• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

DCAA Audit Quality Under Fire from DoD OIG (Again)

E-mail Print PDF

Recently we wrote yet another article about management decisions made by the leadership of DCAA and how those decisions spawned adverse consequences for the audit agency. We also wrote recently about at least one call from an industry group to rethink those decisions, to address the unfortunately adversarial relationship between the Pentagon and its suppliers—starting with reducing the “inefficient” and “wastefully expensive” audit practices of the DCAA. That industry call for audit reform noted that “40 percent of DCAA personnel have five or fewer years or less experience in government auditing.” It also noted a “decentralized” audit agency management structure that “allows variation in practice and culture among its auditors” as a contributing cause of the poor audit practices found at DCAA.

Since 2008, DCAA has been under fire from a variety of sources. Each volley has taken aim at poor audit practices that (allegedly) contribute to a host of problems, from lack of timeliness and quality to a lack of usefulness by requesters. The audit agency has taken a number of steps to try to fix its problems (both real and perceived) but the problems persist. A recent review by the DoD Office of Inspector General found that 81 percent of DCAA audit reports reviewed had one or more significant GAGAS deficiencies.

Fundamentally, both industry and reviewers want to see the same thing in a DCAA audit report. They both want to see conclusions adequately supported by evidence. Unfortunately, that turns out not to be the case in far too many audits.

On December 23, 2014, the DoD OIG issued another report finding fault with the quality of a DCAA audit report. The DoD OIG found that “the DCAA field audit office did not comply with generally accepted government auditing standards (GAGAS) or agency policy when it questioned $6.6 million in contractor-claimed subcontract costs.” Moreover, the OIG reported that “The auditor did not obtain sufficient evidence to conclude that the subcontract costs were unsupported … [and] the field audit office applied an arbitrary and unsupported 20-percent decrement factor to calculate the questioned costs.” In addition, the OIG noted that “the auditor made significant errors on the DCAA Form 1” that was provided to the cognizant Contracting Officer.

In May, 2012, the DCAA FAO No. 3311, located in the Central Region, issued Audit Report No. 3311-2009W10170001, opining on the allowability, allocability, and reasonableness of a contractor’s claimed subcontractor costs in its FY 2008 proposal to establish final billing rates (popularly known as the annual “incurred cost proposal”). According to the OIG—

DCAA concluded that the contractor could not adequately support its claimed subcontract costs of approximately $33 million … DCAA based its conclusion on a statistical sample of 70 subcontract invoices, which comprised $13.5 million of the $33 million in claimed subcontract costs. DCAA found that the contractor did not provide documentation to support the allowability of any of the 70 invoices.

DCAA found that zero costs in its sample were adequately supported, but decided not to question 100 percent of the $33 million in claimed costs. Instead, “the FAO elected to question 20 percent (about $6.6 million) of those costs based on its consideration of contractor performance and product delivery.”

In the foregoing are the makings of a quotidian DCAA audit story, where a contractor performs work and expects to be paid for its incurred costs, yet DCAA finds a way to question those costs and the Contracting Officer is expected to exercise the wisdom of Solomon in negotiating a settlement, which the contractor must then accept or else incur a large amount of attorney fees pursuing justice in court—where there is little guarantee that justice will be found.

We don’t know the contractor or the auditor or the details of the story but, if the story were similar to the ones with which we deal every single day, the most infuriating aspect of the story would be found in the following details reported by the OIG—

Our evaluation disclosed that DCAA failed to comply with Chapter 5 of GAGAS and the AICPA standard by not obtaining adequate evidence to support its conclusion that $33 million in subcontract costs were unsupported. Specifically, the auditor’s failure to obtain adequate evidence was due, at least in part, to the auditor not considering all information provided by the contractor. For each of the 70 selected transactions, the auditor documented in the working papers her reasons for concluding that the contractor did not adequately support the claimed costs. Then, according to the working papers, the contractor provided a rebuttal to each of the auditor’s conclusions and, in many cases, the rebuttal indicates the contractor provided the auditor with additional information or explanations to support the allowability of the claimed cost. However, we found no evidence suggesting that the auditor appropriately considered the additional information or explanations included in the rebuttal.

[Emphasis added.]

In our experience, it is not that the contractor objects to a legitimate audit finding; it is that the contractor objects to the DCAA auditor ignoring the evidence provided in order to reach an inequitable conclusion that is actually contradicted by the facts.

That’s not to say that there was much (if any) legitimacy to these particular audit findings. For instance, the auditor questioned 12 of the 70 sample invoices because “the contractor could not provide any support for the subcontractor’s invoice costs.” We take that to mean that the contractor could not show how the subcontractors’ costs were supported by the subcontractors’ books and records. We don’t mean to disparage anybody’s professional judgment, but that is a stupid audit finding. According to the OIG—

The auditor’s notes … indicated that the auditor would request that the Government audit the invoice costs as the result of [the contractor] not having access to the subcontractor’s books and records. The auditor did request an assist audit … However, the working papers did not indicate if the auditor had appropriately considered the contractor’s explanation, or why the auditor questioned the invoiced costs before receiving the assist audit results.

Indeed.

The appropriate course of action is to request assist audits because the contractor does not have access to the subcontractor’s financial records and cannot (as a rule) be expected to support the subcontractor’s invoiced costs to the same level of detail as the subcontractor can. Yet in this case, the auditor decided to question the subcontractor’s costs for lack of support even though assist audits had been requested and another DCAA auditor would conclude on the allowability, allocability and reasonableness of those costs. That’s not the best professional judgment we’ve ever seen displayed by a DCAA auditor.

Perhaps in recognition that the audit conclusion that zero percent of the claimed costs had been adequately supported was somewhat questionable (pun intended), the FAO ultimately decided to question only 20 percent of claimed costs, instead of 100 percent. It was a merciful gesture but one that the OIG found to lack merit. The OIG found several reasons that use of the 20 percent factor was inappropriate but we liked this one:

… the 20-percent decrement is arbitrary because DCAA lacked a legal, regulatory, or other appropriate basis for establishing the amount of questioned costs it reported and included in the accompanying Form 1. The decrement also failed to provide the contracting officer a rational or otherwise justifiable basis for limiting the potential disallowance to only 20 percent of what DCAA considered to be inadequately supported costs. Thus, the FAO should not have used the decrement to either question the subcontract costs or recommend that the contracting officer disallow them in accordance with FAR. Questioning costs in this manner did not serve a useful purpose to the contracting officer in negotiating a fair and reasonable settlement on the claimed subcontract costs.

Fortunately for the contractor, the Contracting Officer did not sustain the questioned costs. The end result of the audit was favorable, as painful as it must have been for the contractor. All’s well that ends well, we suppose.

So how did this quotidian DCAA audit report of a contractor’s claimed FY 2008 incurred costs come to the attention of the DoD OIG?

Somebody called the DoD Hotline and complained. Somebody alleged that the DCAA did not comply with professional auditing standards, or DCAA policy, when it questioned the subcontractor costs claimed by the contractor. We don’t know who made the complaint.

In the meantime, the auditor has left DCAA. However, there are still thousands of auditors left at DCAA with less than 5 years of experience and with training under questionable management policies. This particular little audit issue was resolved, but other contractors continue to experience similar audit issues every day. One contractor has even filed suit against DCAA, alleging negligence and professional malpractice.

Audit quality starts with use of professional judgment in evaluating audit evidence. Audit quality continues with issuance of conclusions that are supported by evidence. Audit quality includes reviewing all relevant evidence and, perhaps, audit quality includes revising preliminary conclusions when the audit evidence indicates that the preliminary conclusions were wrong.

Until DCAA focuses on audit quality as its number one mission and until DCAA measures and tracks audit quality as its number one metric, meaningful reform at the audit agency will never be achieved. And if no meaningful reform is ever achieved, the defense acquisition stakeholders will find other players to perform the role once held exclusively by the Defense Contract Audit Agency.

 

A Banner Year for Corruption-Related Settlements

E-mail Print PDF

During 2014, the U.S. Department of Justice collected almost $2.4 Billion dollars in criminal and civil actions, according to a recent DOJ press release. And that was just within the purview of the Eastern District of Pennsylvania – that was not the entirety of the DOJ haul, just one piece of it.

You know it’s going to be a good year for the DOJ as a whole. We know: we’ve seen the daily enforcement summaries.

It gotten to the point that we decided to simply stop reporting on the repetitive stories. We were bored, and we assumed our readers were bored as well. Why continue to make a point about the cost of corruption when there is no apparent deterrence from the story? Why continue to argue for investing in effective internal controls when so few companies seem to listen?

Fraud and corruption are endemic, it seems. Bribery and kickbacks are simply part of how business is done. How else can we explain the same story, repeated over and over, ad nauseum, about corporate wrongdoing?

You think we exaggerate? Deal with the following list:

  • December 8, 2014 – Contractor agrees to pay $1.9 million (plus interest) for compliance failures related to its GSA Schedule contract.

  • December 8, 2014 – Supreme Group and its various affiliated companies agree to pay more than $338 million to settle a bevy of allegations. (This one merited its own write-up.)

  • December 10, 2014 – A Dallas, Texas, aircraft maintenance company admits to FCPA violations and agrees to pay $14 million to resolve the bribery charges.

  • December 12, 2014 – The former President, CEO, and Chairman of the Board of the Louis Berger Group pleaded guilty to “conspiring to defraud the U.S. Agency for International Development (USAID) with respect to billions of dollars in contracts over a nearly 20-year period.” Readers may recall our original story on the questionable cost allocation practices of that contractor. Those who wish closure can read the DOJ press release here.

  • December 15, 2014 – An employee of Day & Zimmerman, International – a large engineering contractor – is found guilty of 8 counts of wire fraud related to his attempts to fraudulently obtain $650,000 by creating fictitious subcontractors. This is actually a fairly humorous story (as these things go). The DOJ press release can be found at this link.

  • December 15, 2014 – Contractor agrees to pay $2.5 million (and to relinquish rights to additional withheld contract funds) to resolve allegations related to violations of The False Claims Act. Apparently the contractor’s employee, the Director of Contracts, accepted kickbacks from potential subcontractors in return for awarding them subcontracts. The contractor submitted invoices on its prime contracts for work that was never performed by the subcontractors. Oops!

  • December 16, 2014 – Former employee of contractor is indicted for bribery related to award of contracts to local Afghan firms. Again, the employee under indictment is the former Director of Contracts. What is it with these people? You would think they would have a good clue about the cost of corruption, wouldn’t you?

  • December 18, 2014 – A former employee of Wackenhut Security is indicted for alleged theft of U.S. Government property and money laundering, related to her work at the East Tennessee Technology Park. According to the allegations, the employee received checks as part of her job and converted more than $214,000 of funds she received to personal use.

  • December 19, 2014 – A subcontractor on a federally funded construction project in New York agrees to pay $1,750,000 to resolve allegations that it fraudulently claimed that a disadvantaged business enterprise (DBE) performed work on the project.

  • December 19, 2014 – A jury finds a civilian Navy employee guilty of obstructing a NCIS investigation and making false statements. According to the DOJ press release, “The evidence at trial showed that the NCIS was investigating Ashton for conflicts of interest and using inside government information to advance his business. When Ashton learned about the investigation, he created fraudulent documentation purporting to show that he had fully disclosed his business to Navy authorities and received approval.”

  • December 19, 2014 – Contractor Iron Mountain agrees to pay $44.5 million to settle allegations under the FCA that it violated the requirements of its GSA Multiple Award Schedule contracts in the areas of commercial sales practice disclosure as well as the Price Reductions clause.

  • December 19, 2014 – Lockheed Martin Integrated Systems agrees to pay $27.5 million “to resolve allegations that it violated the False Claims Act by knowingly overbilling the government for work performed by LMIS employees who lacked required job qualifications.”LMIS allegedly used “under-qualified employees” who were billed “at the rates of more qualified employees.”

  • December 22, 2014 – The former owner of a defense contractor is sentenced to 6 months in prison for defective aircraft parts. “In 2013, the [DoD] discovered that the wing pins … might be defective.…Based on this discovery, auditors were dispatched to Phoenix to interview Markson and inspect Action Machine’s books and records.… Markson supplied auditors with a document that appeared to show that a third-party testing company had conducted all of the necessary safety testing on the wing pins. In fact, this document was a forgery created by Markson.”

When fraud and bribery and product substitution and other corruption become the routine, boring norm for a blog such as this one … well, then you know we are all in trouble from an ethics perspective.

Happy New Year.

May the New Year be less ethically challenged than 2014 was.

 

 

Lessons from Sikorsky Aircraft Corp. v. United States

E-mail Print PDF

This is one of those times where we are required to remind our readers that we are NOT attorneys. Our analyses of legal matters are limited to those of laypersons. Any criticisms we level, any fingers we point, at jurists, jurors, or attorneys are likely the result of our limited perspective. Do not rely on our blog articles for legal analysis. (Or much of anything else, really.)

With those caveats in mind, let us now discuss the recent decision by the U.S. Court of Appeals, Federal Circuit, in the appeals of Sikorsky Aircraft Corporation v. United States.

You remember the case, don’t you? We have blogged about the original case before. In fact, there are at least six articles on the case in our news archive. You can use the site’s keyword search feature to find them. To get you started, here’s a link to one article, in which we discuss Judge Lettow’s March, 2013, decision at the U.S. Court of Federal Claims. The title of that article was “Sikorsky Wins CAS 418 Case, But Other Contractors Lose.” The Appellate decision continues that trend.

The Appellate decision was authored by Judge Dyk. You remember Judge Dyk, don’t you? We’ve published some mild criticisms of his CAS-related decisions before. In fact, we were tempted to title this article “Dyk Strikes Again” but we didn’t know how to pronounce the Judge’s last name. Does “Dyk” rhyme with “Strike”? We didn’t know, so we went with the title we went with.

We are not going to recapitulate the gravamen of the parties’ CAS 418-related dispute. A link to our prior article on the dispute is provided above. Sikorsky prevailed at the Court of Federal Claims and the Government appealed to the Federal Circuit. Judge Dyk authored an opinion that affirmed Judge Lettow’s original decision.

But there’s more to the story.

The Appellate decision affirmed several points that are relevant to government contract-related litigation. First, Judge Dyk clearly confirmed that “the government bears the burden of proving Sikorksky’s noncompliance.” This is important because too often DCAA and Contracting Officers want the contractor to prove its cost accounting practices are CAS compliant. Not so. The burden is on the government to prove they are not compliant. That is a critical distinction.

Second, Judge Dyk dismissed the government’s argument that “internal government documents concerning the history of the CAS provisions and other materials which were not published provide support for the government’s argument about the rule’s meaning.” Judge Dyk decided that “those unpublished materials are not relevant to our interpretative task. The CAS standards, like any other regulation, must be interpreted based on public authorities.” (We were interested to see Judge Dyk cite to his own opinion in the infamous Rumsfeld/UTC/Pratt decision as support for his finding today. Stare decisis in action, we suppose.) Further, the Judge declined “to rely on the ambiguous language from the ‘preamble’ to contradict the plain language of the rule itself.’ As we see it, the Judge was saying that, where helpful in interpretation, text from a Standard’s preamble could be used; but in any conflict between a Standard and its preamble, the plain language of the published Standard will control.

A very important aspect of the decision was to better define the nebulous phrase “material amount” with respect to interpreting CAS 418. Sikorsky argued that “material amount” refereed to comparing the costs of supervision or management in the indirect cost pool to the total amount of costs in the cost pool, whereas the government argued that the phrase referred to comparing the amount of the costs of supervision or management to the total amount of supervision or management costs in the entity as a whole. Judge Dyk wrote –

Sikorsky argues … that the relevant inquiry is whether the costs of management or supervision are a material part of the pool as a whole, not whether a given pool contains all of the related management or supervision costs. We agree with Sikorsky that the proper inquiry is whether the costs of supervision and management comprised a material amount of the material overhead pool at issue. …

The next question is whether the costs of management and supervision here were a material amount of Sikorsky’s materiel overhead pool. The government argues that ‘material’ means more than a de minimis amount. We agree with the Claims Court that ‘material’ refers to a significant amount. Sikorsky argues that, applying the correct standard for materiality, managers and supervisors comprised seven percent of the materiel logistics workforce and fourteen percent of the purchasing group staff, and that the costs of management and supervision were [therefore] not a material amount. The government does not argue that these costs … were a significant portion of Sikorsky’s total pool, or that other factors should be used in considering materiality. Therefore, we affirm the finding of the Claims Court that the costs of management and supervision were not a material amount of the total pool costs.

Based on the foregoing, we have a strong legal decision that costs comprising as much as fourteen percent of a single indirect cost pool are not material in amount. This is a significant finding. (Pun intended.)

Judge Dyk also addressed the CDA Statute of Limitations in his decision, though his discussion might be characterized as obiter dicta rather than as being precedential. Readers may recall that we have pleaded for a “bright line” regarding when the CDA SoL clock starts to tick. We didn’t get that bright line in this decision. Instead, we got a bit of a bombshell, as Judge Dyk found that the six-year limitation period is not jurisdictional. Sikorsky argued that the Judge needed to decide on the CDA SoL issue before deciding on the merits of the case; but Judge Dyk disagreed. He wrote –

To be sure, we have previously characterized the six-year limitation in the CDA as jurisdictional … However, our decision … was effectively overruled by the Supreme Court’s more recent decision in Sebelius v. Auburn Regional Medical Center … the latest in a series of Supreme Court opinions that have articulated a more stringent test for determining when statutory time limits are jurisdictional.

Judge Dyk interpreted the CDA SoL as being a filing deadline, which made it a “claim-processing rule” and not jurisdictional. He wrote, “The context of the [CDA] statute also does not suggest that it is jurisdictional. Insofar as it applies to claims by the government, the statute pertains to the submission of a claim by a contracting officer to a contractor, rather than to a government body.” Judge Dyk spent more than 3 pages of the 19 page opinion discussing why his interpretation was correct, but then mooted his discussion by writing “Because we affirm the Claims Court on the merits, we do not address whether § 7103 was satisfied in this case.” Thus, in our view, the effect of the dicta is to muddy the waters even further with respect to interpreting the CDA SoL.”

Sikorsky won once again and, in doing so, helped us better understand how the concept of “materiality” will be applied in CAS-related litigation. However, Sikorsky’s victory did other contractors no favors with respect to better defining and developing a “bright line” for applying the Contract Disputes Act’s Statute of Limitations.

 

 

In Which NASA Prepares to Jettison DCAA Out the Nearest Airlock

E-mail Print PDF

NASA
Kind of a smug headline, we suppose. It’s an exaggeration of course; hyperbole that probably doesn’t accurately reflect the true reality of the situation. And yet it may not be all that far off the mark either. The signs are all pointing that way.

Do you read them the way we read them?

For some time now we have been telling readers that choices made by DCAA’s leadership were going to have consequences. We told readers that DCAA’s new approach to “risk-based” audit selection was going to generate repercussions. We’ve been pointing out that Executive Branch agencies such as the United States Postal Service have deemphasized use of DCAA on a reimbursement basis because of concerns over timeliness and audit quality. We’ve noted that the Department of Defense has started to look for ways to finalize contractors’ billing rates and close-out contracts without waiting for an official DCAA audit report. We’ve reported that the DoD Inspector General has recommended that the Defense Contract Management Agency learn to manage DCAA in a more tailored fashion, with respect to audits of contractors’ Forward Pricing Rate Proposals. We’ve reported that the DoD IG has recommended that DCMA enhance processes and staff training with respect to negotiating new contract awards, because DCAA doesn’t audit as many of those as it used to audit. And we’ve also told readers that the DAR Council is seeking to reduce DCAA’s role in reviews of contractor business systems because reducing DCAA’s role will lead to increased “efficiency and effectiveness” of those reviews.

But that’s not all. We’ve also reported that DCMA has taken on reviews of contractors’ CASB Disclosure Statements for adequacy. We’ve also reported that DCMA Contracting Officers will issue Forward Pricing Recommended Rates on their own if DCAA cannot issue an audit report in time to support the analysis of contractors’ FPRPs. In short, we’ve fairly well documented the diminishment of the universe as measured by DCAA audit scope, and we’ve opined that the tide will continue to ebb in that respect. We’ve even gone so far as to suggest it’s time to let the 50 year-old audit agency go, and replace it with something better.

Thus: this opinion of ours, this reading of the signs and portents, this belief that DCAA is going the way of the dinosaurs and the Dodo Bird—it is really nothing new. It’s been our position on the matter for several years. Sometimes we rant and rave about DCAA ineptitude, and other times we shake our heads and mutter in despair as the state of the Pentagon’s contract audit agency. But we’ve been convinced for some time that the only thing that’s going to save DCAA is a complete regime change.

So when we tell our readers that the NASA Office of Inspector General has issued a report in which it found that “NASA is at increased risk of paying unallowable, unreasonable, and unallocable incurred costs and of losing the opportunity to recoup improper costs because Agency contracting officers rely too heavily on DCAA’s incurred cost audit process,” you may simply mark it up to more of the same ranting and raving in which we’ve been engaging for some time. Or you can read our summary and thoughts of the NASA OIG report and, perhaps, conclude that we may be on to something. Or you can read the report yourself and ignore our thoughts.

It’s all good.

The OIG reported that NASA spends more than $8 Billion each year reimbursing contractors via cost-type contracts. The report noted that contractors with such contracts are required to submit, annually, “an incurred cost proposal outlining their direct and indirect costs.” It noted that “Under the FAR, NASA generally has 6 years to recover unallowable costs from the date the contractor’s adequate incurred cost proposal is submitted.” Since 1969 DCAA has audited NASA contractors’ “incurred cost proposals” and DCMA has provided contract administration services for NASA on a reimbursable basis.

The support DoD provides to NASA does not come cheaply. The OIG reported that “From FYs 2009 through 2013, NASA paid DCMA approximately $204.8 million for contract administration and support services and DCAA approximately $77.5 million for audit services. For FY 2014, NASA anticipates paying DCAA $17.7 million for 150,000 hours of work. Based on DCAA’s 2013 work, we estimate approximately 71 percent of this figure, or $12.6 million, will pay for incurred cost audits.”

What does NASA get from DCAA? According to the OIG: “Between FYs 2009 and 2013, DCAA performed 337 incurred cost audits of proposals submitted by NASA contractors and identified $313.5 million in questioned costs. … Since 2009, the rate of sustainment for questioned costs in NASA contracts has fluctuated between 6 and 71 percent.’

Well, that seems like a good deal, doesn’t it? NASA is paying DCAA roughly $18 million a year and, in return, DCAA is questioning roughly $60 million in contractor costs, of which somewhere between 6 and 71 percent end up as bona fide cost reductions and taxpayer savings. (Even if the average sustainment rate was 40 percent, that would still be a good return on investment for NASA.) So what’s the problem, then?

The problem, according to the NASA OIG, is that “NASA contracting officers relied almost exclusively on DCAA’s incurred cost audit process to identify unallowable, unreasonable, and unallocable costs. Contracting officers we spoke with pointed to these audits as their only means of identifying questioned costs.” And the problem with that reliance, according to the OIG, is that DCAA’s new “risk-based” audit approach “substantially decreases” the number of contractor “incurred cost proposals” that are audited. Many contractor annual proposals to establish final billing rates are never audited because DCAA deems them to be “low risk.”

Because the NASA Contracting Officers rely on DCAA, and because DCAA is letting a substantial number of contractor proposals through unaudited, that means that nobody is looking for unallowable costs. The OIG is (rightfully) concerned that millions of dollars of contractor costs that would previously have been audited and questioned by DCAA are getting through with zero scrutiny, and that NASA will be in the position of reimbursing contractors for costs for which they are not entitled to reimbursement.

Here is the conclusion from the NASA OIG audit report:

NASA contracting officers place an unhealthy reliance on DCAA audits to identify unreasonable, allocable, and unallowable costs charged on NASA’s cost-type contracts, performing little to no additional oversight of costs on the 20 contracts in our sample. In addition, this reliance on DCAA – which has an approximately 6-year backlog in conducting incurred cost audits – has delayed NASA’s ability to timely close contracts and deobligate funds. Moreover, the delays and 6-year time limit to recover funds may affect NASA’s ability to recoup funds improperly charged by contractors. DCAA’s revised incurred cost audit methodology reduced the number of incurred cost audits performed on NASA contracts and under the new procedures only a sample of vouchers submitted for payment on NASA’s cost-type contracts receive a high-level review. Accordingly, NASA cannot afford to rely solely on DCAA to determine whether incurred costs are allowable, allocable, and reasonable and should revise its current processes or develop additional procedures and oversight mechanisms to better safeguard the billions of dollars it spends annually in contract funding.

The NASA OIG made five recommendations intended to help address the foregoing situation. Among those recommendations, we noted the following –

Revise the NASA FAR Supplement 1815.404-2(a)(1)(F)(1) to allow independent public accounting firms to provide supplemental audit coverage for NASA contracts where DCAA currently conducts any contract audit services but cannot be responsive to NASA’s need for an audit.

In other words, revise the regulations to permit auditors other than DCAA to do the job that DCAA has been performing for NASA since 1969.

Are we reading too much into this audit report? Perhaps. Or perhaps we are correctly seeing this audit report as being yet one more indication that DCAA’s management decisions are putting it out of business.

 

The DFARS Forward Pricing Rate Proposal (FPRP) Checklist

E-mail Print PDF

The hard part of any accounting system implementation – especially implementation of an ERP or large-scale accounting system at an entity running a complex business – is not actually implementing the new software. Running the new software may actually be the easiest part of the implementation. The conversion of legacy data is also not likely to be the hard part. Same thing with respect to mapping the old organizational structure to the new org structure. Those tasks are not particularly challenging.

What’s the hardest part of a complex ERP implementation? Just ask anybody who’s been through one of those multi-month wire brush sessions. They’ll almost certainly tell you that the hardest part of their job was change management. We bet they’ll tell you that the hardest part of the accounting system implementation was identifying how the entity would operate in its post-implementation “future state” and then selling those changed practices to affected employees.

Change is hard, which is why meeting the CAS-mandated requirement to disclose changes to cost accounting practice 60 days in advance of their effectivity date is such a challenge.1 For example, say you want to make a prospective voluntary change to cost accounting practice – or what the kids today call a “unilateral change” – and that you want that changed practice to be effective on January 1, which is the start of your new fiscal year. That desired timing means you have to have your revised Disclosure Statement out the door and in the hands of your cognizant Federal Agency Official (CFAO) by not later than November 1.2 Which means, generally, that you have to have your changed practices identified, and the impacts quantified (at a high level), before then—often well before then.

You can’t disclose what you can’t describe, and you can’t describe what hasn’t been identified and approved. Thus, as a general rule of them you need to have the cost accounting practices you will be using next year decisively determined before the end of this year’s Q3. That gives you a month to go from management decision to Disclosure Statement revision and submission.

The problem with the foregoing is that decisions to change cost accounting practices often go hand-in-hand with other budgetary decisions. Frequently, it is an entity’s budgetary constraints that drive the need to make changes to the methods used to measure, assign and/or allocate costs.

From where do an entity’s changed cost accounting practices originate? The notions almost always originate from the top of the entity. Management gets a bright idea to make the changes, either to align with the strategic needs of the business or to adapt to changed business conditions … or (more likely) because somebody’s budget got cut. Although we would like to be charitable and tell you that these high-level strategic and tactical decisions are made throughout the year -- based on monthly variance analyses and dynamic changes to the business environment -- experience forces us to be honest and to write that these types of decisions are very often made at the last-minute in the heat of budgetary battles. That is to say, typically these issues are raised and decided in late November/early December, and not in Q3.

Because the decisions that lead to changes in cost accounting practice are very often made at the last minute, it is unfortunately too often impossible to meet the 60 day advance notification requirement. The regulations assume you have all your financial and accounting ducks in a row, lined up with precision, ready to disclose, on November 1st. But the reality is that, far too often, November 1st comes and goes, and management still hasn’t come to an agreement on how the entity will operate on January 1st. Asking the management team to agree, in advance, on future state run rules, often before any budgets have been discussed (let alone issued) or any financial impacts to the entity from the changes have been calculated, is a very difficult task indeed.

And that’s just the “business as usual” fiscal planning environment; the typical tension between leadership and compliance that exists in “normal” transitions from one fiscal year to the next. The regulations expect and require a 60 day advance notification of all changes to cost accounting practice, whereas the reality of the business environment is that reaching an internal agreement 60 days in advance of the changes is an extremely difficult undertaking and, in some circumstances, damn near impossible.

Which brings us (perhaps by rather circuitous means) to the discussion of the new DFARS FPRP Adequacy Checklist. Let us start by linking to the Federal Register notice. Next, let us remind you that we told you this new Checklist was coming, and we invited you to offer comments to the DAR Council regarding its implementation. In that previous article, we offered some mild criticisms of the proposed DFARS rule. We wrote –

This is another example of bureaucrats fixing a problematic process by adding more processes. We discussed that unfortunate phenomenon right here. DCMA would be better off, in our view, by training up its contracting workforce to restore the lost expertise, and then giving the trained personnel discretion to enter into FPRAs without the burdensome and time-consuming oversight of the current process. DCAA would be better off, in our view, by admitting that contractor FPRPs are not the same as cost proposals submitted to enter into a priced contract, and permitting auditors more flexibility in audit approach. (Establishing firm deadlines wouldn’t hurt either.) Taking an incurred cost audit approach to a SWAG is never going to work out well for either DCAA or the contractor.

The proposed rule is now a final rule and, effective immediately, cognizant DoD Administrative Contracting Officers “shall require contractors to comply with the submission items in Table 215.403-1 in order to ensure that their forward pricing rate proposal is submitted in an acceptable form in accordance with FAR 15.403-5(b)(3).” Moreover, the ACO “should request that the proposal be submitted to the Government at least 90 days prior to the proposed effective date of the rates.” The ACO “shall request that the contractor complete the Contractor Forward Pricing Rate Proposal Adequacy Checklist at Table 215.403-1 and submit it with the forward pricing rate proposal.”

Perhaps some of you read our invitation to offer comments to the DAR Council. Certainly, the rulemakers received public input and discussed it amongst themselves. It seems as if the comments might have actually impacted the final rule in at least one respect, which is always nice even if we believe the final rule is still problematic in some very significant respects that might have been resolved had the Council listened to the imput it received.

As is our wont in such matters, we want to focus less on the final rule and the final Adequacy Checklist and, instead, focus more on the rulemakers’ comments about the public comments. Why? Because you can read the FPRP Adequacy Checklist for yourself – we provided a link for you – but a year from now too many readers are going to forget about the comments. Our approach memorializes the rulemakers’ comments. (It also provides a better opportunity for us to write snarky stuff about their comments, which is more fun for us!)

As you might have guessed from the long-winded introductory paragraphs, our fundamental issue with the new DFARS requirement is the timing. Indeed, according to the promulgating comments—

… respondents claimed that the proposed rule creates unintended and harmful liabilities for contractors. … Requiring companies to submit forward pricing rates at least 90 days in advance of their effective date directly conflicts with TINA and the False Claims Act. … key bases for estimates such as budgets or sales projections may simply not be available 90 days prior to submission of rate proposals. [Ed. Note: We think the DAR Council meant 90 days prior to the effective date.] Beyond that, the budgetary and factual data upon which FPRPs are based (1) may simply not be available 90 days in advance, (2) may be subject to more current data, or (3) may be affected by certain large proposals that may require a resubmission of rates when a contract award would have a significant impact on bases/rates.

The DAR Council pondered those concerns and, with a blasé air typical of those who don’t actually have to live with the rules they write, responded as follows –

Submitting FPRPs 90 days in advance of their effective date is reasonable. The parties (Government and contractor) need time to negotiate forward pricing rates prior to their effective date, which is often the start of the contractor’s fiscal year. Prior to the start of their fiscal year, contractors have established strategic plans and put budgets in place to manage their business. [With respect to concerns about TINA and FCA compliance] [i]t should be understood by the parties that the proposed rates are based on forecasts and contractors must provide updates whenever the validity of the agreement may be affected.

The DAR Council’s position, as expressed in the foregoing paragraph, is ignorant. We don’t mean to be unnecessarily disparaging; we mean that the position is literally based on ignorance. The individuals espousing the position likely have not ever investigated how the FPRP process works from a contractor’s perspective (or, if they did, they have ignored what they learned). As a result, the DAR Council’s position is based on ignorance of the challenges inherent in the contractor’s process of establishing budgets and it is based on ignorance of the timing of how budgets are turned into forward pricing rates. The position is based on ignorance of the number of iterations and the number of management reviews and the input of the Business Development Marketeers and the impact of forward pricing rates on provisional billing rates and the impact of forward pricing rates on contract Estimates-at-Completion (which impacts revenue recognition). Because the DAR Council members are ignorant of all those things (or seem to be), they have espoused a position in which “submitting FPRPs 90 days in advance of their effective date is reasonable.”

No, it is not reasonable. In many cases it is going to be impossible.

And now you may see why we started this article the way we did. We wanted to share just a hint of the challenges involved. Just the tip of the iceberg, so to speak. We didn’t even talk about DCAA audits of forward pricing rates and DCMA reviews of next year’s Disclosure Statement. Those are governmental processes and, as we’ve written before, we believe they are broken. No FPRP Adequacy Checklist is going to fix those broken governmental processes.

While we are on the topic of timing, consider this info-nugget: The CAS regulations and the FAR regulations and the CAS clauses require that voluntary/unilateral changes to cost accounting practice must be disclosed at least 60 days in advance of their effectivity date.3 The intent of that requirement is to give the government sufficient time to review the changed practices and determine whether a cost impact is required. (Let’s be clear that nobody really expect the government folks to actually make that determination within 60 days, but that’s what the regulations say.) Sixty days is deemed to be sufficient time for DCMA to review, for a DCAA audit to be requested if judged necessary, for DCAA to complete its audit and report back to the CFAO, and for the CFAO to make his/her determination regarding how to proceed.

Sixty days.

Yet, the DAR Council wants the contractor to submit its FPRP 90 days in advance.

Ninety days.

Let’s be clear: If the contractor is going to make changes to its cost accounting practices, this new DFARS rule requires the contractor to understand the impact of those changes on its indirect rates at least 30 days before it has to disclose them to the CFAO. It has to know the impact of its management decisions on its cost structure and calculate the resulting indirect cost rates 30 days before it tells the CFAO about them.

And this process seems “reasonable” to the DAR Council.

That’s the big one, at least in our minds. There was some other stuff as well.

To the commenter who “stated the rule does not address the issues associated with the DCAA’s inability to audit industry submissions in a timely fashion,” the DAR Council replied: “Establishment of comment expectations … will promote adequate initial submissions … which will shorten the acquisition cycle making for more efficient negotiations for both contractors and Government.”

Way to respond to the comment directly, DAR Council.

To the commenter who “suggested DCAA should begin auditing the most recent incurred cost submission to gain a thorough understanding of the contractor’s operations necessary to best opine on contractor forward pricing estimates,” the DAR Council replied—

… The Government employs multiple avenues to obtain an appropriate understanding about the contractor’s operations. The Government has a responsibility to perform appropriate review of contractor proposals to establish well-supported negotiation positions and to negotiate effectively to wisely use taxpayer money and to ensure that contract prices are fair and reasonable to both the contractor and the Government. Taxpayers receive a direct tangible benefit from the auditing of FPRPs. Meanwhile, DCAA is working to reduce the inventory of incurred costs audits to become current.

We have so many comments about that paragraph – all of them sarcastic and snarky – that we are literally unable to choose which ones to type. So we’ll just leave that turd of a response here for posterity. Feel free to make your own sarcastic and snarky comments to yourself.

One commenter stated that “DCAA should conduct better and more accurate transaction testing. … Unable to rely on contractor business systems and coupled with not having audited recent contractor incurred cost submissions, DCAA has made detailed testing of large samples of recent incurred cost transactions a part of their FPRP audit program.” Apparently, the thrust of the comment was that, if the DAR Council wanted to make the FPRP negotiation process more efficient and timely, one good place to start would be to have DCAA auditors do “better and more accurate transaction testing” so that the audit cycle time could be reduced. To that cogent suggestion, the DAR Council replied, “… the purpose of the rule is to provide guidance to contractors for the submittal of FPRPs. DCAA’s audit approach is to design cost audits within FPRP audits. DCAA is working to reduce its backlog of incurred cost audits so that the agency can conduct the audits more promptly.”

We swear we are not making this stuff up. They really published that in the Federal Register. Go check and see for yourself if you don’t believe us.

The problem with the response (or at least the most obvious problem) is that it utterly ignores the role played by DCAA in delaying FPRP negotiations. The problem is not that contractors lack guidance regarding how to prepare nicely formatted SWAGs of future years’ costs and indirect rates. No, the problem is that “DCAA’s audit approach is to design cost audits within FPRP audits.” If you fix DCAA’s audit approach instead of worrying about the contractor, you will have gone a long way to solving the problems inherent in the process. Check out the plank in your own eye, DoD, before you worry about the speck in the contractor’s eye.

To the commenter who “suggested” that the DCAA audit process could be made more efficient by relying on “relevant auditing and analysis by others,” such as “the contractor’s internal audit department, other Government oversight organizations … or even other DCAA auditors,” the DAR Council replied, “In order to comply with [GAGAS], DCAA’s audit opinion must be derived from the results of sufficient audit procedures performed on the underlying contractor data.” Again, the response ignored the elephant in the room, which is that somebody in authority needs to be asking whether or not DCAA audits of FPPRs should even be subject to GAGAS. DoD could take the reasonable and supportable position that such reviews will not be performed in accordance with GAGAS requirements, which would be a significant improvement.

On the positive side, the references to FAR Table 15-2 were deleted in the final rule. That’s one nice thing to balance out the negatives we have listed herein.

Other comments received and published by the DAR Council addressed concerns with adding more administrative burdens. The DAR Council was not swayed by those comments. We know that Executive Branch leadership is concerned about the complexity of government contracting and how that complexity acts as a barrier to keep out contractors and thus reduce competition. We wrote about efforts to reverse the situation here. The new OFPP Administrator called for “opportunities for contractors to provide ‘frank, open assessment feedback’ to agencies regarding the agencies’ acquisition practices.”

Meanwhile, the DAR Council continues to add more complexity to existing processes, to add more administrative burdens to an already burdensome process. The DAR Council continues to ignore the real drivers in the process and, instead, continues to focus on the contractor’s role as if that were the sole – or the most impactful – problem.

And while the OFPP calls for “frank, open assessment feedback,” the DAR Council continues to cavalierly dismiss public input, to ignore astute suggestions for process improvement, and to engage in hand-waving instead of pursuing the fundamental and quite necessary job of improving the defense acquisition system. If the Executive Branch leadership really desires a “frank” and “open” dialog with industry, one important step to take might be to make sure public comments are listened to and dealt with in a forthright manner. The DAR Council’s comments on this final rule are a good – but by no means the only – example of why industry is rightfully cynical of the value of that dialog.

 

1 Okay. We admittedly kind of fudged that for the general readership. We know that you know that the actual requirement, as found in contract clause 52.230-6, is “not less than 60 days (or such other date as may be mutually agreed to) before the effective date of the proposed change.” We just thought that was too much detail for the article.

2 Unless you are not a CAS-covered contractor -- in which case, you have a lot more freedom to choose your timing.

3 Yeah, we know. See Note 1, above.

 


Page 120 of 278

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.