• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

TINA Sweeps and Defective Pricing (Part 1 of 2)

E-mail Print PDF

Many government contract compliance practitioners are aware of the Truth-in-Negotiations Act (or Truthful Cost or Pricing Data) or whatever the kids are calling it these days (I’m calling it TINA). Whatever you call it, it is really two statutes (10 U.S.C. 2306a and 41 USC 35) —that, together, require contractors to submit (1) accurate, (2) complete, and (3) current “cost or pricing data” under certain circumstances, and then to certify that they have done so. (The statutes define the term “cost or pricing data” but FAR 2.101 also defines that term, as well as the term “certified cost or pricing data”.) The remedy associated with providing “defective” cost or pricing data—i.e., a failure to disclose accurate, complete, and current cost or pricing data when the contractor has certified that it has done so—is specified in the implementing regulations and associated contract clauses. However, as we’ve noted from time to time on this blog, the real kicker comes from being accused of liability under the civil (or perhaps even criminal) False Claims Act for any inflated invoices related to its defectively certified contract price. The False Claim Act penalties are far more severe than the administrative remedies for a mere defective certification.

A contract price that was increased from defective certified cost or pricing data is said to have been “defectively priced,” to the extent that the government negotiators relied on that defective data to establish the contract price. (Our understanding of case law is that defective certified cost or pricing data is presumed to have led to an inflated contract price.) Thus, a common compliance concern is “defective pricing” and many government contractors implement some form of control to minimize their defective pricing risk. Many contractors have implemented “sweeps” to provide assurance that all cost or pricing data has been disclosed. The sweeps are efforts—via phone call and via email and other means—to survey the original cost proposal data inputs to identify any information that has since been updated, so that the updated data can be disclosed to government negotiators prior to certification.

The key requirement of TINA is that all cost or pricing data must be kept accurate, complete, and current not only at the time of proposal submission, but also through negotiations—right up until the “handshake” date upon which final price agreement has been reached. Thus, the risk of defective pricing exists until that date (it actually increases after proposal submission, because the proposal team is often disbanded); but there is no risk after the “handshake” date. Whatever new information comes to light after the date of price agreement is irrelevant to the negotiations, so long as it was not known before that date.

The government has implemented its own processes to identify contractor defective pricing. The most common effort is the “post-award” audit (or whatever they’re calling it these days) conducted by DCAA. DCAA starts with looking at actual contract costs compared to proposed (and agreed-upon prices) and asks if any underruns were intentional—i.e., based on a lack of disclosure of certified cost or pricing data. The risk from those audits has decreased markedly in recent years, since (as we’ve reported) DCAA’s focus has been elsewhere. However, the risk of a civil False Claims Act case that originates with an allegation of defective pricing made by a whistleblower seemingly has increased at the same time, such that defective pricing remains a compliance concern.

But it’s tough to develop a compliance program when you really don’t understand the risks and the risk inflection points.

Vern Edwards recently said that there are not ten people in the United States (outside of attorneys who specialize in the area) who really understand TINA requirements and risks associated with defective pricing. Assuming he’s correct, that means that there are a lot of contractors out there who may be basing compliance efforts on an incorrect understanding. They may be mitigating the wrong risks or they may be mitigating the rights risks but at the wrong time.

So we thought we’d devote an article (or two) to the topic. Not that we necessarily claim subject matter expertise such that we are one of those rara avis people who understand the topic completely. Still: we’ve been doing this for a number of years and have seen some things, and we’ve thought about this a bit. And we’ve had some discussions with top people such as Vern (and Don), who have helped us shape our thoughts into something that we believe will add some value.

The first thing we noticed is that compliance requirements differ between contractor and government personnel. The FAR establishes certain roles and responsibilities for government contracting officers and other personnel involved in negotiations, while applicable solicitation provisions and contract clauses establish another set of roles and responsibilities for the contractor. We thought it might be helpful to first focus on the government’s roles and responsibilities, and then discuss the contractor’s roles and responsibilities (in the second part of this article).

The Government’s Role and Responsibilities

The government contracting officer is required to acquire goods and services at “fair and reasonable prices.” Thus, in a negotiated procurement the contractor’s proposed costs must be evaluated reach a conclusion that the price is reasonable. Generally, the type of data a contractor is expected to provide will be either (1) certified cost or pricing data, or (2) information other than certified cost or pricing data. In competitive acquisitions, price analysis of the offers may be sufficient to determine that the awarded contract price is fair and reasonable, but in non-competitive acquisitions some type of cost data is very likely to be required. However, FAR 15-402(a)(3) cautions contracting officers to only require the minimum data necessary for their determination, stating: “Obtain the type and quantity of data necessary to establish a fair and reasonable price, but not more data than is necessary. Requesting unnecessary data can lead to increased proposal preparation costs, generally extend acquisition lead time, and consume additional contractor and Government resources.”

A contracting officer is prohibited from requiring a contractor to certify its cost or pricing data in certain circumstances (see 15.403-1). Importantly, it is not the contractor who gets to determine whether or not those circumstances are present; that responsibility is given to the contracting officer. (However, if an exception applies but the contracting officer still requires contractor certification, then the certification doesn’t matter: the cost or pricing data will be deemed to be uncertified cost or pricing data. See 15.403-4(c)). Further, even if obtaining certified cost or pricing data is prohibited, the contracting officer may still require the contractor to provide information other than certified cost or pricing data. But for purposes of this blog article we are going to focus on the requirements associated with certified cost or pricing data, because that is where the risk lies.

Unless an exception applies, a contracting officer must obtain certified cost or pricing data for every action (new contract award or modification to an existing contract) that is expected to exceed $750,000 in value. Frequently, contracts are awarded via competition but subsequent modifications are not; and thus the contractor may have to provide certified cost or pricing data at that later time. When a contracting officer is required to obtain certified cost or pricing data, it must be obtained not only from the prime contractor, but also from any subcontractor (at any tier) whose subcontract (or subcontract modification) exceeds $750,000, unless the subcontractor’s contract action is valued at less than 10 percent of the total prime contract action. (See 15.404-3(c).) [Note: this is the contracting officer's responsibility. A prime contractor is required to obtain certified cost or pricing data for all actions that exceed $750,000--period. The prime is required to submit the subcontractor's certified cost or pricing data if the subcontract action exceeds 10 percent of the total prime contract value.]

When certified cost or pricing data is required, it is normally formatted in accordance with FAR Table 15-2 (as discussed at 15.403-5 and as found at 15.408). The format also applies to any subcontractor required to submit certified cost or pricing data. As we shall see, the prime contractor is responsible for updating any subcontractor certified cost or pricing data in addition to its own, and may also be required to perform its own cost or price analysis on that data (and submit that analysis along with other certified cost or pricing data). But regardless of what the contractor does (or does not) do, the government contracting officer is still required to look at the certified cost or pricing data as part of their determination that the price is fair and reasonable. The FAR states (at 15.404-3(a)) that –

The contracting officer is responsible for the determination of a fair and reasonable price for the prime contract, including subcontracting costs. The contracting officer should consider whether a contractor or subcontractor has an approved purchasing system, has performed cost or price analysis of proposed subcontractor prices, or has negotiated the subcontract prices before negotiation of the prime contract, in determining the reasonableness of the prime contract price. This does not relieve the contracting officer from the responsibility to analyze the contractor’s submission, including subcontractor’s certified cost or pricing data.

The contracting officer is responsible for informing the contractor if they learn that any certified cost or pricing data is defective before the agreement on price—regardless of the impact that correcting the data will have on contract price. (See 15.407-1(a). “The contracting officer shall consider any new data submitted to correct the deficiency, or consider the inaccuracy, incompleteness, or noncurrency of the data when negotiating the contract price.”)

In addition, the contracting officer is responsible for establishing and documenting the government’s pre-negotiation objectives and the pertinent issues to be negotiated, as well as for documenting the negotiation via a Price Negotiation Memorandum (PNM). Importantly for this topic, the PNM is required to address the use of certified cost or pricing data. When certified cost or pricing data was obtained, the PNM must address whether the CO –

… relied on the certified cost or pricing data submitted and used them in negotiating the price; recognized as inaccurate, incomplete, or noncurrent any certified cost or pricing data submitted; the action taken by the contracting officer and the contractor as a result; and the effect of the defective data on the price negotiated; or determined that an exception applied after the data were submitted and, therefore, considered not to be certified cost or pricing data.

(See 15.406-3(a)(6).)

Critically, it is the responsibility of the government contracting officer to require the prime contractor to execute a Certificate of Current Cost or Pricing Data (CCCPD) whenever certified cost or pricing data is required. It is that CCCPD that turns mundane cost or pricing data into certified cost or pricing data. It is that CCCPD that creates defective pricing risk. Without a contractor certification, there can be no defective pricing. (But as we will see, a lack of certification, when one was required, is no defense to an allegation of defective pricing.) It is the contracting officer’s responsibility to obtain the executed CCCPD from the contractor, using the exact language and format specified by 15.406-2.

The CCCPD has two important dates: the date it was signed (signing date) and the date it is effective (effective date). The signing date “should be as close as practicable to the date when the price negotiations were concluded and the contract price was agreed to.” The effective date is to be “the day, month, and year when price negotiations were concluded and price agreement was reached or, if applicable, an earlier date agreed upon between the parties that is as close as practicable to the date of agreement on price.” Thus, the effective date can be the handshake date on which price agreement was reached, or it can be a different date if the parties agreed on one. But it is the effective date of the CCCPD that establishes the cut-off point, after which there is no risk of defective pricing.

One final responsibility of the government contracting officer: to insert the appropriate solicitation provisions and contract clauses as required by FAR 15.408. It is those provisions and contract clauses that establish the contractor’s roles and responsibilities, which we will discuss in the next part of this article.

 

The Dangers of UCAs

E-mail Print PDF

Undefinitized Contract Actions (UCAs) are the bane of government contracting.

Nothing_But_TroubleUCAs are government contract actions where performance is authorized to commence prior to the finalization of some aspect of the contract, such as price, terms, or specifications. In other words, the parties have entered into a binding agreement without a final contract. Examples of UCAs are letter contracts and orders under basic ordering agreements, where performance has officially started but no price has been agreed upon.

The regulations addressing UCAs are scarce. DFARS 217.74 implements the applicable statutory requirements and provides guidance to DoD contracting officers. Among other things, it requires each UCA to contain a “definitization schedule”—i.e., a plan for coming to agreement (typically price) in accordance with a schedule. The rules regarding that schedule are that it must provide for contract definitization within either: (1) The date that is 180 days after issuance of the action or (2) The date on which the amount of funds obligated under the contract action is equal to more than 50 percent of the not-to-exceed price.

But that rarely happens. It is a rare (and happy!) event when a UCA is actually definitized within 6 months of issuance. Historically, the government has blamed delays on inadequate contractor proposals. To be clear, UCAs typically require two proposals: the first one to develop the SOW and associated not-to-exceed price, and the second one to definitize the price. Historically, it is the second proposal that has been the perceived problem. At the point the proposal is submitted, the contractor has already incurred some (or a lot) of costs, and the government wants to see and understand those costs as part of reaching a final price. Importantly, this approach differs from the standard Part 15 solicitation/proposal/evaluation/award process, because some aspect of the proposal is no longer an estimate; some aspect is based on known historical costs. And to make matters even more interesting, the contractor continues to incur costs as the government evaluates the definitization proposal and while the parties are negotiating. Thus, the cost data submitted in the proposal is almost immediately obsolete.

The government’s concern with adequate and “qualifying proposals” submitted from the contractor. In fact, the DFARS regulations are quite subjective in defining what constitutes a “qualifying proposal,” requiring that a qualifying proposal is one that “a proposal containing sufficient information for the DoD to do complete and meaningful analyses and audits.” The kicker is that, if the contracting officer determines that the contractor’s definitization proposal is inadequate, then “the contacting officer may suspend or reduce progress payments under FAR 32.503-6, or take other appropriate action.” In other words, failure to submit a qualifying proposal means that, technically, the contractor is in material breach of its contract.

We should also mention that, at many contractors, the cost of preparing and negotiating a UCA definitization proposal is a direct cost of the UCA; that cost is not treated as being B&P. Why? Because, unlike traditional FAR Part 15 proposals for new work, the submission of a UCA definitization proposal is an actual contract requirement—i.e., if the contractor doesn’t submit it, then it is in a material breach of its contract. On the other hand, if you are one of the contractors that treats all proposals as being B&P (which you can do if you want), then a prolonged period of UCA negotiation may blow your B&P budget and end up impacting your G&A expense rate, which could be a problem.

Further, the contractor should expect to see a lower profit when UCAs are used, when compared to a traditional FAR Part 15 contract. The reason for this is that, since some part of the final price is based on actual costs, the contractor’s risk is perceived to be lower than it otherwise would be, thus the contractor would not be entitled to a higher profit.

If the UCA contains the clause 52.216-26 (“Payments of Allowable Costs Before Definitization”) then the contractor will not be receiving payment for 100% of the costs it is incurring while awaiting definitization. Generally speaking, the contractor will be reimbursed for no more than 85% of its allowable costs, without any profit or fee, during the time between commencement of performance and final contract definitization. If the customer doesn’t move quickly to definitize then the contractor could see some cash flow impacts.

Further, the requirement that only allowable costs be invoiced means that the UCA needs to be treated as a cost-type contract, even if the final definitized contract action will be firm, fixed-price. Contractors that are happy with FFP contracts but unprepared for cost-type contract requirements are in for a shock if they receive a UCA—and that is likely a significant cause for many inadequate or non-qualifying contractor proposals. Those contractors had proposed—and thought they were receiving—a FFP contract award, and they were unprepared for receipt of a cost-type UCA that came with audit rights. Remember, award of a cost-type contract requires a finding that the contractor has an adequate accounting system, whereas award of an FFP contract does not have that same requirement. Thus, many contractors’ accounting systems may not support accounting for a UCA or developing a “qualifying” proposal suitable for fact-finding and negotiation.

For all the above reasons, we dislike UCAs. Contractors should try very hard to avoid them. That being said, often a UCA is the only way to go. If the customer tells you “take the UCA or I’ll find somebody else that will” you often have little choice in the matter. Nobody likes to turn down work. So you take the UCA and try to make the best of a bad situation.

Now let’s discuss the business challenge faced by L-3 Communications Integrated Systems (L-3) when it received a UCA that it could not definitize, brought to us by the U.S. Court of Federal Claims, courtesy of Judge Kaplan, in this decision.

L-3 entered into a UCA with the US Air Force to provide training services. To complicate matters, the UCA was for a Foreign Military Sale (FMS) to the Royal Australian Air Force. There were several CLINs in the contract, among which was reimbursement for use of an L-3 training simulator. L-3 was to be reimbursed on a per-hour basis, with separate rates for each operating period of the UCA. The UCA was awarded September 5, 2014 and the parties entered into definitization negotiations on December 18, 2014, after L-3 submitted a qualifying proposal containing a Standard Form 1411.1 The parties reached agreement on all CLIN pricing, except for X031 and X032. After months of negotiations, the parties were very far apart regarding the per-hour simulator reimbursement rate.

Despite L-3 providing additional information to support the reasonableness of its proposed simulator prices, the Air Force refused to budge. The negotiators stated that “the government could not justify any more movement on the prices” even though L-3 thought it had provided them with that justification. (We assume the Air Force negotiators felt some special obligation to the Australians to get for them the best deal possible.) The Air Force negotiators stated that if L-3 wouldn’t agree to the lower hourly prices, then it would have “no choice” but to definitize the pricing via unilateral action.2

As Judge Kaplan wrote, ”On October 29, 2015, the Air Force issued Amendment PZ0001 ‘unilaterally definitizing the UCA.’ In it, the Air Force stated that the amendment was issued in accordance with ‘DFARS 252.217-7027(c) ‘Unilateral.’’ Importantly, the unilateral contract mod clearly stated that it was being issued “subject to contractor appeal as provided in the contract’s Disputes clause. So it was probably not a surprise when, nearly a year later, L-3 filed its appeal with the CoFC, alleging that the unilateral contract modification was “was arbitrary, capricious, and unreasonable in that it denied L-3 PID a reasonable rate of return on the Simulator CLINS, not covering the cost to perform these line items, let alone provide for a reason[able] profit, in violation of FAR Subpart 15.4.”

Unfortunately for L-3, the company made a crucial mistake in its approach to appealing the modification: it had failed to receive a formal Contracting Officer Final Decision (COFD). It had nothing to appeal. Now, you and I might think that a unilateral contract mod that cited the Disputes clause was a COFD, but we would be wrong. The Disputes clause and related legal requirements, and legal precedent, establish a very formal structure to these things—and one of the required steps is for the contractor to first submit a certified claim to the contracting officer. If the CO rejects that claim, then that is a COFD that can be appealed. But L-3 never submitted that claim; it went directly to the CoFC—and that mistake caused its case to be tossed “without prejudice.” Thus, L-3 is free to now submit its certified claim to the CO, have it be rejected, and to then refile its appeal with the Court.

The problem with that situation is that L-3 will be incurring double attorney fees (all of which are unallowable pursuant to the cost principle at 31.205-47). So L-3 may think twice about its next steps. We also hope that L-3 will think twice about accepting any FMS-related UCAs in the future. In fact, we hope that L-3 (and other government contractors) think twice before ever accepting a UCA, because they tend to be more trouble than they are worth.

 

1 The SF 1411 was cancelled in 1997. We find use of the form in 2014 to be inexplicable and a little bizarre.

2 At this point, L-3 had been performing under the UCA for more than a year. Obviously, the USAF was under some pressure to definitize the UCA (since at that point they were likely in violation of the statutory requirements). Still, the USAF likely still had some choices about how to proceed, including escalating the matter to a higher contracting authority for resolution.

 

Paying the Pension Piper

E-mail Print PDF

Lockheed Martin has recently received $13.2 million from the US Air Force to compensate it for impacts to pension plan accounting.

No big deal, right?

What’s $13 million compared to the half-a-trillion overall defense budget?

We get that. We really do. From a pure materiality perspective, this is hardly worth reporting.

But from another perspective—looking at bad decision-making and failed leadership—this is an event worth noting.

This blog has reported, several times, on the liability created more than 10 years ago when CAS 412 and 413 were revised to address the impacts of the Pension Protection Act. For example, here’s a link to an article we published in 2012—more than five years ago!—reporting that DoD had failed to account for contractor pension liabilities potentially worth billions of dollars. We quoted from various news sources, some of whom were themselves reporting quotes from then-DoD Comptroller Robert Hale, who implored contractors to “work” with the DoD in “tight fiscal times” to minimize impacts from the pension accounting rule changes.

The key point of this story is that DoD was aware, from the beginning, that the rule changes were going to result in an increase in pension plan costs. DoD was aware and not only did nothing about it, but actively prevented contractors from including estimates of the increased pension costs in their cost proposals. Thus, liabilities that could have been covered via obligation using funds from 10 years ago must be covered with today’s current period funds.

As if funds were somehow going to be less tight in 2016 and 2017 than they were in 2006 and 2007.

There’s some good news here, not that anybody at DoD should try to claim credit for it. The good news is that the stock market has done extraordinarily well since the financial meltdown in 2007 and 2008. Thus, by kicking the can down the road for a decade, the impact was minimized. Instead of an impact measured in billions of dollars, we are seeing one measured only in millions.

How lucky for us all—especially the warfighters who would otherwise have been significantly impacted by this bureaucratic tomfoolery.

Last year we reported that Boeing received $22.6 million from the US Air Force to cover its additional pension plan costs.

Now Lockheed has received $13.2 million—also from the US Air Force—for its additional pension plan costs. In the words of the Pentagon announcement, “This sum reflects the total of the individual contract adjustment to which the contractor is entitled as result of the impact of the PPA on its affected contract with the U.S. government and Air Force Space Command.”

Interestingly, the announcement stated that the payment amount was being funded from “missile procurement; and research, development, test, and evaluation funds” related to Government Fiscal Years 2010, 2011, and 2012. We didn’t know you could do that. We didn’t know you could obligate funds 5 or more years after the close of the Government Fiscal Year!

But apparently one can, because that’s what was done. We assume it was done via “no-year” money previously authorized for those GFYs, but obviously we do not know the details.

In any case, DoD has now “paid the piper” with respect to two very large defense contractors. There may well have been other payments that we simply missed, or perhaps there are still some payments to come. We would expect Raytheon to receive a payment, given that it is a fully CAS-covered contractor and has an (inactive) defined benefit pension plan (which are the two qualifications necessary to submit a claim). Obvously smaller, non-CAS-covered contractors will not qualify, even if they have a defined benefit pension plan and were otherwise impacted by the Pension Protection Act. (See our article on that issue if you are interested.)

We have other articles on this topic to be found via use of the keyword search feature, for those individuals who are interested in reviewing the history of how we got here. (Search using “pension”.) Our first article was posted in 2010.

Thus, the DoD has been deferring action for a long time. It’s notable that the pension piper is being paid today, and it’s also notable that the payment amount(s) are much smaller than many (including us!) had feared.

 

 

UPDATE: BAE Systems Defective Pricing and False Claims Cases

E-mail Print PDF

The decision to allege that a contractor has violated the False Claims Act when it has “defectively priced” its contract proposal (i.e., violated the Truth-in-Negotiations Act or Truthful Pricing Data Act or whatever you want to call it) has long interested and—truthfully—confused us. See, for example, this article, originally published in 2013. A couple of years later we referenced it in another article discussing a lawsuit filed against BAE Systems Tactical Vehicle Systems (which used to be called Stewart & Stevenson before the acquisition by BAE Systems), in which the government alleged that BAE’s defectively priced proposal (submitted in 2008) had led it to submit false claims. In that latter article we summarized the allegations thusly—

The factual heart of the allegations is BAE Systems’ certified cost and pricing data submitted to the U.S. Army for a contract awarded in 2008 to build 20,000 trucks. Now these trucks were not your commercial Fords or Dodges; instead, these trucks were ‘Family of Medium Tactical Vehicles’ or FMTVs. The FMTV production contract actually goes back to 1996—nearly twenty years ago—when Stewart & Stevenson originally designed and built them at its plant in Sealy, Texas. Stewart & Stevenson held the contract for ten years (between 1996 and 2006, and then the Sealy plant was merged with Armor Holdings, Inc., who held the contract for two years (2006 to 2007). BAE Systems bought Armor Holdings, Inc. in 2007 and merged it into its Land & Armaments Division (which also included the old United Defense manufacturing operations). BAE Systems continued to hold the Army’s FMTV contract until 2010, when it lost it to Oshkosh. (We wrote about that competition and its aftermath here and also here.) In 2011, the final FMTV rolled-off the Sealy production line and the plant was shuttered in mid-2014.

But the fact that the plant was closed and most employees laid-off didn’t stop the DCAA auditors and the Defense Criminal Investigative Service and the Army Criminal Investigation Command and the DoJ’s Civil Division Commercial Litigation Branch from filing suit against the parent company seven years after the alleged violations took place.

Looking back we can now put some (but by no means all) of the pieces together, using ASBCA decisions. Apparently, the cognizant contracting officer had issued a COFD (Contracting Officer Final Decision) and demand for $56 million—in an entirely separate action from the government’s False Claims suit filed in a District Court. BAE Systems appealed that COFD at the ASBCA. The appeal proceeded until the government requested an indefinite stay because of the other litigation. Judge O’Sullivan, writing for the Board, denied that stay—and her decision provided some clues into what had (allegedly) happened.

According to the Board’s decision—

After the May 2008 award of the FMTV contract, the Army and BAE TVS commenced price negotiations, which were concluded on 22 September 2008. On 24 September 2008, BAE TVS executed a Certificate of Current Cost or Pricing Data stating that the cost or pricing data it provided the government during price negotiations were current, accurate, and complete as of 4 September 2008 (the effective certification date). On 15 July 2014, following a post-award audit by the Defense Contract Audit Agency (DCAA), the Army CO issued a final decision finding defective pricing with respect to the FMTV contract and demanding repayment in the amount of $56,386,953 plus interest. …

BAE TVS contests the government's defective pricing allegations in the following major respects: first, it contends that DCAA (and the CO, who adopted DCAA's determinations) used the wrong bill of material (BOM) as the baseline for the defective pricing allegations. While DCAA used a BOM dated 11 September 2008 (which was generated after the effective certification date of 4 September 2008), it should have used the BOM generated when BAE TVS, at the direction of the CO, conducted a ‘sweep’ of cost or pricing data that concluded on 24 September 2008 and incorporated the data from the sweep into a superseding BOM (hereinafter the ‘sweep BOM’) that was disclosed to the Army by uploading it on 24 September 2008 to a file transfer protocol (FTP) website used to share data with the Army during price negotiations.

(Internal citations and footnotes omitted.)

BAE provided several other arguments, among them the assertion that cost or pricing data (e.g., vendor quotes) received after the certification date cannot constitute defective pricing, and the assertion that data incorporated into the “sweep” BOM (i.e., the BOM submitted after agreement on price) cannot constitute defective pricing.

Which is all interesting stuff, and got us thinking about the timing of things with respect to compliance with the “truth in negotiation” contract clauses, and those thoughts will likely show up in a future blog article. But in the meantime, we have learned that the COFD led to a payment demand for $56.4 million, that BAE appealed that COFD, that the government filed a parallel suit in District Court under the False Claims Act, and that the government wanted the ASBCA appeal put on hold while it pursued its civil suit in District Court.

(This situation appears to be similar to that faced by United Technologies Corp., where parallel litigation took place before the ASBCA and at a District Court. In that case, the finding by the ASCBA that there was no defective pricing, because the government had not relied on the defectively priced cost or pricing data, conflicted with the District Court’s finding that the government had been harmed by a false certification.)

In any case, Judge O’Sullivan, as we noted above, denied the government’s request for a stay. So what did the government do in response to that denial?

The contracting officer rescinded the COFD that had alleged defective pricing, the COFD that had led to BAE Systems’ appeal. Accordingly, BAE Systems’ appeal was dismissed by the ASBCA.

As Judge O’Sullivan wrote for the Board—

Where a contracting officer unequivocally rescinds a government claim and the final decision asserting that claim, with no evidence that the action was taken in bad faith, there is no longer any claim before the Board to adjudicate. The government's voluntary action moots the appeal, leaving the Board without jurisdiction to entertain the appeal further.

Thus, the parties will now turn their attention to the District Court, where the trier of fact (and a jury) will attempt to determine whether BAE Systems knowingly submitted a false Certificate of Current Cost or Pricing Data, and whether that allegedly false Certificate created a series of false claims predicated on an inflated contract price. In 2008.

And speaking of ancient history, whatever happened to Boeing and the government’s dispute about EELV pricing? You know, the one where Boeing ended up filing suit against the government? We suspect it’s been settled, but who knows?

If you know the latest status of that EELV controversy, send us an email, would you?

 

 

First Interim Report of the Section 809 Panel

E-mail Print PDF

You review the NDAA in great detail because it tells you what’s coming.

Each year we post an article linking to Bob Antonio’s WIFCON analysis of the NDAA, and we point out things we believe to be of interest.

What’s the NDAA? It’s the annual National Defense Authorization Act, a piece of legislation passed every year that tells the Department of Defense what Congress expects and requires it to do. In Government Fiscal Year 2016, the NDAA (at Section 809) directed the Under Secretary of Defense (AT&L)—a position that was subsequently eliminated by the GFY 2017 NDAA—to establish “an advisory panel on streamlining acquisition regulations.” We noted this requirement in our article on that NDAA, and we wrote that we hoped it went better than other recent USD (AT&L) efforts at acquisition reform.

The quality of the panel’s results will be largely driven by the quality of panelists. With that thought in mind, let’s provide a link to the Panel’s team. The Panelists, aided by a professional staff, have established nine Teams to address acquisition reform ideas—the nine teams are described here. (For example, Team 9 is focused on “modernizing” the Federal Cost Accounting Standards.

The Section 809 Panel has been active for roughly eight months, and just issued its first Interim Report. Along with the Interim Report came a Supplemental Report containing four recommendations at regulatory roll-backs—four “quick wins” or four pieces of “low-hanging fruit” if you will.

We have provided a number of links in this article so that you can see for yourself what the Section 809 Panel is up to. Here are a couple of quotes from the Interim Report that readers may find to be of interest (all emphases in original, internal footnotes omitted):

  • DoD’s focus must be on mission readiness and performance results. The current acquisition system is designed to achieve too many competing ancillary good policies, sacrificing innovation and technological dominance yet adding complexity, cost, and time.

  • The time for superficial conversation and insubstantial changes to regulations and statutes has passed. The global threat is rapidly changing, the relevance of the unique defense industrial base is waning, the processes for acquisition are no longer efficient or effective, and implementing these processes is left to a workforce that is mired in constricted thinking and risk aversion.

Sounds like quotes taken directly from this blog—but they are from the official Interim Report.

Obviously, we shall all have to wait and see what recommendations the Panel ultimately puts forward, and which ones are accepted. We will be looking for those recommendations that create the most push-back from the DoD bureaucracy, which has a strong history of resisting change. We will also keep our eyes on the Team 9 Sub-Panel, to see if they can assist in untangling the Gordian knot that the Federal Cost Accounting Standards have become.

More to follow on this ....

 

 


Page 71 of 278

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.