• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

CH2M Hill Sues DynCorp

E-mail Print PDF

Readers know that DynCorp has had a number of recent challenges. As The Washington Post reported, “The McLean-based defense contractor has been cited for labor violations by the Defense Department inspector general, seen sales drop by more than 30 percent and replaced its chief executive twice in one month.” As we have reported here, it has been alleged that DynCorp overcharged its prime contractor, Northrop Grumman, as much as $100 million. Recently, the company lost its recompetes for two large Defense Intelligence Agency support contracts estimated to be worth as much as $71 million.

It’s been a “challenging” year for DynCorp.

On top of the other challenges faced by the contractor, it is now being reported that one of its subcontractors, CH2M Hill, has filed suit against it. The CH2M Hill suit “claims that DynCorp did not pay CH2M Hill its fair share of profits on the contract over the last two years, a total of $26 million, according to the company.” According to WaPo,”The two companies have been partners on the Army contract [in Afghanistan] since 2007.” We suspect that unnamed Army contract is LOGCAP IV. The LOGCAP contracts are generally to provide logistical support to military services stationed around the world.

Apparently, DynCorp and CH2M Hill have some sort of contractual arrangement that included profit-sharing, since WaPo reported that CH2M wanted “its fair share of profits”—profits which, presumably would be calculated on a basis other than costs incurred by CH2M Hill.

For its part, DynCorp disputes the claim.

WaPo reported, “DynCorp says it owes the company only $12 million, and made one payment of $6.3 million toward that end earlier this year.” Hmm. That seems kind of strange. If CH2M was owed $12 million, then why would only a partial payment have been made? And if DynCorp admits that it owes CH2M some amount of money, then why did WaPo report that “in June, DynCorp sent CH2M a letter saying it did not owe the company any money, according to the suit.” Either DynCorp did not owe CH2M any money, in which case no payment would have been made at all, or else DynCorp did owe CH2M Hill, in which case why would a letter have been sent denying that any money was owed? Strange ….

Effective subcontractor management is, fundamentally, relationship management. It is seeking to align the potentially disparate interests of two individual firms. It is attempting to defuse what can too easily be an adversarial relationship by finding common ground and an alignment of interests.

Unfortunately too many attorneys, and too many program managers, and too many contract managers, believe their job is to solely represent the interests of their own company at the expense of the other company. They see a zero-sum game in which they can “win” by forcing the other guy to “lose”. We see this bias emerge when metrics such as “savings through negotiation” are reported, as if saving money at the expense of program execution was an acceptable trade-off.

It’s not an acceptable trade-off.

Focus on self-interest at the expense of the group interest leads to strained relationships; it leads to sub-optimal decision-making; it harms program execution and impacts contractual outcomes. Self-interest creates an adversarial relationship instead of an aligned relationship. We have seen self-interest scuttle the best interests of the program, over and over and over again. So think about that the next time you want to force your key subcontractor to accept something it really doesn’t want to accept.

For CH2M Hill and DynCorp, it is too late to fix the relationship. The lawyers are now running the show, at (let us guess) $750 per hour. Who knows who’s right and who’s in the wrong? At this point, all we know is that the two parties are now mired in the lengthy, resource-consuming, expensive, adversarial legal process.

The situation has to be difficult. It has to be hard to execute well when you are in court. We suspect the situation is much more than a distraction. It’s probably more in the nature of a pre-divorce argument. You know, the kind in which the two parties retire to separate rooms in which to cry and sulk, and meanwhile the injury just festers and grows. Nobody is happy … except the lawyers.

Meanwhile, in the midst of these distractions, we have to ask: Are the service men and women of the US Army receiving the best efforts of their LOGCAP IV contractors?

 

Why Companies are Reluctant to Contract with the Defense Department

E-mail Print PDF

Competition is good, and so is innovation. Having more contractors willing to sell to the Pentagon addresses both of those goods. Having more “non-traditional” contractors willing to sell to the Pentagon is even better. Consequently, most policymakers want to see what can be done to attract those non-traditional companies to the defense industrial base.

DOD leadership has been focusing on innovation in order to “maintain military superiority,” according to this story by The Washington Post. In fact, Mr. Frank Kendall, USD (AT&L) has announced that he is dedicating “Better Buying Power 3.0” to “innovation, technical excellence, and speed,” according to the story. Readers may recall that previous incarnations of BBP focused on reducing DOD bureaucracy and increasing supplier efficiency. Previous BBP initiatives focused on reducing suppliers’ costs, among other things. (It’s not like this blog hasn’t provided detail upon detail of those previous BBP foci. The site’s keyword search feature is your friend.) Today’s BBP is about innovation, because (according to Kendall’s quoted speech) “We cannot assume, as we did in the 1950s and ’70s, that the Department of Defense will be the sole source of key breakthrough technologies.”

So innovation is the current area of focus, and it is believed that innovation can best be found in the non-traditional technology companies. It is felt that the DOD is too bureaucratic, too moribund, to drive disruptive technology breakthroughs. (We’ve written about that before, as well.)

The RAND Corporation tackled the subject via one of its Federally-funded Research and Development Centers (FFRDCs). As part of its analysis, it interviewed representatives from 16 non-traditional suppliers in three industries “where DoD indicated that it wants to seek substantial innovation from nontraditional suppliers.” It also interviewed three DoD staff members who dealt with such companies.

It recently published its results.

It cited four commonly heard complaints with the DOD business environment. Those were—

  • a lack of access to and communication from DoD

  • an extensive, complex, and inefficient bid and selection process

  • administration and management of contracts that created extra work and delays

  • a lengthy funding time line and final payments that often also involved delays and gaps.

With respect to management and administration of contracts, the RAND study reported—

Our interviewees noted particular problems with contract management by the Defense Contract Management Agency (DCMA) or the Defense Contract Audit Agency (DCAA). Correcting errors, whether by DoD or the contractor, could be extremely difficult, and critical errors affecting the scope of work or payment could take months or even years to fix if contract management had shifted from the original contracting officer to DCMA. Similarly, final contract payments could reportedly be stalled for years because of large DCAA backlogs.

(Emphasis added.)

To address those perceived barriers, the RAND authors recommended (among other actions), “reducing backlogs at DCMA and DCAA, noting the chances of project cancellation, and adopting best commercial procurement practices or even those used in state and local governments, which tend to be far less cumbersome.”

Sure.

You might want to call those recommendations “innovation in contract management.” Except there’s nothing at all innovative about them. We’ve heard it all before, haven’t we?

Whether it’s Mr. Kendall pleading for tech companies to invest their own funds to create disruptive technologies that can be transferred to the U.S. military, or it’s the RAND folks recommending the adoption of “best commercial practices,” we’ve heard all this before.

Remember “acquisition reform” under President Clinton? Remember the Federal Acquisition Streamlining Act (FASA) and FARA and IMTRA? Remember Kelman’s acquisition revolution? Remember “reinventing government” and “a government that works better and costs less”? Remember all that?

Because we do.

We remember it was driven by a perception that DOD had fallen behind Silicon Valley, that this newfangled Internet thingee was going to revolutionize the way the Federal government did business—if only we could convince the Federal government employees to use it.

Yeah. Mr. Kendall? Sir? Been there; done that.

In fact, the notion of abandoning bureaucratic and moribund Pentagon acquisition practices in favor of “best commercial practices’ has a long, honored pedigree. For example, the Manhattan Project used it in World War II (“Operation Silverplate”). You can go back farther than that, if you’d like to.

Allow us to quote—

Three points stand out prominently … The first is that the established system of doing business in the War and Navy Departments broke down early in the war. The second is that the civilians, expert and inexpert, who attempted to carry on business which properly belonged to the departments, where they succeeded at all in doing better than the departments themselves, did so usually by violation of the law—the very law which, in large measure, prevented the departments from doing as well as the civilians did. The third is that it was found necessary to replace a bureaucratic order with the more elastic and freer methods of private business.

We quote, of course from the Editor’s Preface to Preliminary Economic Studies of the War: Government War Contracts, published by the Carnegie Endowment for International Peace. It was published in 1920. That was very close to one hundred years ago.

It’s actually a very interesting book. It explained the advantages of using Cost-Plus-Incentive-Fee contracts instead of CPFF types. It discussed how the Supply Bureau perpetuated and enhanced competition during wartime. It discussed how contract changes and modifications were handled. And tt shows just how little has changed in the past 95 years of defense acquisition, despite initiative after initiative, study after study, and at least three separate incarnations of Better Buying Power.

We particularly like this quote summarizing the Navy’s approach to cost-control in a cost-reimbursement manufacturing environment: “The accounting organization has been imbued with the idea that a way must always be found to prevent the waste of the government’s money without interfering with the expeditious prosecution of the work.” That was the approach taken in World War I.

Where did the Pentagon fall away from that foundational principle and, instead, let the auditors take control?

How did we reach a point where companies with something to offer the Defense Department would rather not sell to the DOD because they don’t want to deal with audit backlogs and stalled final delivery payments?

We learned lessons in World War I. We learned them again in World War II. We learned them in Korea, in Vietnam, and in the first Gulf War.

Now, apparently, we are learning them again.

 

DCAA’s Approach to Evaluating Audit Evidence

E-mail Print PDF

PCAOB Auditing Standard 15 addresses audit evidence. What is audit evidence?

Audit evidence is all the information, whether obtained from audit procedures or other sources, that is used by the auditor in arriving at the conclusions on which the auditor's opinion is based. Audit evidence consists of both information that supports and corroborates management's assertions regarding the financial statements or internal control over financial reporting and information that contradicts such assertions.

Audit evidence obtained must be sufficient to support the conclusion(s). Sufficiency is a measure of the quality of the audit evidence. Audit evidence must be appropriate, as measured by the relevance and reliability of the evidence. The reliability of evidence depends on its nature and source, as well as the circumstances under which it is obtained. Evidence obtained by the auditor is more reliable than evidence obtained indirectly. Moreover, “evidence provided by original documents is more reliable than evidence provided by photocopies or facsimiles, or documents that have been filmed, digitized, or otherwise converted into electronic form, the reliability of which depends on the controls over the conversion and maintenance of those documents.”

Audit procedures for obtaining evidence generally consist of inspection, observation, and inquiry. The audit evidence may be evaluated via recalculation or reperformance. Reperformance involves the independent execution (by the auditors) of procedures or controls that were originally performed by company personnel.

Auditing Standard 14 discusses the evaluation of audit results. It states—

If the auditor has not obtained sufficient appropriate audit evidence about a relevant assertion or has substantial doubt about a relevant assertion, the auditor should perform procedures to obtain further audit evidence to address the matter. If the auditor is unable to obtain sufficient appropriate audit evidence to have a reasonable basis to conclude about whether the financial statements as a whole are free of material misstatement, AU sec. 508 indicates that the auditor should express a qualified opinion or a disclaimer of opinion.

The DCAA Contract Audit Manual (April 2014), Chapter 2, states—

An examination consists of obtaining sufficient, appropriate evidence to express an opinion on whether the subject matter or assertion is based on or in conformity with the criteria in all material respects. An examination report provides a high level of assurance and the auditor’s conclusion is expressed in the form of an opinion (stated as positive assurance). Therefore, the audit objective is to gather sufficient evidence to restrict attestation risk to a level that is, in the auditor’s professional judgment, appropriately low for the high level of assurance that is imparted by the audit opinion. In such an engagement, the auditor should select a combination of procedures to assess inherent and control risk and restrict detection risk such that attestation risk is restricted to an appropriately low level. In the contract audit environment, evaluations of complete submissions (price proposals, claims, and overhead rate proposals), where the auditor establishes the scope, are performed as ‘examinations.’

That same chapter also states—

The auditor must obtain sufficient evidence to provide a reasonable basis for the conclusion expressed in the report. This requires that sufficient procedures be performed to test the contractor’s assertion to provide reasonable assurance that unallowable costs and other noncompliances with applicable Government laws and regulations are identified. The first step in obtaining sufficient evidence is to perform an adequate risk assessment to identify risk areas for the performance of substantive procedures. Substantive procedures include analytical procedures and detailed testing. The nature and extent of substantive procedures is a matter of auditor judgment based on the risk assessment. However, audit risk would never be low enough to eliminate the need for substantive procedures. Furthermore, inquiry and/or analytical procedures alone are not sufficient to support the high level of assurance provided in examination engagements. Detailed testing must be performed in all examination engagements.

Chapter 3 of the CAM basically recapitulates the PCAOB Auditing Standards we quoted at the beginning of this article. It adds some additional guidance for auditors, including—

… a controller's written statement explaining how costs are allocated to contracts by a computer program is not sufficient by itself, to use as the basis for an opinion on the reliability of the generated costs. This is the poorest quality evidence, since it is testimonial and is generated by the contractor. A written manual, even if prepared by an outside computer programmer, documenting the program's operation also alone is not sufficient. While it is better quality evidence since it was prepared by an independent source, it is still not sufficient alone to satisfy the audit objective; however, it may be used as corroborative evidence with the controller's statement. But even the two together are not sufficient evidence to base an opinion on the costs. Testing of several transactions processed through the program are necessary to assure that costs are being allocated as they should. The testing alone may be sufficient (i.e., relatively better quality evidence since it is directly obtained), but also may require further evidence to develop an opinion. These tests combined with the other two pieces of evidence may be sufficient on which to base an opinion.

In addition, Chapter 3 of the CAM states—

The chain of evidence extends from documents describing individual transactions through the books of original entry to ledger accounts and to the cost representations. The reliability of ledgers and accounts as evidence is dependent on the soundness of the principles and policies upon which the records were developed and on the adequacy of internal controls exercised in the preparation and review of the records. Auditors should constantly be alert for potential manipulation of contractor ledgers and accounts. One example would be the removal of pages containing transactions that management or others do not want the auditor to review from a computer listing. If such a listing includes many transactions, it would be difficult to manually verify the accuracy of the totals at the end of the listing.

There are discussions of physical observations and discussions of perambulations. There is a detailed discussion regarding the contractor’s use of scanned images in lieu of original documents. There’s quite a bit of audit guidance.

But there’s almost nothing regarding checking beyond the contractor’s documentation. There’s almost nothing regarding obtaining cancelled checks and/or bank statements to verify claimed costs can be traced, on a cash basis, to the source of the cash. Similarly, there’s very little to be found regarding having contractors reperform their work under the watchful eyes of the auditors, in order to ensure that the data is not being manipulated.

So why do so many DCAA auditors insist on those types of approaches?

Our experience with supporting recent DCAA 10100 audits (aka “incurred cost proposal” audits) has befuddled us. We run accounting system reports and provide the original output to an auditor, who then tells us that s/he need it provided in an Excel spreadsheet in order to run analytics. We run accounting system reports and provide the output in an Excel spreadsheet to another auditor, who tells us that s/he cannot accept that data because it is not in the original format. We run accounting system reports and provide both the original output and an Excel spreadsheet to the auditor, and then s/he tells us that we need to reperform the report queries under the watchful eyes of yet another auditor, who is supposed to witness the query and make sure nobody is manipulating the data.

Where in the CAM does it say to do all that?

We are at the point where we feel that DCAA should simply move into the contractor’s facility and live with the contractor personnel, just to save the duplication of effort. Just watch everything the employees do and then they’ll only have to do it once.

This notion that transactions have to be traced back to payroll deposits and bank statements is getting silly, in our view. If the auditors have reviewed the accounting system – as they should have – then they should have confidence that the system works. If they lack confidence in the system then they must have done a poor job in reviewing the accounting system in the first place.

It is indisputable that audits take longer – far longer – than they ever have. The most common explanation given for the delays is that the auditors are being more diligent. They are complying with GAGAS. They are doing a better job in terms of audit quality, and quality cannot be rushed. Blah, blah, blah.

We know, because the DOD Inspector General told us, that DCAA audit quality is still lacking. We know, because the DOD Inspector General told us, that DCAA still fails to comply with GAGAS in far too many audits. We know, because the DOD Inspector General told us, that too many audits still lack sufficient evidence to support the conclusions reported.

We know that DCAA still takes far too long to issue its audit reports. And we know that too many of those delayed reports are deficient in the quality department as well.

Why?

Well, perhaps one driver is the need to witness everything the contractor does, to reperform every accounting system query and see the output in as many formats as possible. Perhaps another driver is the need to trace every transaction down as far as it will go. We get that fraud risk has to be addressed, but we believe DCAA has gone too far in that regard … as it has in almost every “audit quality” initiative the audit agency has undertaken since 2008.

Too many DCAA audit reports still fail to meet GAGAS standards. Too many reports fail to deliver value to the customer that asked for them. The audit process takes too long and still fails to deliver a quality product. We suspect one big cause of the problem is a lack of professional judgment in the area of obtaining and evaluating audit evidence.

Maybe somebody should look into that?

 

Did Taxpayers Fund Climate Research Institute’s Christmas Party?

E-mail Print PDF

Climate_Change_Conspiracy
From the Fort Wayne Journal Gazette comes a story about NEON (National Ecological Observatory Network), a Colorado-based not-for-profit (NFP) who may have used grant funds received from the National Science Foundation (NSF) to fund unallowable expenses. According to the story, the alleged unallowable expenses included “$112,000 for lobbying, $25,000 for an office Christmas party and $11,000 for ‘premium coffee services’ and an unspecific amount on French hotels.”

Interesting. We did not realize that French hotels were unallowable.

For that matter, we did not see the Cost Principle that made coffee service unallowable. Perhaps regular coffee service is allowable, whereas “premium” coffee service (whatever that may be) is unallowable?

As we said: Interesting.

The story of how this alleged newstory came to national attention is also interesting

About NEON. “NEON is a continental-scale observatory that measures the causes and effects of climate change, land use change and invasive species on U.S. ecosystems.” Some people – notably some U.S. politicians who have conservative points of view – tend to look askance at scientists and entities that may be spending taxpayer funds pushing an agenda that promotes the notion that global warming is caused in significant part by the impacts of humanity on the ecosystem. In this case, two Republican U.S. Senators, (Grassley and Rand) wrote a letter to NEON in early September, 2014, expressing their concerns with the NFP’s use of taxpayer dollars to fund “meals, entertainment and travel that is not part of official business, which is paid from or attributable to a federal grant.” The Senators expressed concerns about the NSF’s management of its grant funds, “since documents show that the foundation was aware of the expenses and paid them.”

The Washington Post also reported the story as well. WaPo noted, “The [two] senators are now asking NEON and the foundation for correspondence between them related to the reimbursed expenditures, the justification for using taxpayer funds for the expenses and details about the nonprofit group’s lobbying efforts.”

But how did the two Senators come across this story? According to the sources (links above), a DCAA auditor brought the matter to the Senators’ attention because he was concerned that his management was going to engage in a “whitewash” by overriding his findings and approving the costs. Indeed, the DCAA confirmed that intention. The articles reported –

From 2009 to 2013, NEON classified all the expenses that Grassley and Paul are questioning as a ‘management fee.’ Internal documents show that the NSF was told by NEON that it was having a difficult time covering the costs because it had little in the way of private funds. …

‘Government regulations put no restrictions on the company’s use of this fee,’ [DCAA] said in its prepared statement. ‘Because Government regulations put no restrictions on management fee expenditures, it is inappropriate for DCAA to disallow those costs.’ A fee is supposed to cover the costs of managing a contract or a cooperative agreement with a government agency, and it is typically is less than 1 percent of an organization’s budget, records show.

So NEON needed to use some of the NSF grant funds to cover its operating expenses. The auditor objected to some of those operating expenses, because they were either expressly unallowable or because they were unrelated to the purpose of the grant. For its part, NSF was aware that NEON priced in a “management fee” (aka profit or fee) into its grant requests in order to cover such expenses, and NSF knew and approved of the practice.

Note that this is yet another case of a draft, unissued, DCAA audit report ending-up in the hands of politicians. KBR knows of this unfortunate and possibly unlawful practice all too well, having been the victim of it more than once.

For its part, NEON disputed the audit findings and issued its own statement, in which its Chairman stated, NEON “has spent all funding in strict compliance with our understanding of the guidelines provided” and that the records requested by the two Senators would be provided.

The basic question, as we see it, is whether a grant recipient can add an additional cost to its grant request in order to cover certain unallowable operating expenses. (Assuming, for the sake of argument, that the expenses cited by the Senators were unallowable.) In the commercial world, entities are expect to cover their unallowable expenses from the fee or profit they add to their total costs. So the question is whether NEON’s “management fee” adder accomplished the same thing.

Apparently, according to the NSF (who issued the grant) and to DCAA (which audited expenditures associated with the grant), the answer to the question is “yes.” The two Senators believe they know better, and apparently believe there is some kind of conspiracy going on to ignore how NSF grant recipients spend the management fee adder.

Kind of like the conspiracy that many believe is involved with climate change. A column in USA Today (link in previous sentence) asserted that –

… the idea that climate scientists are using global warming alarmism as a means to feather their own nests is common among climate change denialists. This view seems to be based on the idea that there is an immense amount of grant money available to scientists who perpetuate the ‘hoax,’ that this grant money makes these scientists rich, and that this incredibly corrupt and dishonest group of people has decided that this is a more lucrative path than, say, convincing the billionaire Koch brothers, who have spent a lot of money supporting climate change denialism, to put them on their payroll to take the opposite position.

The author of that column asserted that “This is an unlikely scenario.” Your mileage may vary. But regardless of your position on the conspiracy (or on the science) involved in climate change and global warming, it seems clear that the (inherent) conspiracy between NSF, DCAA and NEON to misuse grant funds intended to measure climate change would fit nicely into the point of view that already sees a conspiracy in place. It just means the conspiracy would include a few more conspirators.

Unfortunately for those who see a conspiracy intended to hide misuse of taxpayer funds, the OMB Circulars and NSF grant rules and applicable Cost Principles will provide a more black-and-white answer. Indeed, the official position of the Defense Contract Audit Agency seems to already have provided that black-and-white answer, despite the protestations of a couple of Republican Senators.

Government contract cost accounting and compliance with applicable statutes, regulations, and rules ain’t rocket science.

 

Let’s Sue DCAA? Well, KBR Just Did!

E-mail Print PDF

Remember that old article we wrote? The one in which we said, “Sooner or later, a contractor is going to get fed up with the situation and sue DCAA for malpractice under the FTCA. We suspect it will be sooner, rather than later.”

So that happened.

We don’t have the details, because Law360 has a paywall and the subscription is too dear for this little consultancy. But what we do know is that Law360 reported the following:

Kellogg Brown & Root Services Inc. sued the U.S. government in Delaware federal court on Tuesday, seeking to recover $12.5 million in legal fees from litigation that arose out of an allegedly defective Defense Contract Audit Agency report on its use of private security contractors during...

The lawsuit, which seeks damages under the Federal Tort Claims Act, accuses the DCAA of wide-ranging professional malpractice …

Readers of this blog know about that dispute. Here’s a link to the article in which we reported—

… 35 pages of Findings of Fact that summed up a colossal Charlie Foxtrot, wherein the U.S. Military tried to perform its primary mission under difficult circumstances, a mission that (based on testimony and evidence and Findings of Fact) did not necessarily include protecting the civilian contractors, who were thus forced to protect themselves by hiring PSCs, which led to questioned, suspended, and disallowed costs. We have an opinion on the equity of the situation, but that opinion is not relevant to this article.

See that there? That was us being discreet! That part about “we have an opinion … but that opinion is not relevant to this article.” That was good, right? Seriously, how often do we do that on this blog?

Anyway our opinion is still not relevant, but we will venture one here anyway, just for the record. For the record, then, our opinion is that if you take civilian contractors into a war zone, you owe them the obligation of providing them safety and security at least equal to that provided to military service members and civilian employees of the DOD. At least that amount, if not more. And if it turns out that the military cannot provide civilian contractors with at least that level of security, those contractors will have to go look elsewhere. Or they have to abandon their posts and put the overall mission in jeopardy and probably get sued by the DOD for nonperformance. So pretty much they have to go look elsewhere for their security and safety. They have to go find their own security suppliers if they want to stay at their posts.

And if you then say, thanks for staying at your post, but we are going to make the cost of you providing your own security unallowable, because reasons, then that is manifestly unfair. If the military can’t do the job, then somebody else has to. Or else don’t bring civilian contractors into a war zone.

Don’t bring civilian contractors into a war zone, and tell them the U.S. military is going to protect them, and then have them find out later that, in fact, the U.S. military has a mission to perform—and that mission does NOT include protecting the civilian contractors. Surprise!

And don’t have them shrug their shoulders in resignation, and then go provide their own security, security that is obviously allocable to the contract at hand as a direct cost, a direct cost that is allowable since it was not made unallowable by any contract terms or conditions, and then have the auditors say “unallowable.” That situation strikes us as being more than simply unfair. It strikes us as being a bit cowardly and more than a little duplicitous. “Good faith and fair dealing” is the standard and, in this case, that standard seems to have been missed by a mile.

So there’s our opinion on that. For the record.

KBR, which was forced to spent $12.5 million in legal fees to recover its questioned, suspended, and disallowed PSC costs, and which lost the use of a roughly a hundred million dollars in cash (but still had to keep performing its contracts and pay its employees) on the basis of an allegedly flawed DCAA audit report, is now suing the audit agency.

Good for them.

Meanwhile, as readers know, the DOD IG recently found errors in 81 percent of recent DCAA audit reports it reviewed. Which leads us to wonder how many other contractors may be out there, looking to sue DCAA for similar flawed audit findings.

 


Page 124 of 278

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.