRI should have provided a help line for them to call.

Now, perhaps TSRI did all that. We don’t know.

But what we do know is that TSRI, a non-for-profit educational institution, just paid out $10 million to resolve allegations related to its timekeeping “challenges.”

One more thing: As with so many other DoJ settlements, this one started with a qui tam suit filed by a former employee. The DoJ press release notes that the qui tam relator will receive $1.75 million (17.5%) of the settlement. As we recently noted, there is evidence showing that contractors with active hotlines or emails see reduced legal settlements. We have also observed that companies with internal reporting mechanism offer their employees a means of reporting concerns or suspected wrongdoing without having to file a lawsuit.

The continuing reportage of legal settlements related to mischarging of labor makes us think that every government contractor should think about these things.

 

Reasonableness in Claims and REAs

E-mail Print PDF

Recently Judge Dyk and the Court of Appeals, Federal Circuit, issued an opinion that resulted in another contractor loss. This is another Dyk ruling in a long string of questionable rulings against contractor appeals. There is temptation to categorize the Dyk rulings as the result of bias against contractors. But we’re not qualified to judge the quality of the rulings, as we are not attorneys, so thus will refrain from casting further stones at the Honorable Judge Dyk.

As we are not attorneys, you should perhaps rely on qualified legal advice to help you navigate the challenges created by the decision, which set a “new and undefined reasonableness standard” that contractors submitting claims and Requests for Equitable Adjustment (REAs) now apparently have to meet.

Short summary of the appeal: contractor Kellogg, Brown & Root (KBR) had a LOGCAP contract, under which it was awarded a CPFF Task Order to provide temporary housing trailers to soldiers and coalition forces at various locations in Iraq. (There was a war at the time. Some would argue there still is.) Under that Task Order, KBR issued a Firm, Fixed-Price subcontract for about 4,000 trailers to First Kuwaiti Company of Kuwait (“First Kuwaiti”). Those trailers were to be manufactured in Kuwait and then transported via convoy to a couple of Iraqi locations. Delays occurred because the US Government breached the contract by failing to provide adequate force protection to the convoys. (See Sec’y of the Army v. Kellogg Brown & Root Servs., Inc., 779 F. App’x 716, 718 (Fed. Cir. 2019). We wrote about the dispute here.)

Pursuant to the Changes clause in its subcontract, First Kuwaiti submitted an REA to KBR and the parties eventually negotiated an upward price adjustment of $48.7545 million to its FFP subcontract. KBR then paid First Kuwaiti and billed the FFP value through its prime contract Task Order (which was, remember, CPFF). The contracting officer disallowed all but $3.8 million of the additional costs. KBR appealed to the ASBCA, where the Board found against KBR on various bases, including (1) the government didn’t breach the contract, and (2) even if the government did breach the contract, KBR had failed to show that the REA settlement amount it had paid First Kuwaiti was reasonable.

In the words of the Federal Circuit—

The Board stated that KBR had failed to provide the actual costs incurred by Kuwaiti, as is typical in claims for equitable adjustments in other contracts. Instead, KBR’s claimed costs were based solely on Kuwaiti’s estimates. The Board found that the damages models were ‘unrealistic,’ ‘inconsistent,’ ‘flaw[ed],’ ‘unreasonable’ and assumed a ‘perfect world.’ The Board concluded that ‘KBR [was] not entitled to any recovery.’

The Federal Circuit affirmed the ASBCA’s decision, which upheld the contracting officer’s decision and cost KBR about $45 million.

In its opinion, the Federal Circuit did not agree with the ASBCA’s finding that KBR was required to have submitted to the contracting officer actual costs incurred by First Kuwaiti. Judge Dyk wrote “As the government conceded at oral argument, the amounts paid by KBR to Kuwaiti were ‘costs’ under the prime contract, and there is no provision in the prime contract that required KBR to submit the actual costs incurred by its subcontractor. KBR’s obligation was to show that the payments to Kuwaiti were ‘reasonable.’” So far, so good.

However, the Judge also noted that “the failure to collect and submit Kuwaiti’s costs bears on the reasonableness of the payments” that KBR made to First Kuwaiti. That issue became the fatal flaw in KBR’s claim.

The methodology used by KBR and First Kuwaiti was based on quantification of the number of delay days times a fixed price per day. The problem with this methodology, according to the Federal Circuit, was that KBR made several unrealistic assumptions, chief of which was the assumption that any delays were caused solely by the lack of force protection. As Judge Dyk wrote:

Third, KBR’s spreadsheets calculating idle truck days, ‘without substantiating data or records,’ were insufficient to establish the reasonableness of its costs. KBR offered no fact or expert witnesses to support the reasonableness of its estimated number of idle truck days. Although Change 5 did not require KBR to provide actual costs to support its claim, the Board properly determined that KBR’s failure to provide any supporting data was fatal to its claim. Under KBR’s contract with Kuwaiti, Kuwaiti was obligated to ‘maintain books and records’ reflecting actual costs, and KBR had the right to ‘inspect and audit’ those records. As the Board found, it was simply not plausible that Kuwaiti did not record ‘how long trucks actually waited’ at the border … and KBR made no attempt to access or utilize these records. At bare minimum, KBR was required to support its estimates with representative data as to the number of trucks actually delayed. In fact, KBR supplied no representative data whatsoever. Without further evidence demonstrating the reliability of KBR’s estimates, the Board properly found that KBR’s claimed costs were not reasonable.

So KBR is out roughly $45 million, unless it decides to proceed further. But we’re not done yet. There was a dissent filed by Judge Newman that’s worth a bit of discussion.

Judge Newman concurred with the basic reasoning of the majority, but believed that the appeal should have been remanded back to ASBCA in order to determine whether or not the negotiated REA was reasonable. She wrote “My colleagues hold that the correct standard is ‘reasonableness,’ and while complaining about the absence of evidence and witnesses and argument on this standard, my colleagues make extensive findings on information that has not been presented, and decide the issue of reasonableness without participation of the parties.” She further wrote—

I also agree that the correct standard is ‘reasonableness.’ However, my colleagues do not remand for application by the ASBCA of this standard; they do not discuss whether the methodology used by KBR was reasonable, although this aspect was the subject of testimony at the ASBCA; and they do not consider whether any of the costs of delay were reasonable in the circumstances that existed. Instead, my colleagues extract isolated costs from un-briefed documents, and rule, with no briefing and no argument, that reasonableness was not shown. Although KBR requested remand to the ASBCA if this court agrees that the ASBCA’s decision should be reversed, remand is not provided. KBR has no opportunity to meet this court’s new standard. Instead, my colleagues scavenge among assorted materials that were provided in other contexts, and complain about the absence of evidence and expert testimony related to the court’s new standard.

Okay. So what have we learned here?

We have learned that it’s not simply enough to negotiate a subcontractor REA or claim and then submit the payment to the government for reimbursement. Instead, prime contractors (or, potentially, higher-tier subcontractors) need to thoroughly review the basis for the subcontractor’s REA or claim, including requesting and reviewing actual costs incurred. In this case, according to the Courts, even though Kuwaiti’s subcontract was FFP, it included language requiring Kuwaiti to maintain books and records reflecting actual costs incurred—and thus KBR should have looked at those books and records before choosing a quantification strategy that ignored them.

Now this is not the first time we’ve written about subcontractor cost reasonableness. Far from it. For example, in 2012 we devoted a three-part article to subcontractor cost reasonableness. That article (link to first post) discussed yet another KBR legal decision that cost the company roughly $30 million in subcontractor payments.

Are you getting the picture that subcontractor cost reasonableness is a big deal? Because if so, then we’re doing our job here.

It’s important to show a contracting officer that you, as a prime contractor (or higher-tier subcontractor) approached evaluating and negotiating your subcontractors’ REAs and claims in a reasonable manner. The FAR defines “reasonableness” at 31.201-3. It’s not a “bright line” definition, because “what is reasonable depends upon a variety of considerations and circumstances ….” However, the concept of reasonableness generally is summed up as “A cost is reasonable if, in its nature and amount, it does not exceed that which would be incurred by a prudent person in the conduct of competitive business.” Thus, you have to show that your actions and course of dealing are those of a prudent businessperson. In this case, both the ASBCA and the Federal Circuit found that KBR’s actions and course of dealings did not meet that standard.

This concept is also important for contractors evaluating supplier and other subcontractor claims for COVID-19 related costs, such as CARES Act Section 3610 stand-by labor costs. In fact, there may be a good analogy between your subcontractor’s REA (or claim) for Section 3610 stand-by labor costs and the REA submitted by First Kuwaiti to KBR for the truck driver labor associated with delayed convoys. In the case of First Kuwaiti, the Courts expected KBR to thoroughly review First Kuwaiti’s books and records to evaluate whether the additional costs it was claiming were actually reflective of the costs it had incurred. If the analogy holds true, then we would expect prime contractors receiving Section 3610 REAs to make the subcontractors support those REAs with actual cost reports.

There are going to be subcontractors who either cannot or will not support their REAs. They may have inadequate accounting systems. Or they may assert that they will not provide cost information to a potential competitor. There are going to be challenges in reviewing subcontractor Section 3610 REAs under the standard established by the Federal Circuit in this recent KBR opinion. Prime contractors simply are going to have to overcome them.

As we’ve written before, we expect a number of Section 3610 REAs to become claims, which will ultimately be appealed. This Federal Circuit decision established the standard for how prime contractors’ handling of their subcontractors’ REAs will be judged.

You ignore it at your own peril.

 

Fighting Corruption

E-mail Print PDF

How do you measure the [ethical] strength of [a] corporate culture?” – Eric Feldman

You can go back on this blog for more than 10 years now. As of this writing, there are 1,326 individual blog articles. Some are short and pithy; others long-winded. In any case, that’s a lot of words. Conservatively estimated, it’s more than a million words.

Did they matter? That’s not for us to say.

But if you look at all the articles on procurement fraud and bribery and product substitution and timekeeping fraud and small business misrepresentation, you might get the sense that there is a hell of a lot of corruption in this world of public procurement. It’s always puzzled us that there are so many people and so many companies that think they are going to get away with something; obviously, some do, but so many others do not.

If there is one theme that permeates all the fraud-related articles it is this: companies that invest in internal controls designed to detect and/or prevent employee wrong-doing are making smart investments that have quantifiable returns, in terms of reduced litigation expenses.

We were reminded of this theme once again as we wrapped-up our annual compliance and ethics training, courtesy of the Society of Corporate Compliance & Ethics (SCCE).

In that training we were exposed to the 2020 Report to the Nations, recently published by the Association of Certified Fraud Examiners. It covered more than 2,500 instances of occupational fraud reported globally in 2018 and 2019. The Report supported what we have been long saying.

  • Across the globe, corruption (which includes offenses such as bribery, conflicts of interest, and extortion) was the most common fraud scheme, other than asset misappropriation (theft)

  • 43% of fraud was detected via tip; 33% of fraud was reported via hotline email or telephone account

  • The presence of anti-fraud controls is associated with lower losses and quicker detection

  • Median fraud losses at companies that had did not have hotlines were nearly double the median losses at those companies that did

As was explained during the training, the conclusions from the AFCE report are clear:

  • Internal controls pay for themselves

  • Hotlines work

  • Use of hotlines is a sign of an ethically healthy company

We also learned that Artificial Intelligence (AI) has advanced to the point where anybody who is not using it in anti-fraud activities is really missing a cheap and effective means of detecting anomalies. At this point, one can use AI to “risk-score” every single accounting transaction in an entity. Every expense report and every Accounts Payable transaction can be risk scored. Employee addresses in a vendor master file can be detected; indeed, employee addresses adjacent to a vendor’s address can be identified. Vendors can be compared to one another: all suppliers of the same commodity can be compared to see if any stick out in terms of average payment size or frequency of payments. If a supplier sticks out, that supplier can be correlated with the buyer to see what’s going on. At this point, there is really no excuse for failing to deploy AI in anti-fraud activities.

This article is not the first time we’ve mentioned some of these ideas, but it’s the first time the return on investment of internal controls has been so clearly shown.

And it’s becoming more important than ever to be focused on detecting instances of corruption. The Association of Certified Fraud Examiners also recently published another benchmarking report: “Fraud in the Wake of COVID-19.” The ACFE received 1,851 survey responses. According to that report:

  • As of May, 2020, 68% of respondents “had already experienced or observed an increase in fraud levels, with one-quarter saying the observed increase had been significant.”

  • “Frauds perpetrated by vendors and sellers … are also a top risk … 86% of respondents expect to see more of this type of fraud over the coming year, and 68% have already seen an increase in these schemes.”

  • Ten percent of respondents “expected a reduction in their anti-fraud staffing over the next year” and eight percent “anticipate budget cuts to affect their anti-fraud programs and initiatives.”

It seems that one impact from the COVID-19 crisis is an increased in perceived fraud risk and a potential decrease in corporate resources used to detect/prevent fraud. That’s not good.

At a macro level, the U.S. Government is gearing up to fight COVID-19 related fraud. At a recent webinar presented by Ernst & Young, we learned that the CARES Act created three separate oversight bodies: (1) The Pandemic Response Accountability Committee (PRAC), (2) the Congressional Oversight Commission, and (3) The Special Inspector General for Pandemic Recovery (SIGPR). At least two of those three oversight bodies have both civil and criminal referral authority to the Department of Justice. According to EY, “SIGPR has entered into Memorandums of Understanding with the U.S. Attorney’s Offices of Massachusetts and Eastern Virginia to investigate and prosecute fraud related to CARES Act funds such as loans, loan guarantees and other investments.”

EY also reported that, at a June 2020 speech, the Principal Deputy Assistant U.S. Attorney General told the audience that—

  • The DOJ’s Civil Division will energetically use every enforcement tool available to prevent wrongdoers from exploiting the COVID-19 crisis.

  • The division will use the False Claims Act to prosecute fraud related to the Paycheck Protection Program (PPP), the Main Street Lending Program and other programs.

Let’s wrap this up: the corruption risk environment is increasing, anti-fraud resources may be at risk, and the U.S. Government is gearing up for intense scrutiny. We know that anti-fraud internal controls pay for themselves. In particular, we know that hotlines work, and that companies that have healthy avenues for employee referrals should expect to have reduced losses and reduced legal settlements.

Given all that, we have to ask you to reflect upon your company’s dedication to fighting corruption. Is it a priority? If not, should it be?

 

The Unconscious Bias

E-mail Print PDF

NCRNo, this is not going to be a political polemic, unless you choose to see it that way. No mention of political parties shall be made, nor shall there be made mention of any shades of the spectrum of political beliefs. However, we will discuss a noticeable bias—a prejudice if you will—against the West Coast.

There is no question that, in the rather arcane world that is government contracting, the center of gravity is Washington, D.C. The National Capital Region—i.e., the District of Columbia and surrounding environs—is home to hundreds of defense contractors, ranging from General Dynamics to Lockheed Martin to Northrop Grumman, and including lots and lots of smaller names. Even companies that aren’t headquartered in the area have large offices there. “The Washington Office” is a familiar phrase for many government contractors, evoking images of “government relations” experts and martini-fed power lunches with Congressional staffers.

The top-ranked government contracting law firms all have offices in the Region, as does nearly every top-ranked government contracts consulting firm. There’s a reason many of those firms are called “Beltway Bandits.”

You can’t throw a rock in Arlington or Tyson’s Corner without hitting somebody who is involved in some aspect of government contracting.

Why is that? Well, obviously it’s because that’s where the seat of the Federal government is. That’s where Congress is. That’s where most Cabinet-level agencies are found. That’s where the Pentagon is. The coalescence of government contracting power in the National Capital Region is extraordinary.

There is no question that Washington, D.C., and its surrounding counties is the center of gravity. However, those within that sphere of influence seem to forget there’s a whole country outside The Beltway. Whether they are aware of it or not, they are biased against those outside The Beltway—especially those of us on the West Coast.

Now, government contracting on the West Coast today is but a shadow of it once was. In the sixties and seventies, Los Angeles was the center of gravity for government contractors, home to corporate headquarters for Northrop, Lockheed, Hughes Aircraft, TRW, and others. The Los Angeles Air Force Base was huge. And it wasn’t just Los Angeles: before there was Silicon Valley there was the Lockheed Missiles and Space Company, located in Sunnyvale, CA. Aerojet was located in Sacramento. Down in San Diego, there was General Dynamics’ Convair Division (home of the Atlas-Centaur rocket) and Ryan Aeronautical (later Teledyne Ryan, and home of early unmanned aerial vehicles that subsequently evolved into the Global Hawk). Looking further north, Seattle was famously the home of The Boeing Aircraft Company.

Those were the days. But now most of the leadership has moved east. Hughes Aircraft was split up. TRW was acquired. Northrop and Lockheed moved to within spitting distance of the Pentagon. Even Boeing moved to Chicago. The addition of innovators such as SpaceX has not significantly reversed the trend. The West Coast just isn’t the same, with respect to government contracting.

But West Coast government contracting is not dead.

Headquarters may have moved, but the programs and the people who work them didn’t. Thousands and thousands of government contractor employees still work in Los Angeles and San Diego and Sunnyvale and Seattle. And with them are thousands of government employees, from contracting officers to program managers to auditors. It’s surely not the same, but it ain’t over either.

But you wouldn’t know that from the way certain organizations are acting.

Recently, I’ve participated–or tried to participate–in several association meetings and prominent training seminars. Many of them—perhaps most of them—act as if nobody from the West Coast will want to participate. Many have starting times that are ridiculously early for those who set their clocks on Pacific Time.

Let me provide you with some recent examples:

  • The recent American Conference Institute’s Advance Forum on DCAA & DCMA Costs, Pricing, Compliance and Audits started at 9 AM Eastern. As speaker, I had to be ready (and online) by NLT 5:30 AM Pacific Time.

  • The upcoming National Defense Industrial Association’s October Procurement Committee Meeting starts at 9 AM Eastern.

  • A recent all-day national educational seminar started at 7 AM Central.

And those are just a few examples of the curious phenomenon where people putting on those meetings and seminars seem completely unaware that anybody from the West Coast might want to participate.

In fairness, perhaps there just aren’t that many potential participants from the West Coast. It’s certainly possible that if the meeting time was moved, then it might not impact overall attendance. For example, starting at 11 AM Eastern instead of 9 AM Eastern might inconvenience some local members without noticeably attracting West Coast folks. That’s certainly a possibility.

Another possibility is that the times were set before COVID-19 made in-person participation unlikely. It may be that the times were set and it was too much trouble to change them just because the meeting or seminar went virtual. That’s certainly another possibility.

But we know this to be true. The most certain way of ensuring that the National Capital Region maintains its center of gravity, the most certain way of continuing to erode the government contracting expertise on the West Coast, is to continue to make it inconvenient to join in continuing professional education and networking opportunities that are seemingly taken for granted by those in Washington, D.C.

There is no longer any valid reason for starting at 9 AM Eastern, assuming there ever was. It’s time to make a change. (Pun intended.)

As we move towards a virtual training environment where people might conceivably log-in from anywhere, does it still make sense to maintain this biased attitude that believes nobody outside of The Beltway matters?

We think not.

 


Page 16 of 278

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.