DCAA Finds New Ways to Reduce its Audit Backlog
 In September, 2012, the Defense Contract Audit Agency (DCAA) announced a fundamental change to its approach to auditing contractors’ proposals to establish final billing rates (also known as “incurred cost submissions”). We discussed the new, “risk-based,” approach in some detail.
A fundamental aspect of the new approach was the bucketing of contractors’’ proposals into either “low risk” or “high risk” categories. In order to be classified as a “low risk” proposal, several criteria must have been met. For example, DCAA must have performed at least one full-scope incurred cost audit on the contractor in the past. The contractor must have no inadequate business systems with deficiencies that might have a “significant impact” on the contractor’s ability to calculate an adequate proposal. And—perhaps most importantly—the previous DCAA audit must not have questioned a significant amount of claimed costs.
The September, 2012, DCAA audit guidance included a table that defined “significant exception dollars” in terms of strata based on the contractor’s proposed “auditable dollar value” (ADV). For example, if the contractor’s proposed ADV was between $15 and $50 Million, total questioned costs needed to have been less than $55,000. Anything more and the contractor’s current final billing rate proposal could not be classified as being “low risk”. For a proposal with an ADV between $50 to $250 Million, total questioned costs needed to have been less than $100,000. (Proposals with an ADV greater than $250 Million could never be classified as being low risk.)
The beauty of falling into the “low risk” bucket is that it greatly decreased your chance of DCAA actually performing an audit of your claimed costs. Again, the probability associated with a contractor’s proposal being audited was based on ADV strata. For example, if you were found to be low-risk, and your proposed ADV was between $50 and $100 Million, then there was only a 10% chance your proposal would be audited. Conversely, there was a 90% chance your proposal would never be audited and you would be able to finalize billing rates that were equal to your proposed final billing rates. DCAA would simply send a Memo to the cognizant ACO, and that would end the audit agency’s involvement in the process.
We know several, smaller, contractors who’ve already experienced that happy result. They’ve finalized rates and never had to go through an audit. Lucky them.
The reason for the change in audit approach, as our readers know all too well, is that DCAA wasn’t getting its job done. The backlog of unaudited contractor final billing rate proposals was growing and growing and growing, and so was the backlog of physically completed contracts awaiting closeout. DCAA’s implementation of audit milestone tracking and “streamlined” report reviews have not noticeably reduced the time it takes the agency to perform an ICS audit, which (at last report) was roughly four years per contractor proposal. Instead of reducing audit backlog through implementation of efficiency initiatives, DCAA reported that its backlog of ICS proposals actually increased over the past Government Fiscal Year.
While DCAA has kept to its key talking point that all will be well by the end of GFY 2016, the agency’s Director has also quietly admitted that DCAA ““has frozen hiring and will lose about 5 percent of its workforce, or 250 employees, this year.” That situation is not going to help DCAA catch up any time soon.
DOD’s answer to the intractable problem of the growing backlog of final billing rate proposals to be audited? Stop auditing so many submissions.
The not-so-hidden flaw in this cunning plan, as we told our readers in our original article discussing the new approach (first link above), was that the number of “low risk” submissions that met the criteria was going to be much lower than DOD leadership thought. We wrote—
… we think the number of contractor final indirect billing rate proposals that will actually be classified as ‘low risk’ is likely to be relatively low. The criteria DCAA has established for assessing a submission as ‘low risk’ are actually going to be tough for many companies to meet. For example, former DCAA Director Stephenson once testified that as many as two-thirds of contractor business systems were inadequate. If that testimony was accurate, then none of those contractors will have their final billing rate proposals assessed as being ‘low risk’ by DCAA. Thus, we expect that many contractors will see their submissions targeted for audit, regardless of the size of their ADV.
And we were right about that, as Government Accountability Office (GAO) reported. We discussed that GAO report right here. Among our discussion points, we noted that GAO had found that DCAA’s initial assessment of contractor proposals had resulted in more than half the submissions being classified as high-risk, meaning that a full scope audit would be required. In contrast to reality, DCAA’s initial planning has assumed that only about 20 percent of submissions would be found to be high risk. And this was in relation to contractor proposals with ADVs of less than $15 million.
What went wrong? GAO reported that the problem was that too many of the contractors submitting final billing rate proposals had no incurred cost history—and thus (pursuant to its own risk criteria), DCAA could not find those proposals to be low-risk.
Not to be stopped by this unfortunate reality, DCAA has recently revamped its risk criteria so that more contractor proposals can be passed with minimal or no audit testing being performed. In the words of the new DCAA audit guidance—
Policy performed an analysis of audits completed in FY 2013 to determine if our incurred cost sampling process is working in the most efficient manner to apply our limited audit resources to the audit areas with the highest risk. … Based on this analysis, we found that there was room for improvement. Therefore, adjustments were made to the questioned cost thresholds and the sampling percentages. In addition, feedback from the field indicated that the current risk determination criteria requires revision to better allow auditors to use their professional judgment when determining if an adequate incurred cost proposal is high risk or low risk. Therefore, the risk determination criteria was modified, and the tools were updated to make it less of a checklist and more of a tool to assist the auditor in documenting the judgments they made in arriving at their final determination of high or low risk.
First, let us write (again) that we are in favor of more auditor professional judgment and discretion, and anything that introduces flexibility into the system is just fine by us. (Assuming of course that the auditors have appropriate experience and training so as to properly apply that professional judgment.)
Second, we don’t really care about the new criteria. We don’t really care that the “exception dollar” thresholds were raised so that more proposals can be found to be “low-risk”. That’s nice for DCAA. We don’t expect that very many contractors will be affected by the changes.
Third, it appears that DCAA may have backed off from the requirement that a previous full-scope ICS audit was required to be conducted before a contractor’s proposal could be determined to be “low-risk”. We may be reading between the lines a little bit, but we noticed that the revised audit guidance discusses “previous experience” with the contractor and does not expressly call out a full-scope ICS audit requirement. For example, the guidance says (for proposals with ADVs between $5 Million and $250 Million)—
For all proposals with $5 million - $250 million in ADV, consider the following significant risk criteria:
- Known significant fraud referral (Form 2000) applicable to the proposal fiscal year or the period in which the proposal was prepared
- Pre-award accounting system performed that resulted in an opinion of ‘unacceptable,’ or there are reported business system deficiencies relevant to the incurred cost year under audit
- No previous experience with the contractor such as voucher processing, forward pricing proposal, pre-award accounting system, etc.
- Specific relevant risk with the contractor that has material impact to the incurred cost proposal being assessed (i.e., significant CO/Auditor identified risk)
So it seems to us that DCAA has found a way to remove the key impediment to “risking-away” its backlog of contractor proposals to establish final billing rates. Instead of requiring a previous ICS audit, it now requires “previous experience” and has empowered the auditors to use their professional judgment to find that experience is relevant to the risk assessment.
If true, we expect that DCAA will be able to report good news to Congress in its next report. It will have significantly reduced its backlog of roughly 26,000 contractor final billing rate proposals awaiting audit. It will have accomplished this feat not be streamlining its procedures or redefining “GAGAS-compliant” audits. Instead, it will have reduced its backlog by finding innovative ways to classify proposals as being “low-risk” and, thus, avoiding the need to audit them.
NASA Proposes to Adopt DFARS Proposal Adequacy Checklist
We were dumbstruck to learn that the USPS OIG thought that the DFARS Estimating System adequacy criteria were “best practices” for designing an adequate estimating system. We were croggled to learn that DOE had decided to adopt the DFARS Business System compliance regime. We continue to believe that the DFARS business system adequacy criteria might be fine for a contracting environment that is willing to pay a nearly 20 percent price premium for such niceties, but that the criteria make little or no sense outside of such an environment.
What works for DOD should not be expected to work for civilian agencies—and there is considerable room for debate as to whether the Business System compliance regime actually works well for DOD. As we recently reported, the DOD Inspector General has expressed concerns with the ability of the Defense Contract Audit Agency (DCAA) auditors to conduct business system related audits in a timely fashion. Further, there is some question in our minds as to whether the adequacy criteria associated with Purchasing System adequately address taxpayer interests.
And now NASA has proposed to adopt the DFARS Proposal Adequacy checklist.
Why?
According to NASA rulemakers—
This proposed rule supports the NASA Assistant Administrator for Procurement's “Reducing Transaction Costs in NASA Procurements” initiative by incorporating the requirement for a proposal adequacy checklist into the NFS at 1815.408-70(c), and associated solicitation provision at NFS 1852.215-85, to ensure offerors take responsibility for submitting thorough, accurate, and complete proposals.
Yeah, sure it will. Forcing bidders to complete an onerous checklist is sure to reduce the overhead costs of those same contractors. Oh, wait! NASA doesn’t really care about the overhead costs of its contractors. Instead, NASA cares about “streamlining” its source selections so as to reduce “lead time.” Don’t believe us? Check this out.
Implementation of the DFARS Proposal Adequacy checklist will do neither.
NASA already has jumped on the DOD/DCAA bandwagon with respect to “risk-based” audits of contractors’ proposals to establish final billing rates (aka “incurred cost audits”). (See this memo.) And now the nation’s space agency wants to keep the momentum going by taking on the DOD/DCAA Proposal Adequacy checklist.
What do these two things—DFARS Proposal Adequacy checklist and acceptance of DCAA’s new approach to not auditing contractors’ claimed costs—have in common?
You guessed it: DCAA is what they have in common.
While DCMA is moving away from use of DCAA wherever it can, NASA seems to be cuddling closer and closer. Apparently NASA is so tied into use of DCAA that it is eager to adopt any initiative that DCAA proposes, regardless of whether the evidence supports a linkage between initiative and desired results. Pretty weird for a science-based agency, huh?
If you are a NASA contractor and want to submit comments regarding the proposed adoption of the DFARS Proposal Adequacy checklist, the link to the proposed rule (above) will tell you how to do so.
|
ASBCA Takes Hard Line on J.F. Taylor’s Request for Attorney Fees
 The original J.F. Taylor decision was a resounding victory for contractors who think DCAA has overreached in its attempts to find a basis for questioning compensation costs. We wrote about the decision right here. Judge Shackleford found that the unrebutted evidence showed that DCAA’s methodology for establishing the reasonableness of executive compensation was “fatally flawed statistically” and “significantly overstated and speculative.”
Good stuff, and a great win for contractors everywhere (though DCAA has, to all appearances, ignored that ASBCA decision and continues to question exec comp costs using the same flawed methodology).
But then J.F. Taylor submitted an application for nearly $200,000 in attorney fees it had incurred appealing the matter, pursuant to the Equal Access to Justice Act (EAJA). Judge Shackleford denied the request, finding that the government’s position was “substantially justified” because it was based on published regulation (citing R&B Bewachungsgesellschaft mbH, ASBCA No. 42221, 93-3 BCA If 26,010, aff'd on recon., 94-1 BCA 126,315). As Judge Shackleford wrote, “… the method used by the government to evaluate the reasonableness of executive compensation had been used over a long period of time and this methodology was part of the DCAA contract audit manual.” In other words, Judge Shackleford conflated the DCAA Contract Audit Manual (CAM)—which is an internal document published by and for DCAA auditors without public input and without the force of regulation—with published regulations such as the FAR. Even the non-lawyers here at Apogee Consulting, Inc. thought that was an error of law that demanded a Motion for Reconsideration.
J.F Taylor’s attorneys thought so too, and filed that Motion. In a recent decision, Judge Shackleford denied it as well.
Judge Shackleford’s decision was based on the fact that the government’s position was supported by legal precedent—namely, the Techplan decision. Even though the original decision found that DCAA “generally followed” the Techplan approach to evaluating exec comp, the Judge also found that J.F. Taylor’s expert statistician challenged “Step 6” of the Techplan analysis, and that challenge was unrebutted. Therefore, the Judge opined that—
That [failure to rebut] may have been a tactical error in defending the claim, but not one fatal to substantial justification of the position it took relying on Techplan as precedent. … [while] reliance on the DCAA manual and long standing practice alone might not justify an otherwise unreasonable position, but those factors combined with the fact that the methodology in the manual was based upon legal precedent (Techplan) justified the government's position.
Having so found, Judge Shackelford then indulged in a bit of what attorneys might call obiter dicta, opining that—
While one could quibble over the status of the DCAA manual and the established practice by DCAA in approaching executive compensation cases, the fact remains that the Techplan decision was established law that the government relied upon and that the DCAA manual was based upon; and, on that basis, we do not modify our decision that the government's position was substantially justified.
So okay, then. Unlike our prior article where we thought Judge Shackleford’s elevation of the DCAA CAM to regulatory status was a travesty and judicial error of epic proportions, we’re not going to go there again. You win some; you lose some. J.F Taylor won its case in main and avoiding paying some $500,000. The fact that it had to spend $200,000 to do so is an unfortunate reality of litigation.
We are not going to get all worked up regarding how the Judge changed the basis of his original finding, so as to continue to find that the government’s position was “substantially justified.” We’re not going to get all worked up about how he elided J.F. Taylor’s attorneys’ arguments about the purpose of the EAJA. DCAA and DCMA got away with another one, apparently.
It happens.
In order for the contracting community to roll back the tide of unreasonable DCAA findings and unsupported Contracting Officer decisions, individual contractors, such as J.F. Taylor, need to stand up and say, “enough is enough.” Those courageous contractors need to spend the funds litigating, even with little likelihood that they will have their attorney fees reimbursed. Only in such a manner can the rule of law prevail over the petty bureaucrats and their flawed administrative policies.
The Timeliness of Follow-up Audits
 The Government contracting community was uneasy when DOD proposed to revise the Defense Federal Acquisition Regulation Supplement (DFARS) in 2011 to adopt a new approach to surveilling and evaluating contractors’ internal control systems. We shared the general apprehension. In fact, we wrote articles and even submitted comments to the DAR Council, in the hope that the members might reconsider the proposed approach.
Yeah, like that was ever going to happen.
And so the final rule was issued and now several Defense contractors have joined the 5 percent “withhold club”—which may be an amusing turn of phrase, since DOD now uses the threat of payment withholds as a club to beat contractors into agreeing with audit report findings (no matter how flawed) or to beat price concessions out of them when negotiations become rocky. And it’s no longer just Defense contractors who will be feeling the pain associated with the “business systems” oversight regime. As we told our readers, the Department of Energy has decided to adopt the DOD oversight approach. And thus, soon the lives of the DOE contractors—but not the M&O contractors, who were exempted from DOE’s new rules—will be filled with joy and rainbows. (Please read that previous sentence in a sarcastic tone of voice.)
Yet, as we look back on the original concerns and comments submitted by so many (including us), we are struck by their relevance. For example, we took the DAR Council to task because we thought the proposed rules would be “unworkable” since DCMA and DCAA would lack resources to support the new requirements. In particular, we thought DCAA’s role in the follow-up process (to confirm contractors had implemented the required system corrective actions) was going to be problematic. We told the DAR Council—
At its current workload, DCAA already takes years to resolve follow-up business systems audits. The author has personally been witness to follow-up audits that lay fallow for two or more years, because DCAA’s auditors constantly are reassigned to meet the needs of ‘demand audits’ and other internal priorities. Let us reiterate: DCAA cannot support timely audits of contractor business systems, issue its audit reports in a timely manner, and provide timely reviews of contractor corrective actions. It’s simply impossible and no platitudes from DCAA or the DAR Council will make it possible.
[Emphasis in original. Link to comments provided above.]
And now the Department of Defense Inspector General has told Patrick Fitzgerald, Director of DCAA, much the same thing. In a recent audit report, the DOD IG told DCAA its business system follow-up audits were not being performed timely.
The DOD IG was investigating a hotline allegation that DCAA auditors had negligently, in non-compliance with Generally Accepted Government Auditing Standards (GAGAS), issued an audit report concluding that a contractor in the Northeast had corrected previous findings of system deficiencies in that contractor’s Material Management and Accounting System (MMAS), which is one of the six “business systems.” In September, 2005, DCAA issued an audit report finding 30 individual deficiencies in the MMAS. In January, 2007, DCAA initiated a follow-up audit to evaluate whether or not the contractor had corrected those 30 deficiencies. DCAA issued its audit report in September, 2008, finding that the contractor had corrected 28 of the 30 deficiencies.
Note it took DCAA a full 18 months to start the follow-up audit, and another 21 months to issue it—meaning the ACO received the follow-up report more than three years after hearing about the contractor’s system deficiencies. In fairness, we also have to note that this all took place years before the promulgation of the revised DFARS rules. But similar anecdotal evidence of DCAA’s inability to issue timely audit reports abounded at the time—and informed the comments submitted to the DAR Council. Since then—as we’ve reported—the delays have gotten worse, not better. For example, the IG reported that the DCAA Field Audit Office (FAO) “initiated a second follow-up audit” to evaluate the two remaining deficiencies in August, 2011—nearly three years after the first follow-up audit report was issued. And according to the IG, that second follow-up audit was “still ongoing” two years after it started.
And therein we find the crux of this article.
We are much less concerned that the IG substantiated the original hotline allegation that the DCAA auditor (since retired) had concluded 28 of the 30 deficiencies had been remediated “without obtaining adequate evidence” and thus “the Government does not have a reasonable basis for relying on the accuracy of material costs charged by the DoD contractor.” Whatever. We all know that DCAA obtaining adequate evidence to support its audit findings is, by far, the exception and not the rule. The IG’s finding is but one of a host of similar findings they could make, if only they looked for them.
The big deal—and this is something that the DOD IG keyed on as well—is the untimeliness of the DCAA follow-up audits. The IG wrote—
In March 2010, the contracting officer requested that the DCAA FAO perform a second follow-up audit to review the contractor’s efforts to eliminate the two outstanding deficiencies and provide the results of the review by May 2010. Yet, more than 3 years later, the FAO has still not completed the second follow-up audit. The FAO told us that the completion of the audit was delayed because of other priority work. It is unreasonable for the FAO to take more than 3 years to complete a limited follow-up audit of two deficiencies.
In addition to be unreasonable, the DOD IG also found that the situation was noncompliant with the DCAA Contract Audit Manual (CAM). It wrote: “According to the [CAM], the auditor should place a high priority on conducting follow-up audits of previously reported business system deficiencies….” More importantly, the IG wrote—
The failure of DCAA to conduct a timely follow-up audit compromises the contracting officer’s responsibility in determining the adequacy of the MMAS, implementing withholdings in accordance with DFARS 252.242.7005, and reducing or eliminating withholdings to reflect the contractor’s progress in correcting deficiencies. Contracting officers might not withhold payments if DCAA does not uphold its responsibility to conduct timely follow-up audits of contractor corrective actions.
To address this concern, the IG recommended that DCAA should “assess the timeliness of follow-up audits on an agency-wide basis and make appropriate improvements in related quality assurance procedures.”
Readers may find it interesting that the DOD IG thought the DCAA Director’s comments to that recommendation were “non-responsive”. The IG wrote—
The Director, DCAA, agreed ‘in principle.’ DCAA recognizes that it can improve the timeliness of business system follow-up audits agency-wide. However, the Director stated that the requirements for DCAA services far exceed the available staffing and management must make decisions on which priority assignments take precedence. In addition, the Director does not believe ‘a detailed assessment of the timeliness of business systems follow-up reviews is a good use of DCAA’s limited resources.’
The DOD IG thought the Director, DCAA, could do better. The audit report stated—
We disagree that assessing timeliness is not a good use of DCAA’s limited resources. An assessment could identify opportunities, best practices, and lessons learned for improving timeliness When DCAA reports that a major DoD contractor’s business system contains significant deficiencies as defined in DFARS 252.242-7005, DCAA asserts that the deficiencies materially affect the ability of DoD officials to rely on information produced by the system. If the contracting officer agrees with DCAA, the contracting officer must withhold payments until the contractor eliminates the deficiency. Therefore, DCAA plays a critical role in providing the contracting officer with timely information on the status of contractor corrective actions. If DCAA commits resources for conducting a full business system audit and reporting on significant business system deficiencies, then DCAA should place a high priority on performing a limited and timely follow-up of those deficiencies. Although DCAA policy allows for the reporting of significant business system deficiencies in other audits, this does not address the need for performing timely follow-up audits of the deficiencies (including those identified in other audits).
Yeah.
We told the DAR Council this was going to be an issue under the new DFARS business systems rules. We were not alone in sounding that particular alarm. And the DAR Council ignored all those warnings, for which we believe its members ought to be ashamed.
As for DCAA’s part, we suspect that business system reviews and follow-up audits are going to come back into vogue sometime in the future. This audit report may help in that regard. In addition, the movement of CASB Disclosure Statement adequacy reviews from DCAA to DCMA should help as well—as will the dropping of DCAA from its formerly key role in the Forward Pricing Rate Proposal analysis process.
In other words, DCMA seems to be more than a little tired of receiving audit reports too late to be helpful and which are of dubious quality in any case. Consequently, they are carving DCAA out of their contract administration processes wherever possible. Sooner or later, DCAA will find itself with lots of time on its hands. Perhaps they’ll use that time to perform some business system reviews and follow-up audits.
What else are they going to do?
|