Limitation of Cost/Limitation of Funds
Many people believe that, when they receive a cost-type contract, they will be reimbursed for all costs incurred on that contract. That belief is wrong. First, the government customer will only reimburse the contractor for allowable costs (as defined at FAR 31.201-2). Costs that are not allowable will not be reimbursed. Second, there are a couple of contract clauses that impose a ceiling on the amount of costs that may be reimbursed, even if those costs are allowable. Those contract clauses are 52.232-20 (Limitation of Cost) and 52.232-22 (Limitation of Funds). The Limitation of Funds clause applies when the contract is being incrementally funded and the Limitation of Cost clause applies when the contract has been fully funded.
In order to have an adequate accounting system for government contracts, a company must show that it can comply with those contract clauses. Accordingly, it is very important that you understand those clauses and comply with them to the letter.
It’s difficult to define the clauses with much specificity, because the contracting officer can tailor them for the individual contract. Suffice it to say that the clauses require the contractor to track its costs (and earned fee) against the amount funded to date (or against the total contract’s estimated cost and fee), and report to the contracting officer before it has incurred a specified percentage of those values. Typically, the contractor must report 60 days before incurring 75 percent of the values, but that’s not a given.
Right away it’s clear that the contractor must be managing its costs and projecting its future expenditures, because if you wait until after you’ve passed the reporting values then you are already in noncompliance with the clause requirements. It’s a difficult challenge, but one that must be met in order to have an adequate accounting system and receive cost-type contracts.
The challenge is even more daunting when one has received an ID/IQ contract with multiple task/delivery orders, each with its own ceiling values. The challenge is even more daunting than that when one thinks the ceiling values are associated with the ID/IQ contract instead of the individual task/delivery orders, but then one is informed by a court that the belief was wrong. Let’s look at the recent Court of Federal Claims decision in the appeal of Interimage, Inc.
Interimage is a small woman-owned IT business, qualified under the 8(a) program to receive special set-aside awards. In 2005, the Naval Criminal Investigative Service (NCIS) awarded Interimage a cost-plus-fixed-fee (CPFF) contract. The contract contained included eleven individual delivery orders.
Interimage performed the work satisfactorily and then submitted a (single) final invoice in the amount of $990,000, which “represented the difference between the amount paid and the amount InterImage claimed it was owed for both costs and fee.” The problem was that NCIS lacked sufficient funding to pay the full amount of the final invoice. Interimage submitted a certified claim in the amount of $695.6K (the amount not paid). The contracting officer agreed but Interimage was unable to obtain payment. Interimage “was told that funding would need to come from other appropriations because the funds to pay InterImage had been de-obligated.”
Subsequently, the Navy asserted that it did not owe Interimage anything more, because “the Navy had determined that InterImage was seeking payment for both costs and fee above various delivery order ceiling limitations.”
Thus, the dispute centered on whether the contract established the limitation of cost/funds values, or whether it was each delivery order that did so. From the decision—
InterImage argues that it is undisputed that the amounts claimed for costs are within the base contract ceiling, as amended, and that the contract, and not the individual delivery orders, is controlling with regard to the contract ceiling limitation. InterImage also argues that the government’s objections to InterImage’s claim for its fee must be rejected on the ground that the government can only change the fixed fee through an equitable adjustment, which was not done. InterImage further argues that the amount InterImage has claimed for the fixed fee is justified based on the total hours of work performed under the contract as a whole.
… the government argues that the individual delivery orders and not the base contract set ceilings for costs and that InterImage is seeking payments above the ceilings set in the delivery orders in contravention of the limitation of cost and funds clauses in the Federal Acquisition Regulations (‘FAR’) and incorporated into the contract and delivery orders. With regard to the fixed fee, the government argues that InterImage’s fixed fee also must be adjusted under the terms of the contract because the delivery orders provide limitations inclusive of fee and because InterImage did not perform the required hours under certain delivery orders and is thus not entitled to the amount of fixed fee now claimed.
Judge Firestone denied Interimage’s motion for summary judgment, finding that there were issues of fact that needed to be adjudicated. In the meantime, she also found that the task/delivery orders established individual values that should be used in lieu of the overall contract values.
One of the problems was how DCAA had audited the contract and documented values in the Cumulative Allowable Cost Worksheet (CACWS). The DCMA Closeout Specialist stated “’[p]art of the issue appears to be DCAA’s audit did not limit the direct and indirect cost to the contract ceiling and funding limitations for each [delivery order] on The Schedule of Cumulative Allowable Cost by Contract.’” He also stated that he believed the DCAA’s schedule of cumulative allowable cost was incorrect in that the worksheet should have included entries for contract ceilings for each delivery order ….”
“DCAA stated that although DCAA had ‘potentially made an ‘error’ on the [cumulative allowable cost worksheet] . . . we all agree that the [cumulative allowable cost worksheet] is only a guideline for the Contracting Officer and the actual contract terms and ceiling limitations hold the ultimate authority.’”
(Contractors who have disputes with DCAA regarding the CACWS should memorize that quote, above, and use it as necessary.)
Long story short: DCAA and the contracting officer were willing to use the values at the overall contract level when establishing how much more Interimage should have been paid, but the more that Interimage complained about the lack of payment, the less willing the government was to see things the contractor’s way. Eventually the CO was switched out and a new DCAA auditor was assigned, and suddenly Interimage owed the government $434,000 instead of the government owing Interimage $700,000! (Interesting to note that the new DCAA auditor was unable to locate the working papers of the previous auditor.)
Perhaps the parties will settle this dispute, now that Judge Firestone has made her ruling. Regardless, this is a good lesson on the importance of understanding contract terms (as well as individual task/delivery order terms) and making sure one is complying with them. Among the various contract terms for which compliance is required, the Limitation of Cost and Limitation of Funds stand out as being some of the most important.
It’s Complicated But Northrop Won
People who don’t know very much about government contract cost accounting and associated compliance rules think it’s just a matter of reading FAR and CAS, and there you go. Just read the rules and follow them. How hard can that be?
People who know more about the topic realize that it’s not only a matter of an individual’s interpretation of the regulations. You also need to have a basic familiarity with judicial decisions that have supplied the official interpretation. You need to understand how judges (particularly those at the Armed Services Board of Contract Appeals and the Court of Federal Claims) have interpreted those regulations and rules. And you probably need to know whether the U.S. Court of Appeals (Federal Circuit) has sustained or remanded those decisions. You don’t need to be a lawyer but it helps to have read a few legal decisions.
People who know a lot about the topic realize just how complex it is. It’s not just all of the foregoing; there are new issues constantly being raised. The truth of the matter is that reality is more complicated than the regulations can possibly envision, and so new issues arise and need to be addressed. It’s a never-ending cycle and people who do this for a living understand just how complicated some of the issues that arise can become.
Today’s article is about one such issue. It’s so complicated that we skipped writing about it in 2014, when the first ASBCA decision was issued. It’s so complicated that we debated for some time before writing about it today, just after the latest ASBCA decision was issued. Finally we decided to acknowledge the decision without getting into the (complex and complicated) details, just as a lesson regarding how deep the government contract cost accounting rabbit hole can go.
At stake was some $253 million dollars. As we’ve stated before, when the government decides to question big dollar costs, contractors will lawyer-up. They will fight. The stakes are too high. This is one of those times where there was so much money at stake that Northrop had to litigate the issue.
Note that we are not lawyers, we are not actuaries, and we are not experts in the accounting requirements associated with Post Retirement Benefits (PRBs). Northrop Grumman was represented by the top-tier inside-the-Beltway law firm of Crowell & Moring, and if you want better information we suggest you reach out to the attorneys who litigated the matter on Northrop’s behalf.
All that being said, here is a brief summary of the facts as we understand them.
- Prior to 1995, Northrop Grumman (NGC) accounted for the cost of its PRB expenses using a method that conformed to the requirements of the 1984 Deficit Reduction Act (DEFRA), using generally accepted actuarial principles.
- In 1995, the FAR was revised at 31.205-6(o). The government’s position was that the revised FAR required NGC to change its PRB accounting methodology, and to fund its PRB liability before filing of Federal income tax returns.
- Between 1995 and 2006, NGC continued to account for its PRB costs using the DEFRA methodology. “NGC documented its accrual costing method in the company's cost accounting standards (CAS) Disclosure Statement that was reviewed and approved by the government. No allegation was made during that period that NGC's accounting for the Plan's PRB costs using the DEFRA method was noncompliant with NGC's disclosed practices or with CAS. Further, during that period, no unallowable Plan costs were identified by DCAA in any audit of the NGC Corporate Home Office final indirect cost submissions for any period between 1995 and 2005 (the last year audited).”
- In 1990, the Financial Accounting Standards Board (FASB) issued FAS 106, which required a different PRB accounting method than was permitted by DEFRA. NGC implemented FAS 106 for financial reporting purposes (as it had to), but continued to use its DEFRA methodology for government contract cost accounting purposes until 2006. Importantly: “NGC's PRB costs calculated during this period were less than the costs would have been had NGC instead used FAS 106 to measure and assign costs.” (Emphasis added.)
- Starting in 2006, NGC entered into discussions with DCMA regarding its PRB accounting methodology. NGC initially proposed continuing to use its DEFRA methodology but, after that approach was rejected, it proposed transitioning to the FAS 106 methodology. NGC attempted to obtain an Advance Agreement for its practices, but DCMA declined.
- The government asserted that, had NGC used the FAS 106 method after 1995 (as it contended FAR 31.205-6(o) required), it would have had higher PRB expenses in those years. In the government’s view, NGC’s methodology shifted PRB costs from past years to future years. Because NGC hadn’t funded its PRB liability in the current period, those future costs were unallowable. “If NGC had used the FAS 106 method instead of DEFRA, the costs assigned to that period [1995 to 2006] would have been approximately $253 million more (the amount of the disallowance) than were assigned under DEFRA.”
- Importantly: “At some future point, costs calculated using the DEFRA method would exceed FAS 106 calculated costs, barring reduction in Plan benefits. NGC's position is that when and if the cross-over occurred, allowable costs would be limited to the amounts calculated using FAS 106 (pursuant to FAR 31.201-2(c)).”
- In the first decision, addressing entitlement only, the Board found that “for government contract accounting purposes, NGC failed to measure, accrue, assign and fund its PRB costs in accordance with FAS 106 and FAR 31.205-6(o) allowability criteria during FYs 1995-2006, prior to NGC's 2006 ‘transition’ to the FAR-compliant methodology.”
- However, in the second decision, addressing quantum (the amount NGC would owe the government for its failure to comply with the regulatory requirements), the Board found that “the government unreasonably interpreted the cost principle and ultimately suffered no damages as a result of appellant's use of DEFRA from 1995-2006 for government accounting purposes because of appellant's 2006 Plan amendment implemented concurrently with NGC's transition to FAS 106.”
See? We told you it was complicated.
Another important point is that DCMA’s own Contractor Insurance/Pension Review experts disagreed with the position taken by DCMA and, ultimately, the government at trial. The DCMA’s own actuarial experts were fine with the methodology that NGC used, and they were not at all worried about cost-shifting.
So where did the disallowance come from? Where did the DCMA’s initial disallowance and Contracting Officer Final Decision come from?
You guessed it.
DCAA.
From the (second) ASBCA decision—
NGC discussed the possible changes with the DCAA auditor who had been primarily responsible for auditing NGC's PRB costs during most of the period at issue. In those conversations, the auditor suggested that the DEFRA method was not compliant with the FAR and that NGC might have created a pool of ‘forever unallowable’ costs by failing to accrue and charge the maximum amount permitted by the FAR.
This is not the first time a DCAA theory has been rejected by a Court, as documented on this blog. When will DCMA contracting officers stop relying on DCAA auditors for anything other than audit findings? We noted that Northrop tried several times to avoid this dispute, but DCMA (possibly spurred on by DCAA) was having none of it. We’re sure that $253 million in questioned costs looked great to Fort Belvoir and was a nice addition to the DoD OIG Semi-Annual Report to Congress, but the fact of the matter is that the auditor’s flawed legal theory—which was contrary to the findings of the DCMA actual experts—wasted millions of taxpayer dollars.
Anyway, let’s wrap this up by quoting at length from the Board’s decision, written by Judge Peacock.
We consider that FAR 31.205-6(o), properly construed, establishes a cost allowability ‘ceiling,’ and focuses on whether the contractor overcharged the government for PRB costs in its relevant cost-related submissions. There is no dispute that for more than a decade preceding the ‘transition’ NGC did not. From the onset of the FAR requirement in 1995 through 2006, NGC's use of the DEFRA method resulted in the contractor annually charging the government less than it could have claimed had it elected to use the FAS 106 methodology for government accounting purposes during those pre-transition years. For that decade, the government unsurprisingly did not object. In fact, the government was well aware that appellant continued to use the DEFRA methodology but repeatedly approved its use as being in compliance with regulatory criteria. …
Interpretation of the provision with respect to ‘quantum’ was not even clear and uniform within the government. The CIPR team's analysis and interpretation differed from that proffered by DCAA and ultimately adopted by the DCE. We consider that the CIPR team correctly interpreted the principle in the first instance. …
The government interpretation advocated in this appeal regarding the pre-transition years also contradicts the general rule regarding the quantum consequences of noncompliance prescribed in FAR 31.201-2(c). That provision states, ‘When contractor accounting practices are inconsistent with this Subpart 31.2, costs resulting from such inconsistent practices in excess of the amount that would have resulted from using practices consistent with this subpart are unallowable.’ Here, NGC failed to comply with the FAR requirement that allowable costs be accrued in accordance with FAS 106 criteria where an accrual methodology was used by the contractor to determine its allowable PRB costs. Although appellant failed to use the proper accrual methodology, there is no evidence or government contention that the amount accrued by appellant pursuant to DEFRA in the pre-transition years exceeded the amount of costs that would have been allowable applying FAS 106 or even an amount calculable for the Plan using the ‘pay-as-you-go’ methodology. In fact, precisely the opposite is true. …
The requisite PRB funding levels (and costs flowing therefrom) are for NGC to determine. … It is illogical and shortsighted for the government to interpret the provision in a manner dictating that appellant must charge or should have charged the government the full FAS 106 amount, where the contractor determines it is not necessary to pay that full amount to attract and maintain a quality workforce. If NGC had done so, presumptively the excess compensation cost would also be unreasonable as beyond its agreement with covered employees as reflected in the Plan. The assignment and funding requirements are designed to protect the government from paying excessive costs. Any ‘failure’ to assign and/or fund, whether the result of the contractor's best business judgment or other factors specific to the contractor, benefits the government. …
Company-specific PRB costs in this appeal are not ‘incurred’ for government contract accounting purposes based on generic FAS 106 requirements established for purposes of cross-corporate financial comparisons and standardized public reporting. Nor is the amount of cost ‘incurred’ for government contract accounting purposes determined by, or equal to, allowability maximums calculable under the FAR. The regulation does not dictate PRB benefit levels and costs contractors must incur. It simply and solely sets a ceiling limiting the PRB cost allowable and payable under flexibly-priced government contracts. …
The government myopically alleges that appellant should have ‘assigned’ more than required by the Plan to each of those years. However, if PRB costs are not incurred, there is no requirement to assign, much less fund, ‘phantom’ costs. There is no evidence or allegation that a major contractor such as NGC would be unable or otherwise fail to fund properly incurred, measured and assigned costs. NGC funds what it properly accrues and assigns. … The regulation must be interpreted in the context of and in conformance with basic accounting principles of incurrence, assignment and accrual. …
The government has failed to sustain its burden of proving that any of the disallowed amount was or will be amortized as part of the transition obligation and claimed during the post-transition years. Its argument is founded on theoretical constructs that have no factual basis or evidentiary support here. In this case, the government's concerns were legitimate, albeit its legal and factual analysis was faulty.
(Emphasis in original.)
So sometimes government contract cost accounting can be complicated. This is one of those times. At the end of the day, Northrop Grumman spent millions of dollars on unallowable attorney fees, money that could have been used to fund IR&D projects or to attract scientists or engineers. The government took time and resources away from fighting overt contractor corruption in order to pursue one DCAA auditor’s legal theory, a theory that had been rejected by DCMA’s own Insurance and Pension experts. However, we need to keep in mind that the matter was complicated and, although the Board found the legal theory to be flawed, the situation was so complicated that it took two decisions over the course of more than three years to get to the answer.
Which may be appealed….
|
Why Companies Don’t Contract with the DOD (Again)
One of the persistent themes on this blog is that the Pentagon is its own worst enemy when it comes to partnering with its contractors. We didn’t seek that theme out; it was handed to us by report after report, from sources such as the RAND Institute and the Defense Science Board. The overwhelming consensus is that the Department of Defense is a bad contracting partner.
Now you can point the finger of blame elsewhere, of course. You can point at legislation that mandates certain business practices. You can mention the Competition in Contracting Act and the Anti-Deficiency Act and the Buy America Act and the Fly America Act and a host of other legislative mandates that force the DOD to do business in a certain way—a way that seems contrary to normal commercial business practices. You can point at the number of bid protests and the number of attorneys salivating at the thought that a contracting officer made a mistake during the Pentagon’s astoundingly long acquisition cycle.1 (Mistakes are common because the rules are so hard to follow.)
You can also note (as we have done in the past) that the Pentagon’s official policy has changed over time. Whereas in the late 1990’s and early 2000’s the Pentagon desired to “partner” with its contractors, the current policy is to maintain an arms-length distance. Some would say that many in the DCMA and DCAA have taken that philosophical change a bit further than intended: moving from a distant contracting relationship to an adversarial relationship.
So, yeah, there’s plenty of blame to spread around but, regardless of whose fault it may be or how we got here, the overwhelming consensus is that the defense acquisition system is broken. As a result, many companies choose not to do business with the Pentagon—companies with whom the Pentagon greatly desires to do business.
The Government Accountability Office (GAO) recently released another study that addressed the barriers that keep the Pentagon from attracting the kind of companies it says it needs. The barriers included:
-
Complexity of the DOD’s [acquisition] process
-
Unstable budget environment
-
Long contracting timelines
-
Intellectual property rights concerns
-
Government-specific contract terms and conditions
-
Inexperienced DOD contracting workforce
None of the foregoing points are new, of course. We’ve heard it before (and we’ve written about it before). Some of those barriers are cultural, others are legislative requirements. Regardless of the rationale, the end result is a business partner who seems to be the partner of last resort. For example, GAO wrote—
… collectively these challenges have created an environment where companies choose to either not pursue DOD business or believe that their resources could be better spent pursuing commercial business where the cost to compete is lower and selection decisions are made faster. For example, 1 of the 12 companies GAO spoke with conducted a cost comparison study and found that it took 25 full time employees, 12 months and millions of dollars to prepare a proposal for a DOD contract. In contrast, the study found that the company used 3 part time employees, 2 months, and only thousands of dollars to prepare a commercial contract for a similar product .
The GAO study goes into more detail about the challenges that deter companies from selling to the Department of Defense. We choose not to repeat the details and invite you to follow the link (above) to see for yourself. We note for the record that DOD reviewed the report and declined to offer any comments.
The GAO study noted that DOD has commissioned several studies (some at the behest of Congress) to see what can be done about the challenges. We’ve written about the Section 809 Panel before. In addition, there is a DOD Regulatory Reform Task Force. Within the Task Force is a subgroup dedicated to evaluating DFARS rules for elimination or reform. The subgroup is seeking input; feel free to help them out.
Meanwhile, the wheels of defense acquisition continue to grind, albeit slowly. For example, here’s a link to a Memo that cautions contracting officers that the “tools and techniques” they use to acquire goods and services for the warfighters “must be thoughtful and deliberate”. It reminds Defense contracting officers that they must “ensure that we have done the necessary due diligence that we are paying a fair and reasonable price….” In other words, while one hand is evaluating reforms that would streamline acquisitions and make contracting easier, the other hand is telling contracting officers to slow down and make sure they are complying with the myriad Byzantine rules associated with defense acquisition.
Sure seems confusing, at least to us.
1 How long is “astoundingly long”? See, for example, Vern Edward’s recent blog article “When a Source Selection Takes Longer than World War II”. (“It is in the CICA requirement to evaluate cost that we find a 19th Century procurement system at work to the Government’s detriment.”)
Small Business Reporting Math Errors Cost Contractor
From time to time Apogee Consulting, Inc. is asked to assist a contractor in the development of its first small business plan. For those who don’t know, most government contracts awarded to large businesses require those large prime contractors to subcontract certain portions of the contract work to “socioeconomically disadvantaged” small businesses. The large prime commits to making a good faith effort to subcontract certain percentages of its contract work to various categories of small businesses. Periodically the contractor has to report the actual percentages it has awarded to each small business category. (See FAR Part 19 and associated contract clauses for more details.)
In a recent ASBCA decision, BAE Systems Southeast Shipyards Mayport LLC (“BAE Systems”) learned that math errors made in calculating its subcontract award percentages cost it more than $1 million dollars of lost award and incentive fees in its naval maintenance and repair contracts.
BAE Systems was dealing with more than the “normal” small business requirements. In order to attain its full amount of award and incentive fees, BAE Systems was required to subcontract out “at least 40 percent of the direct costs of the contract to small business concerns during each fee evaluation period.” If BAE Systems failed to meet its 40 percent goal, then its award and incentive fees would be adjusted downwards.
The issue here was that Atlantic Marine Florida (AMF), a large business, had the only available certified dry-dock suitable for the types of vessels that would be worked on. Thus, if AMF was included in the amount of subcontracted work, then it would be nearly impossible to reach the required 40 percent small business subcontract goal. This issue was raised by multiple offerors during the solicitation phase and the Navy responded by telling all bidders that “offerors will be allowed to exclude the use of the AMF dry-docking facility from the 40% small business subcontracting requirement.”
In the sixth award fee evaluation period, BAE Systems reported subcontracting 40.32 percent to small businesses. However, government reviewers noted errors in the math. BAE System agreed that it had “double-counted” certain costs and revised its calculations.
The revisions included:
The government didn’t care for this math. As Judge Woodrow, writing for the Board, noted:
In calculating the small business utilization for the USS San Jacinto job, appellant excluded the $1,132,854 from the contract cost (the denominator in the formula) but left that amount in the small business cost (the numerator in the formula). This adjustment resulted in a small business utilization percentage of 235.46 percent for the USS San Jacinto job. After these adjustments, appellant calculated its composite small business utilization percentage for all of the jobs included in AFEP 6 to be 44.68 percent. In contrast, the government calculated appellant's composite small business utilization percentage to be 25.96 percent.
(Internal citations omitted.)
The government’s position was summarized as follows:
The government makes two challenges to appellant's calculation of the small business utilization percentage. First, the government contends that appellant should have subtracted the AMF costs from both the numerator and denominator of the fraction. Similarly, in its answer, the government argues that, if appellant is permitted to subtract the AMF costs from the contract cost in the denominator, it also must exclude from the numerator the corresponding costs of second-tier small business subcontractors who performed work for AMF. The government also makes this argument in the COFD, where it states that the subcontracting dollars in the numerator must have a ‘direct correlation and be attributed to the 'direct costs related to production work’’ as contained within the denominator.
(Internal citations omitted.)
The Board agreed with the government’s argument. If BAE Systems excluded AMF costs from the amount of direct contract work, then it must also exclude AMF’s own small business subcontracting dollars from the numerator.
Granted, this was a complicated situation. Most contractors do not count their subcontractors’ subcontract award dollars in their reports. (But that day is coming.)
The point here is that small business plans need to be more than paper. Hitting the commitment amounts involves more than simply attending one or two “outreach” events per year. In order to successfully implement your plan, it needs to be “owned” by somebody in your organization with authority to make it happen, and there needs to be policies and procedures that describe how it will work. Those policies and procedures must be cross-functional, in that everybody who makes a decision regarding which entities receive work must be aware of the overall organizational commitments.
Too often we have seen “paper” plans with no ownership, with no accountability or responsibility or authority, and with little or no policies and procedures that describe their workings. When we encounter such situations, we can say, with a high degree of confidence, that those plans will never be successful.
When we work with contractors to develop their first small business plans, we emphasize the need for organizational accountability and cross-functional “buy-in”—and we urge our clients to develop appropriate policies and procedures to make those plans successful.
It’s the right thing to do.
|