Executive Order: Paid Sick Leave
This is not going to be political. We are not going to get involved in any discussions about whether the President of the United States of America has the authority to issue Executive Orders, or whether s/he should issue Executive Orders that may or may not usurp the constitutional role of the Legislative Branch. Let’s just take it as a given that President Obama—like all other Presidents in recent memory—issues Executive Orders from time to time, and employees of the Executive Branch have to follow those E.O.’s. To the extent those Executive Branch employees are policy-makers and rule-makers (and Contracting Officers), those E.O.’s have to be followed. To the extent the E.O.’s impact Federal contractors, they have to be followed as well.
But the implementation of certain E.O.’s can be tricky and the recent E.O. that required Federal contractors to establish paid sick leave programs for all their employees is a good case in point.
The Executive Order doesn’t even have a number, at least that we can see. It was issued September 7, 2015. Let’s briefly recap the E.O. (you can follow the link to see it in its entirety).
Section 1 establishes the policy that Federal contractors will permit “employees [performing work] on [Federal] contracts can earn up to 7 days or more of paid sick leave annually, including paid leave allowing for family care.” The policy doesn’t apply to all companies—just Federal contractors. And the policy doesn’t apply to all employees of the contractor—just those performing work on a Federal contract. Presumably, we can infer this means all contractor employees whose labor is charged to a Federal contract either as a direct cost or as an indirect cost. But the policy is somewhat ambiguous in that regard.
Section 2 is the meat of the E.O. It first requires Executive Branch departments and agencies to “ensure that new contracts, contract-like instruments, and solicitations” must include a clause “which the contractor and any subcontractors shall incorporate into lower-tier subcontracts” that specifies “as a condition of payment, that all employees, in the performance of the contract or any subcontract thereunder, shall earn not less than 1 hour of paid sick leave for every 30 hours worked.”
Let’s stop there and see what we’ve got.
The first thing we see is that there will be a new solicitation provision and a new contract clause, and that those new requirements will be incorporated into new solicitations and new contracts. Later on (Section 3) we will see that the new requirements apply to contracts entered into after January 1, 2017. So the requirement cannot apply to existing contracts—unless a bilateral contract modification incorporates the new contract clause post-award. We are not attorneys, but we strongly suspect that if your customer incorporates that new contract clause into your contract post-award, you would be entitled to an equitable adjustment to the original contract price for any increased costs you incurred as a result.
In fact, at the end of the E.O. we found this statement: “This order shall not apply to contracts or contract-like instruments that are awarded, or entered into pursuant to solicitations issued, on or before the effective date for the relevant action taken pursuant to section 3 of this order.” Thus, to the extent your customer attempts to incorporate the new requirement into your contract via post-award contract modification, you would have good grounds to tell your customer that s/he was actually violating the E.O. by trying to implement it retroactively.
Also, in Section 2 we see the basic benefit: Covered employees (i.e., those performing, or who will be performing, on a Federal contract that contains the requirement) must “earn” not less than 1 hour of paid sick leave for every 30 hours they work. To the extent you have covered employees who do not currently earn paid sick leave, you must now extend to them that benefit. You can do more if you’d like, but that is the new minimum benefit requirement.
Section 2 also provides details regarding that basic benefit.
-
The accumulated paid sick leave can be capped at 56 hours, but not less. In other words, if you like, the employee benefit can stop once the employee has accumulated 56 hours of paid sick leave. But until that floor is reached, the basic benefit continues to operate.
-
The accumulated paid sick leave benefit can be used for a wide variety of reasons. For most of us, our bosses don’t check too closely as to our rationale for using sick leave. (In our experience, the simple explanation “I need to stay home to clean my gun collection because the voices in my head told me to” is usually good enough for most bosses.) However, if you are the kind of employer or kind of boss who doesn’t want an employee misusing that precious sick leave benefit, then Section 2 establishes the kind of things for which the benefit may be used.
-
An employee can use the benefit whenever s/he needs to, and “the use of paid sick leave cannot be made contingent on the requesting employee finding a replacement to cover any work time to be missed.” Thus, it’s up to the boss to keep the work progressing while the employee is on sick leave. That implies there needs to be some thought given to workforce staffing and contingency planning. (Efforts which, by the way, you should be doing in any case, regardless of this E.O.)
-
There are some other requirements regarding when and how an employee requests paid sick leave, but they don’t seem especially bureaucratic. “Paid sick leave shall be provided upon the oral or written request of an employee that includes the expected duration of the leave, and is made at least 7 calendar days in advance where the need for the leave is foreseeable, and in other cases as soon as is practicable.”
-
If the contractor is already covered by the Service Contract Act or the Davis-Bacon Act, then those sets of requirements supersede this E.O. To the extent that the contractor’s paid leave policy under the SCA or DBA already meets or exceeds the basic benefit requirement, then it need do nothing else. But if the contractor complies with SCA or DBA requirements, and the paid leave benefit does not meet the basic benefit requirement, then it must do more for covered employees.
-
This part is important. According to the E.O.—“Paid sick leave accrued under this order shall carry over from 1 year to the next and shall be reinstated for employees rehired by a covered contractor within 12 months after a job separation.” Moreover, “Nothing in this order shall require a covered contractor to make a financial payment to an employee upon a separation from employment for accrued sick leave that has not been used.” We’ll discuss the implications of this requirement below because it affects the cost accounting.
Section 3 establishes that the Secretary of Labor will issue the implementing regulations. (You need implementing regulations to define the solicitation provision and the contract clause, and to tell people when they are to use them.) It states that the E.O. requirements are to be effective in contracts awarded after January 1, 2017. Importantly: “This order creates no rights under the Contract Disputes Act, and disputes regarding whether a contractor has provided employees with paid sick leave prescribed by this order, to the extent permitted by law, shall be disposed of only as provided by the Secretary in regulations issued pursuant to this order.” That’s interesting, isn’t it? The rule will be promulgated and enforced by the Department of Labor, even if you are contracting with the Department of Defense or the Department of Energy or NASA. And if you don’t like the way the rule is being enforced, you have no contractual right to appeal the enforcement under the Contract Disputes Act. (Of course, expect the Secretary of Labor to establish an appeal procedure when the regulations are promulgated.)
Section 6 establishes the types of contracts that will be covered by the E.O. It’s a rather broad list, and includes contracts for services or for construction, SCA-covered contracts, DBA-covered contracts, contracts covered by the Fair Labor Standards Act, concession contracts, and to contracts in connection with Federal property or lands. It does not apply to grants, or to “contracts and agreements with and grants to Indian Tribes under the Indian Self-Determination and Education Assistance Act (Public Law 93-638).”
The litany of covered contracts above does not include contracts to acquire supplies, presumably because labor costs are already included in the price being paid for the supply items being acquired. But we assume that the E.O. applies to acquisitions of services, even if those services meet the FAR 2.101 definition of “commercial item.”
Let’s talk about accounting for the new basic benefit. Assuming you have employees that do not have a paid sick leave benefit, how do you measure the benefit cost, and how do you price it into your bids and cost proposals?
As we saw in Section 2 of the E.O., the employee will accumulate sick leave at a minimum rate of 1 hour for every 30 hours worked. That hour has a cost, which is the current hourly rate paid to the employee. In other words, the contractor must recognize a liability (on the balance sheet) and the value of that liability is the accumulated paid sick leave for all covered employees. (We note that as employees receive pay raises, the value of that liability must be adjusted accordingly.) But that’s GAAP accounting. The question is how to recognize that accumulating liability as an expense for government cost accounting purposes.
The key E.O. provision is that the accumulated paid sick leave benefit does not get paid to an employee if s/he departs the company, either through voluntary separation or through lay-off. If the sick leave benefit is not used, the employee forfeits it. Yes, the accumulated sick leave carries over from one year to the next, but there is nothing in the E.O. that creates a non-forfeitable right to the accumulated sick leave. Indeed, as we noted, the E.O. expressly states that the benefit is lost upon separation. If there is no non-forfeitable right then the cost of the paid sick leave is recognized when it is used, not when it is earned. If the employee doesn't use the paid sick leave, there is no cost to be recognized for government cost accounting purposes.
The foregoing guidance is based on CAS 408 (“Accounting for the Costs of Compensated Personal Absence”). 9904.408-50(b) clearly states, “compensated personal absence is earned at the same time and in the same amount as the employer becomes liable to compensate the employee for such absence if the employer terminates the employee's employment for lack of work or other reasons not involving disciplinary action, in accordance with a plan or custom of the employer.” When, as is the case here, there is no non-forfeitable right to the accumulated paid sick leave benefit, then “compensated personal absence will be considered to be earned only in the cost accounting period in which it is paid.” Thus, the cost of the benefit is recognized as it is used by employees, not as it is accumulated on the balance sheet.
Seems relatively straightforward. But over at WIFCON, government contracting practitioners foresee some real problems with implementation of the requirements of this E.O.
For example, Vern Edwards posted—
The biggest problem may well be with subcontractors at the various tiers, especially subcontractors under contracts for commercial items. And what about companies that have both government and nongovernment contracts but that do not provide paid sick leave? How are they supposed to handle this? Do some of their employees get the benefit while some don't? …
Disputes will not be subject to the Contract Disputes Act, but to enforcement by the Secretary of Labor. What kind of enforcement action can the Secretary take? Withholding of payment? Fines? Suspension and debarment?
Those pointed questions are very important. If covered employees are only those who perform (or charge to) a covered contract, then what about the employees who aren’t covered? Will a contractor have a two-tier benefit system, one where covered employees get a paid sick leave benefit while non-covered employees do not? That doesn’t seem right.
And how will prime contractors (and higher-tier subcontractors) ensure their subcontractors are complying with the requirements? Remember, the clause (when promulgated in regulation) will become a mandatory flow-down requirement.
And how will disputes work? That’s going to be interesting.
Mr. Edwards also asked about dollar thresholds. Typically, a clause applies to contract values above a certain threshold, the logic being that the larger the contract value, the more rules with which the contractor will have to comply. But the E.O. says nothing about dollar thresholds, so presumably the E.O. requirements will apply to micro-purchases paid for via procurement cards and/or imprest funds. That doesn’t seem right.
The point of those questions is that the implementation cost incurred by contractors to comply with this E.O (and resulting regulations) will depend on a number of factors, not the least of which is whether all contractor employees are covered, or just the ones working on Federal contracts. That would matter if you are a commercial entity with just a few Federal contracts. If all your employees were subjected to the new requirements, it might well be a case of “the tail is wagging the dog.”
If you are a Federal contractor who will have to start new or enhanced employee benefits in order to comply with this Executive Order, then these are the types of questions you would want to be thinking about right now. Because to the extent you are currently submitting proposals for contracts to be awarded after January 1, 2017, you are going to want to include the cost of the new employee benefit in your bids and/or proposals. And to the extent it’s going to cost you money to implement the new employee benefit, you are going to want to include that cost in your indirect rates so that you will be made whole by your customer for complying with the requirements of this Executive Order.
Too Many Tires Leads to Lawsuit for URS and its Subcontractor
Well, this is awkward.
The Department of Justice recently announced that it had filed a lawsuit that alleged violations of the False Claims Act by URS Federal Services, Inc. and its subcontractor, Yang Enterprises, Inc., with respect to billings under URS’ contract with NASA for facility operations maintenance and support at Kennedy Space Center.
URS, which is now an AECOM company, provides “engineering services and critical technical support to virtually every federal agency, including the Departments of Defense, Energy, State and Homeland Security, as well as NASA, the Intelligence Community and the Environmental Protection Agency.” URS supports the Kennedy Space Center through the KSC Institutional Services Contract, in which “URS personnel support the complex infrastructure and support services necessary to maintain readiness for human space flight, expendable launches, and any other programmatic milestones at the Kennedy Space Center (KSC). We manage and operate the sprawling 4,200-acre KSC complex, including its 900 mission-specific facilities, 16,000 unique NASA systems and equipment, and 600 unique U.S. Air Force systems and equipment.”
Yang Enterprises, Inc. (YEI) describes itself as “a high-technology woman-owned, small disadvantaged company built on a strong culture of ethics, integrity, and a quest for providing our customers the highest level of quality in a safe, timely, and cost-effective manner.” With respect to facility operations and maintenance, YEI asserts that “YEI Systems Engineers monitor failures and conduct root cause failure analysis on critical and non critical systems. This analysis results in recommendations to modify or increase the use of technology which includes vibration analysis, oil analysis, installation of remote sensors, motor analysis, thermographic equipment, and laser alignment to reduce unexpected failures and improve the availability of systems and equipment.” YEI notes on its website that it has “extensive experience” in diverse areas, including “Vehicle/Equipment Maintenance.”
So about that.
According to the DoJ announcement –
In its complaint, the government describes a six-year scheme in which URS and Yang – recipients of over a billion dollars in federal government contracts – systematically defrauded the government. The complaint alleges that URS and Yang, who were responsible for overseeing a General Services Administration (GSA) fleet of approximately 400 vehicles for NASA at Kennedy Space Center, submitted more than a thousand claims for undocumented and unreasonable early replacement of car tires.
The complaint alleges that, between June 2009 and April 2015, URS and Yang submitted $387,000 in false claims to the federal government for payment. During this time period, URS and Yang billed NASA for an unprecedented number of tire replacements, excluding ones for blowouts or catastrophic damage. For example, the government alleges that URS ordered six tire replacements for one vehicle during a 27-month period. Some of these tires had fewer than 5,000 miles of use on them. In some cases, installed tires on government vehicles appeared to have been removed and replaced by inferior tires by the time the vehicle was re-serviced. The government alleges that roughly half of the vehicle fleet for which URS and Yang were responsible had vehicles with tires that did not last 60% of their expected tire life.
Perhaps ironically, YEI was recently named Kennedy Space Center “Small Business Subcontractor of the Year” and received the Marshal Space Flight Center “Small Business Subcontractor Excellence Award.”
But all snark aside, the problem remains that repairs and/or replacement of government-owned property must be strictly controlled, so as to minimize the risk that somebody could allege unnecessary work was performed. Even a topic as prosaic as tire replacement can subject a major contractor to allegations of wrongdoing, as this story demonstrates.
Choosing the correct subcontract type can help to mitigate risks. The trick would be to incentivize superior performance and preventive maintenance, as well as cost control, while reducing purely cost-based incentives. Having a cost-reimbursement material CLIN with minimal (or zero) fee would seem to be indicated in such circumstances.
Also a simple dashboard with key performance indicators, such as number of tires replaced per vehicle managed, or number of quarts of oil replaced per vehicle managed, or number of gallons of gas used per vehicle managed, would be a quick and relatively easy way to spot anomalies that could indicate some kind of scheme was being carried out by a subcontractor.
Tires. Simple tires. So much to learn from simple tires.
|
What is the DCAA Audit Guidance Situation?
The situation is confused. It’s puzzling. And DCAA is not discussing it. So we are left with guesswork and speculation and a frowny face.
We are writing about the current situation with DCAA audit guidance, in case you were wondering.
First, there was the case of the disappearing Memo for Regional Directors (MRD). MRD 15-PPD-002, published by DCAA February 12, 2015, purported to list all the contractors who were late in submitting their proposals to establish final billing rates (aka, incurred cost submissions). We (and other posters) had a lot of fun with the list on LinkedIn because it was so wrong. The list included contractors that had received written extensions, contractors that had already submitted their proposals, and (allegedly) some contractors that didn’t have to submit a proposal at all. It was a lot of fun, and nobody was especially surprised when DCAA yanked that MRD off its website a couple of weeks later.
But it was never replaced.
And since then … nothing.
DCAA has not published a single MRD on its website since that ill-fated MRD 15-PPD-002. Nothing. Bupkus. Nada. Zilch.
Why? We don’t know, nor do we know anybody who knows.
Has DCAA simply stopped issuing MRDs? Our sources say no. DCAA is still issuing audit guidance to its auditors. However, that audit guidance may be for internal use only (i.e., not releasable to the general public). Or perhaps the guidance is releasable … and DCAA is choosing not to release it, for whatever reasons. We don’t know what the situation is.
The only thing we know is that DCAA has not published any new audit guidance on its website since mid-February, 2015 – almost seven months ago. To our knowledge, DCAA has never gone that long without issuing new audit guidance.
Weird, huh?
Another thing that’s weird is that DCAA issued a new Adequacy Checklist for Incurred Cost Submissions (Version 3.0) … and never said a word about it. All you people working on your final billing rate proposal had better review it and figure out what the changes are … because DCAA isn’t going to tell you. And why should they? It’s an internal tool to be used by DCAA auditors. The fact that you and I will use it to make sure our submission is going to be found to be adequate is beside the point. And so now you know and you should use it to help you with your next ICS.
The final weird thing is also hard to understand. Apparently, Chapter 7 of the Contract Audit Manual went missing for a week or two.
The DCAA Contract Audit Manual (CAM), for those who may not know, is the audit “Bible” for DCAA auditors. It contains the agency’s audit policy guidance and DCAA auditors must follow that guidance. (The CAM doesn’t contain the actual audit programs, which are the detailed audit steps. Those are found elsewhere. But it contains a lot of helpful stuff—helpful to both auditor and auditee.) The CAM is “must reading” for anybody who is serious about performing quality contract audits—or who is serious about supporting those audits.
Chapter 7 of the CAM is entitled “Selected Areas of Costs” and covers certain “selected” items of cost and “accounting methods requiring special attention” by DCAA auditors (and contractors). It is a very important part of the CAM. The single chapter is about 220 pages long, and covers diverse topics ranging from leases to insurance, and from selling costs to taxes. For those diverse topics, it establishes which accounting techniques are acceptable and which are verboten. Thus, to think it would disappear is kind of devastating.
But disappear it did, at least for a while.
Darrell Oyer noticed it first, and alerted his newsletter mailing list. He used the disappearance of Chapter 7 as an example of how DCAA had lost its way by focusing on the wrong audit objective. He wrote—
The latest DCAM change removes Chapter 7, which addressed selected areas of cost. … It is difficult to understand why this is a good idea. This guidance seems essential to assuring audit consistency and for the benefit of newly hired auditors. … Removal of valid audit guidance is only logical if your charter has been modified to ‘protect the taxpayer interest’ as opposed to providing profession[al] audit services (based on the regulations). It is difficult to meet the standard ‘protect the taxpayer interest’ if you have to follow rules.
As Assistant Director of DCAA I once had an exit conference with GAO [who was] critical because DCAA selected contracts judgmentally to audit for defective pricing. … GAO insisted that DCAA should be performing a random sample … [because] with a random sample, you can estimate and conclude that there is $xxx billion of defective pricing and you cannot project from a DCAA judgmental sample. That illustrates the difference between what formerly was a DCAA audit and what was then a GAO audit … GAO audited for headlines for the taxpayer; DCAA audited to get taxpayer money back. …
DCAA has gone from professional accountants and auditors who work for the government to government employees who have accounting and auditing experience. … Any auditor should apply the rules of the profession to protect the taxpayer interest, but not toss out the rules and use ‘protect the taxpayer interest’ as the only (and blind objective).
Mr. Oyer was alarmed at the thought of a gradual disappearance of the auditor “rulebook” one chapter at a time, thus freeing the auditors to question any cost that caught his or her eye. (We note that Appendix B of the CAM was cancelled in February 2015, and Appendix E was cancelled in May 2015 … so there was more than one data point from which to plot the line of disappearance.)
But then Chapter 7 was returned to the on-line CAM a couple of weeks later. Mr. Oyer noted that as well in a follow-up email alert. However, the return of Chapter 7 did not assuage his concerns about the direction of the DCAA. After he noted the return of Chapter 7, he wrote: All other comments in the prior newsletter remain operative.
Going Up! (Per Diem and EVMS Thresholds)
Good news, campers!
First, the CONUS maximum per diem rates are going up. The per diems, maintained by the General Services Administration, establish the ceiling of reasonableness for the majority of contractor travel. The GSA per diems are divided into two pieces—lodging and meals & incident expenses (M&IE). Although there are two separate ceilings for employees of the Federal government, contractors are permitted to combine them into one ceiling, and then offset between actual lodging and actual M&IE (assuming the contractor is reimbursing employee travel based on actual cost incurred, which is but one of the options).
Regardless of the details, it’s good news. Here’s what the supplementary information in the Federal Register had to say about it—
The Government-wide Travel Advisory Committee (GTAC) recommended that GSA review the standard CONUS lodging rate annually instead of every three years, and GSA has accepted that recommendation, starting for FY2016 rates. The standard CONUS lodging rate will increase to $89 from $83. The meals and incidental expense (M&IE) rate tiers were revised for the first time since FY 2010. The standard CONUS M&IE rate is now based on the Consumer Price Index (CPI) Food away from home measure, and will be $51 for FY 2016. The M&IE rates for the NSAs continue to be based on survey data from local restaurants in their respective areas, and now range from $54-$74.
The second piece of good news is that the Department of Defense recently issued a Class Deviation to raise the Earned Value Management System (EVMS) review threshold from $50 million to $100 million. This deviation will, we think, tend to reduce the number of EVMS reviews conducted by DCMA personnel, and will tend to reduce the number of EVMS business systems found to be inadequate, which will tend to reduce the amount of contractors subject to mandatory payment withholds for having inadequate EVMS business systems. At last count, nine contractors had EVMS business systems that had found to be inadequate by DCMA.
Why the deviation?
We don’t know for sure, but we suspect DCMA had completed EVM System reviews at the biggest defense contractors, and those contractors had either passed the reviews or had implemented acceptable corrective action plans. DCMA was, in essence, done with the first pass of reviews on the big dogs. The next pass would need to address a whole host of mid-size contractors. It seems to us that, going forward, DCMA would have to make a choice. It would have to either (a) prepare for a significant expansion of the contractor review universe (and increase personnel accordingly), or (b) find a way to limit the contractor review universe to only the largest defense contractors, so that it never had to look at the smaller dogs. (In essence, Option (b) would be a choice to simply ignore the EVMS business systems at the smaller contractors.) By doubling the review threshold from $50 million to $100 million, DoD would seem to have chosen option (b).
If we’ve parsed the bureaucratic logic correctly (and there is no guarantee we have done so), then once again practical resource constraints have impacted the ability of DoD to actually implement the business system compliance regime envisioned by the DAR Council, in response to the proven-by-history-to-have-been-illusory alarmist concerns of the Commission on Wartime Contracting.
Nonetheless, many defense contractors will now be able to stop worrying about DCMA EVMS oversight reviews, except in the rare cases when “the EVM reporting data quality is suspect” or “when the EVM data is not in compliance with one or more of the 32 EIA-748 guidelines.” So it’s not a free pass by any means, but it is good news for the majority of DoD contractors.
Allowable travel costs going up. EVMS review thresholds going up.
We can’t complain about those two things.
|