• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

Managing DoD Supply Chain Risk

E-mail Print PDF

The Government Accountability Office (GAO) released a very recent report that addressed the Department of Defense’s attempts to manage risk in its programs’ supply chains. The 2016 National Defense Authorization Act (NDAA) required GAO to report back to the House of Representatives regarding “single sources of supply” for DoD’s major weapon programs (MDAPS). This topic is important because contractors can compare their efforts to manage supply chain risk to the government’s efforts, and perhaps even learn a thing or two in the process.

The first thing that GAO found is that DoD’s 2016 report to the Senate was incomplete. It was supposed to have four elements and it fully addressed only two of them. The other two elements (“Identify risk management actions with associated implementation plans and time lines DOD will take to prevent negative operational impact in the event of a loss of such suppliers” and “Identify severity of operational impact of the loss of such suppliers”) were not fully addressed.

Next GAO found that DoD’s report was without value; most people interviewed didn’t know it existed and wouldn’t know how to use it if they were aware of it. GAO wrote—

… program officials GAO spoke with were not aware of DOD’s 2016 report, and thus did not have information about parts from single-source suppliers that are considered to be most critical, which could provide important focus for managing these risks. Second, program offices often rely on the prime contractor to identify single source of supply risks, among other types of risks, and GAO found that program offices in some instances had limited information to manage those risks because DOD does not have a mechanism to ensure program offices obtain complete information from contractors. Without such a mechanism, program offices may not be aware of risks early enough to take proactive actions to understand and, as appropriate, mitigate those risks.

It is commonly understood that the DoD’s program office is responsible for program risk management. GAO noted that several programs had risk management committees that met on a regular basis. However, GAO found that proactive risk management actions were limited, primarily because most (but not all) program offices relied on prime contractors. GAO wrote –

During our interviews at the selected program offices, numerous officials stated that they expect the prime contractor for their program to identify risks related to a single source of supply and to bring that information to the attention of the program office. However, they acknowledged that they do not have a way to ensure this information-sharing and that they are not fully aware of risks that exist in the sub-tiers of contracts. In contrast, officials from two programs, both of which manage older systems that have long been in the sustainment phase of their life cycle, told us they did not rely on contractors for information on supply risks. Officials from one of these program offices stated that while a contractor can be an important partner, the government should not rely on a contractor to understand and manage risks to the federal government. Also, these officials stated that independent analysis is critical to appropriately manage risk.

GAO found that, although DoD was moving toward addressing DMSMS issues, it was not addressing its other supply chain risks—especially those associated with single sources of supply. (“DOD has efforts under way to obtain better information from contractors on obsolescence risks but not for other types of related risks, such as those stemming from a single source of supply.”)

GAO made six recommendations. Two of the six are as follows:

  • The Under Secretary of Defense for Acquisition, Technology and Logistics, in conjunction with the military departments, should develop a mechanism to ensure that program offices obtain information from contractors on single source of supply risks.

  • The Under Secretary of Defense for Acquisition, Technology and Logistics, in conjunction with the military departments, should issue department-wide DMSMS policy, such as an instruction, that clearly defines requirements of DMSMS management and details responsibilities and procedures to be followed by program offices to implement the policy.

In a shocking coincidence, DoD just announced that it wants its contractors to report to them their supply chain weaknesses. According to this article at Defense News (authored by Aaron Mehta), John McGuinn, (acting deputy assistant secretary of defense for defense, manufacturing and industrial base policy) “is hoping industry will volunteer information on weak spots in their industrial supply chains, as part of a broader review and war-gaming effort to discover potential failure points for America’s defense industrial base.” The article quoted McGuinn as saying “We’re looking for industrial base risks, and those risks include foreign dependency, sole source, single source, fragile suppliers, suppliers that may not be looking to stay in the market….”

The article stated: “To help the study, the Pentagon will shortly release a questionnaire to the defense industry to try and gather information about potential weak spots. The questionnaire, which will be entirely voluntary, will go out with help from trade associations and major industry players.”

Thus, if you are a major industry player, you should expect to receive a questionnaire about vulnerabilities in your programs’ supply chains. The amount of effort you put into your response—indeed, whether you decided to respond at all—is completely up to you. It is not a requirement, which is why should you not expect to be reimbursed for by DoD for your efforts. We wonder about the quality of the information DoD will receive back from its contractors, remembering the old adage that “you get what you pay for.”

So GAO says DoD needs to do more, and that it should ask its prime contractors for information. DoD says it will ask its prime contractors for information, on a voluntary basis. This entire situation was predictable and—indeed!—we predicted it here in this blog.

First of all, and not to toot our own horn overmuch, we have been discussing supply chain risk here for many years. For example, in 2010 we ranted about the importance of supply chain management in this piece. In another, more recent, piece, we discussed counterfeit electronic parts and how effective supply chain management (should) work to proactively manage that risk. So we believe our bona fides are solid in this area. We’ve been sounding the alarm for years, and if effective action hasn’t yet been taken by DoD or its contractors, don’t point any fingers of blame in this direction.

Second, DoD itself has had the action to map out its programs’ supply chains for several years. Remember S2T2? Sure you do! We wrote about it several times…

In May, 2011, Frank Kendall testified before a Senate Subcommittee that—

We have undertaken an aggressive effort to map and assess the industrial base sector-by-sector, tier-by-tier (S2T2). The goal is to understand the gross anatomy of the industrial base. Just as doctors do not seek to understand the functioning of every individual neuron in the central nervous system, the Department does not seek to know the exact details and reasoning behind every supplier relationship. But we do need to better understand the industrial base’s nervous system, circulatory system, and bone structure. … The new S2T2 repository of industrial base data will also serve as a jumping off point for future assessments by all Defense Components, ensuring that data collection and analysis cumulates, thereby increasing the value of all industrial base assessment efforts.

We offered our opinion of Mr. Kendall’s testimony in a separate piece that followed on the report above. We wrote—

… we have our doubts about DOD’s ability to accomplish its stated goals. We have yet to encounter very many DOD contractors that have actually mapped their entire supply chains, program by program, and identified where lower tier suppliers support multiple programs. The burden to execute the S2T2 strategy will likely fall on the DCMA—and we don’t think they’re prepared for it. That said, we agree with DOD that it’s a laudable—and even important—objective that needs to be accomplished.

A year later, we offered a perhaps controversial opinion that the S2T2 initiative—while being well-intended—was flawed. We suspected it might be intentionally flawed. We wrote—

We thought—and still think—that it’s a back-office type approach to doing what is really needed, which is to have every single prime contractor map individual program supply chains via a common format, and then aggregate those program supply chains in a secure database. … It has not yet come to pass because it’s not finished yet. It’s not finished yet because … well, the Report doesn’t say. We assert it’s not finished yet—and may never be finished—because it’s not the right approach. Or because it’s not in the best interest of the (former) IP Directorate to actually complete the initiative. …

So what was formerly the Industrial Policy Directorate is now the Deputy Assistant Secretary for Defense (DASD) for Manufacturing and Industrial Base Policy (MIBP). The office has been promoted up in the DOD hierarchy, the office lead has been promoted, and the “realigned” organization now has a long-term “priority” mission that it can use to drive funding requests.

This, readers, is what success looks like at the DOD.

The fact that the DOD bureaucracy is growing in a time of budget cut-backs, and that there is no tangible output from this long-term “comprehensive process” for identifying weak points in the defense industrial supply chain—and, indeed, that no S2T2 completion date has even been set—should not be used to judge these individuals. They are winning by their own applicable criteria.

And if they ever do issue a comprehensive S2T2 analysis, their importance in the Pentagon foodchain will diminish. Which is, perhaps, one reason that the initiative may not ever make as much progress as we think it should.

So while the DOD bureaucrats are reorganizing, so is the industrial base they are supposed to be analyzing. The industrial base is reorganizing and evolving quickly, in response to the endemic forces of the marketplace. In contrast to the nimble movements of the market, the bureaucrats are progressing far more slowly than we think they should be. And they are perhaps sauntering down the wrong path.

What’s interesting to contemplate is the impact of the market reorganizations on the S2T2 analysis. By the time DOD gets the S2T2 data input into the database (using the approved template), we predict that data is going to be largely obsolete, overtaken by real-life events such as mergers, acquisitions, divestitures, spin-offs, and bankruptcies. By the time the S2T2 analysis is completed—if it ever is—it will describe an industrial base that no longer exists.

But that’s okay.

We’re quite sure that the good folks at DASD (MIBP) will be willing to undertake a new S2T2 analysis, if more resources and funding can only be made available to them.

In conclusion, here we are, more than six years after DoD initiated its critical S2T2 initiative. The last substantive thing we could find on S2T2 is right here. One of the PowerPoint’s conclusions is that “DoD will never have complete Industrial Base visibility.” We agree. The only way to get visibility is to have the prime contractors map their program supply chains – and pay them to do it and to provide that information into a database. DoD: if you want to do this right, you need a new contract clause.

Meanwhile, GAO and DoD act as if S2T2 never existed.

But we remember….

 

 

Contract Closeouts

E-mail Print PDF

Contract closeouts—or the lack thereof—are on the minds of many in government contracting these days. The backlog of contracts awaiting official closeout is mind-boggling on the government side. Government contracting officers are awaiting contractor action, and they are losing patience. On the contractor side, the amount of work and the lack of resources to accomplish that work is a daunting challenge.

The problem is gigantic and it’s government-wide.

Despite the magnitude of the problem, everybody has an excuse for the situation. Everybody has a finger to point at somebody else.

As noted, the government points at its contractors. Prime contractors have a number of reasons for their lack of contract closeout, including (but not limited to): lack of subcontract closeouts, lack of personnel, challenges in reconciling payments made to funding ACRNs, and the general lack of paperwork to help understand the financial status of a contract that was physically completed literally years ago. With respect to those old-dog contracts, personnel turnover has not helped either the government or its contractors; often there’s nobody left who has first-hand knowledge of the contractual situation. We know of at least one contract where the security certification couldn’t be completed because there was literally nobody left who had the clearance to check.

All in all, it’s a huge challenge that both contracting parties are moving to address, albeit in different ways.

The U.S. Government Accountability Office (GAO) recently issued a report that addresses the challenges of contract closeout across the Federal government. GAO staff reviewed the closeout status at five different Federal agencies (including DoD). A telling finding:

None of the five agencies we reviewed had all of the following: (1) centralized data on the number of contracts needed to be closed out; (2) information on where the contracts were in the closeout process; (3) established agency-wide contract closeout-related goals; and (4) established performance measures to assess progress toward achieving these goals.

The expectation is that the agencies will follow the FAR requirements with respect to accomplishing contract closeout. As the GAO noted—

Contracts are generally considered to be physically complete once all option provisions have expired, the contractor has completed performance, and the government has accepted the final delivery of supplies or services. Physically completed contracts should then be closed within time frames set by the FAR—6 months for firm-fixed-priced contracts and 36 months for flexibly-priced contracts. The FAR prohibits the closing of contract files if the contract is in litigation, under appeal, or where the contract is being terminated and termination actions have not been completed. Flexibly-priced contracts take longer to close because additional steps must be taken during the closeout process; for example, audits on costs incurred and settlement of the contractor’s final indirect cost rates.

(Footnotes omitted.)

Four of the five agencies reviewed by GAO used DCAA for contract audit support services. As readers may guess, lack of timely DCAA audit reports was cited as a cause of the inability to timely closeout flexibly priced contracts. For the period in which DCAA was prohibited from performing audit services for civilian agencies, those agencies had to find audit support elsewhere. At DHS, private auditors were put under contract. However, according to GAO, as of July, 2017, DHS had not actually issued any orders to those auditors to perform work. At the Department of State, work was issued to private audit firms and, as a result, two incurred cost reports were received. However, both State and DHS stated that they intended to stick with DCAA as their primary source of contract audit support, regardless of the lack of timely audits. According to GAO, “HHS officials stated that some of their components use DCAA for incurred cost audits, but others are using alternate options such as conducting the audit work internally or contracting out to private firms for audit support services.”

GAO also noted that the civilian agencies have formed a working group to address the issue. As part of its efforts, the working group identified that the civilian agency market for contract audit services is roughly $100 million annually. According to GAO, “the working group is preparing an ordering guide to assist agencies with placing contracts for contract audit related services. The guide, expected to be completed by August 2017, will also identify best practices to address concerns regarding the quality of audits.”

As noted, four of the five agencies in the GAO review use DCAA to perform audit services related to establishing allowable costs and final billing rates for flexibly priced contracts. GAO acknowledged that DCAA has made progress in reducing its gargantuan backlog of incurred cost audits, writing “DCAA has reduced its overall inventory of incurred cost proposals awaiting audit from about 31,000 in fiscal year 2011 to about 14,000 as of the end of fiscal year 2016. Over that same time period, DCAA reduced what it characterizes as its backlog of old incurred cost proposals—those proposals submitted for fiscal year 2013 and prior—from 21,000 to below 5,000.

However, GAO delivered some bad news in the very next sentence, writing—

DCAA did not, however, meet its original goal of having a 2-year inventory of audit proposals—eliminating its backlog of proposals older than 2 years—by fiscal year 2016 and acknowledged that meeting its revised goal to do so by the end fiscal year 2018 will be challenging. DCAA policy officials stated that they were unable to meet the goal of eliminating the backlog due to resource constraints, including workforce challenges, such as hiring freezes. Overall, as of the end of fiscal year 2016, DCAA’s total inventory included 14,208 incurred cost proposals, representing approximately $825 billion in auditable dollar value (ADV).

GAO noted that DCAA’s “low-risk” initiative has contributed to the backlog reduction. The number of “low-risk memorandums” [memoranda?] issued by DCAA is significant. According to GAO, “Since the risk-based initiative was implemented in 2012, DCAA issued a total of 18,292 low-risk memorandums to close out proposals, compared to a total of 9,641 incurred cost audit reports.” In other words, for every official incurred cost audit report that DCAA has issued, it’s issued two low-risk memoranda—i.e., documentation that no audit whatsoever was conducted. DCAA justifies its lack of audits by noting that performing them on smaller final billing rate proposals is a money-loser. GAO wrote that “DCAA reported that even under its risk-based approach, it conducted 767 audits on incurred cost proposals with ADVs of $1 million or less from fiscal years 2014 through 2016, but expended approximately $18 million more in staff resources than the government received by identifying unallowable or questioned costs.” In other words, from a bottom-line perspective such audits should not be performed.

But DCAA is not a for-profit entity. Why is it performing such bottom-line calculations?

Another DCAA initiative is the use of multi-year audits, which DCAA asserts results in a reduction of up to 40 percent of audit staff hours. “DCAA reported that it used multi-year audits to close 1,232 and 1,536 incurred cost proposals, in fiscal years 2015 and 2016, respectively, which constituted about 13 percent and 19 percent, respectively, of the total number of incurred cost proposals closed in those years.” Not reported is the additional cost that contractors may incur in supporting those multi-year audits.

As readers may have guessed, GAO thinks DCAA can do better—and that if DCAA did better then that would help the contract closeout conundrum. For example, GAO wrote—

DCAA’s data for fiscal year 2016 indicate that once a contractor submits an adequate incurred cost proposal, it took DCAA on average 885 days—or nearly 2 and a half years—before DCAA completed the incurred cost proposal audit. Further, our analysis found that DCAA’s backlog of contractor proposals submitted for 2013 and prior years includes 51 adequate proposals that have $1 billion or more in ADV submitted by at least 15 of DOD’s largest contractors for which audits have not been completed. The number of days from the date these 51 proposals were determined adequate ranged from 78 to 2,206 days at the end of fiscal year 2016, meaning that a contractor submitted an adequate cost proposal more than 6 years ago but DCAA has not yet completed the audit. According to DCAA policy officials, staff availability is the primary factor for the delay before starting audit work. For example, proposals closed in fiscal year 2016 waited in DCAA’s queue an average of 747 days before the start of audit work. From the time that DCAA initiated the audit—which it defines as the date DCAA holds an entrance conference with the contractors—it took DCAA about 138 days on average to complete the audit in fiscal year 2016.

(Emphasis added; footnotes omitted.)

GAO concluded that “Assessing and implementing options to reduce the amount of time DCAA takes to begin its incurred cost audit work and establishing performance measures could help DCAA further reduce its inventory.”

GAO noted that about 10 percent of the whiskered proposals are considered to be “inadequate” by DCAA, and about 45 percent of the newer backlog is similarly considered to be “inadequate”. (We put “inadequate” in quotes because the FAR gives contractors considerably more latitude in proposal format and content than the DCAA adequacy checklist does.) GAO wrote “DCAA officials acknowledged that they do not currently have insight into the reasons why DCAA determined that a contractor’s proposal was inadequate, the number of times that a contractor submits revised proposals until it is deemed adequate, or the length of time it takes to receive an adequate proposal ….” However, DCAA reported a couple of initiatives that they thought might help contractors meet DCAA’s expectations in that area. Among the initiatives is a “web-based submission portal for incurred cost proposals that could allow contractors the option to submit their proposals with real time visibility and guidance on common issues.” (Insiders have dubbed this the “Turbo-Tax approach.”)

With respect to multi-year audits, “DCAA would like to continue the use of multi-year audits to gain work efficiencies by combining proposals under one audit. DCAA has not, however, fully evaluated how the process could be improved nor established related performance measures, such as the number of proposals closed, ADV examined, the timeliness of the audits, or its impact on contractors.”

Obviously, GAO focused its attention on Federal agencies and their contract auditors. We’d like to conclude this article by offering some tips to government contractors that might assist them in more efficiently closing-out their government contracts.

1. Start the closeout process 6 months before the expiration of the contracts’ period of performance. Do not let the PMO or the contracts team transfer away before the work is started.

2. See what efforts you can perform on an annual basis. For example, the patent certification should be an annual exercise. Can you similarly make the property certification into an annual analysis? Can you perform the payment to ACRN funding reconciliation on an annual basis?

3. Closing out subcontractors is not as hard as most people want to make it. Technically, you do NOT need official government-audited final indirect rates to closeout a subcontractor’s flexibly priced contract. (See our article on that topic here.) Most of the risks that people are concerned about can be addressed with the proper certifications.

4. With respect to FPIF subcontract, the clause itself says you should not wait for final rates—though if you have them then you should use them. You could also offer an incentive to a subcontractor for prompt closeout: for example, you could offer an additional ½ point of fee if the subcontract is closed within 12 months of physical completion. (You would have to bake this into the subcontract’s terms, but it could be done.) The point is: you can do this if you focus on making it happen.

5. Consider where closeout efforts will be charged. Are they direct costs of the contract or are they indirect costs of the business? If you want to charge them direct, consider how that will impact your ability to close-out the contract. (Hint: you will have to apply indirect rates to those costs.)

All in all, everybody has fallen behind in contract closeouts because it was not a priority for anybody—neither on the government’s side nor on the contractor’s side. So now we are all faced with a mess and it will require an extraordinary effort to clean it up. But it can be cleaned-up, with the right management focus and a little creativity.

 

 

The T&M Payment Clause

E-mail Print PDF

Every government contract has (or should have) a payment clause. The payment clause tells the contractor the government’s expectations regarding what costs can be billed and how they will be billed. If you have a cost-type contract, you almost certainly have the payment clause 52.216-7 (“Allowable Cost and Payment”) that, among many other things, invokes the cost principles of FAR Part 31 to be used in determining what costs will be reimbursed by the government customer. But that’s not the only payment clause: there are other payment clauses for other contract types.

For example, there are at least ten individual payment clauses with prescriptions found in FAR Part 32, ranging from 52.232-1 (“Payments”) to 52.232-10 (“Payments Under Fixed-Price Architect-Engineer Contracts”). There are other payment clauses to be used when progress payments are authorized, and there is another clause to be used when performance-based payments are authorized. There are a lot of payment clauses and the one you have to comply with is the one that’s in your contract. Indeed, your contract may have more than one clause related to payment and you need to comply with all of them.

Have you read your contract’s payment clause(s)? Are you confident that you are fully complying with the requirements of the payment clause(s)?

If you have a T&M contract the payment clause should be 52.232-7 (“Payments Under Time-and-Materials and Labor-Hour Contracts”). Have you read the clause? Are you confident that you are complying with its requirements?

Go look at the date of the payment clause in your contract. With respect to the 52.232-7 payment clause, the date is extremely important. The current clause (as of today) is dated August, 2012. You need to know whether you are required to comply with the requirements of the current clause or the requirements of the previous clause, because the requirements changed. Granted, that was five years ago, so most contracts will have the current clause—but not all of them will, because sometimes the government is slow to modify its contract-writing software and old clauses stick around for longer than they should. If you have the old clause in your contracts, you are lucky. The old clause is more permissive than the current clause. Compliance is easier and disallowance of payments is harder. Go you!

The current clause is quite prescriptive. We are not going to delve into all the intricacies. From a high level the clause breaks billings down to two elements: (1) hourly rates, and (2) materials. (Duh! It’s a T&M contract. What did you expect?) Hourly rates are used for payment “for labor that meets the labor category qualifications of a labor category specified in the contract” that are (a) performed by the contractor; (b) performed by the subcontractors; or (c) transferred between divisions, subsidiaries, or affiliates of the contractor. The clause requires that the hourly rates “shall include wages, indirect costs, general and administrative expense, and profit.” In other words, the “T” part of the T&M contract is a fully burdened through profit “wrap-rate.”

But wait! How can every entity performing the work have the same wrap-rate? Doesn’t each entity have its own direct labor rates, its own overhead rates, and its own profit rates? Yes! You are correct!

If you want to bill subcontractors or inter-organizational transfers under the “T” hourly rate portion of the contract, you must establish a separate billing schedule for each entity in your prime contract. You must submit the entity’s wrap-rates and negotiate the wrap-rates and get those wrap-rates incorporated into the contract. That’s the only way to do it under the requirements of the August, 2012 clause language. (If you have the old clause you have more options. Go you!)

But what happens if you don’t do all that? What happens if the prime contract just has hourly rates for the prime contractor? In that case, the clause requires that the other entities’ labor be billed under as “materials”—under the “M” side of the T&M contract. The clause defines “materials” as including “subcontracts for supplies and incidental services for which there is not a labor category specified in the contract.” If you didn’t specify then you bill the labor as materials, to which you can apply appropriate indirect costs but to which you cannot bill any fee/profit. Yep, you just lost profit on your subcontractors’ or affiliates’ costs. Not good from a financial perspective.

But what happens if you didn’t negotiate individual hourly rates in your prime contract but you billed subcontractor labor as your own prime contractor labor using the prime contractor’s hourly billing rates? In that case, you end up before the ASBCA, just as Access Personnel Services (APS) did. (Link to case here.)

APS is an 8(a) firm, which means it is small and socioeconomically disadvantaged. Perhaps we should not have expected a firm in that position to understand, and comply with, the terms of its T&M payment clause in its Navy contract. However, when DCAA disallowed subcontractor costs, then APS realized the price it was going to pay—and so it appealed to the ASBCA.

Importantly to us the clause in question was the older version (December, 2002) and not the current version. Judge McNulty didn’t think that difference was as important as we would have thought. The fact that APS was represented by its CEO rather than an attorney versed in government contract law may have contributed to the situation.

APS told its subcontractor (PSA) to bill it for hourly labor at the prime contract rates; there were no separate rates for any subcontractor. DCAA audited the contract and issued a Form 1, disallowing six elements of cost. APS appealed only one of those cost disallowances—the disallowance that was based on the difference between the PSA’s hourly rates and the hourly rates that APS used to bill them. There were some nuances in the situation that we are not going to write about; we suggest you read the case.

Judge McNulty, writing for the Board, found that APS was entitled to be reimbursed for its subcontractor costs, but only for its subcontractor’s costs. To the extent APS billed the government for amounts in excess of its subcontractor’s costs, it was not entitled to reimbursement.

Now we have to say—as non-attorneys and as not offering any legal advice whatsoever—that we think the outcome may well have been different, had APS engaged a skilled government contracts attorney to represent it before the Board. We believe that the old clause language is more flexible than the current clause language. Regardless of our beliefs, however, the case was decided how the case was decided.

APS is a small business, socioeconomically disadvantaged. Perhaps we should not expect such a firm to understand its contract requirements, to comply with them, or to know how to defend itself when challenged by DCAA or its contracting officer. Perhaps APS lacked the financial resources to hire a contract administrator, or a consultant, or an attorney.

On the other hand, if APS wasn’t fully capable of complying with the requirements of its contract, then perhaps it is not ready to be a government contractor.

Don’t be an APS.

Read your contract—all of it.

Read the payments clause. Understand it. Comply with its requirements.

Otherwise you might find yourself before the ASBCA, arguing contract interpretation with thousands of dollars (or more!) on the line.

 

 

A Career Move

E-mail Print PDF

Career_MoveJoe’s goodbye lunch was held on Monday. He’s leaving the company after four years, moving on to a much smaller contractor just down the street. He said he wasn’t looking to leave; but when he heard about the position and the compensation, it was too good to refuse. He’s leaving a DCAA support/compliance position and will become a Manager of (General) Accounting, with oversight of Accounts Payable and Payroll.

He’s leaving a year before he would have vested in the company’s retirement plan.

He’s making a career move.

Pat worked for me 20 years ago. Pat was the sole breadwinner for his family but he didn’t have a college degree. He asserted that his job didn’t require one. His assertion was correct! His job didn’t require a college degree—but his career absolutely demanded a college degree. He was never going to move from his current position without one. I counseled him to pursue a degree (after all, the company would reimburse him for the expense), but he resisted. Subsequently, he was at a significant disadvantage when he was laid off and had to look for a new job.

Pat didn’t understand the difference between a job and a career.

Most of us have jobs but a far fewer number of us have careers. The job is what you are currently doing, whereas the career is what you want to be doing the rest of your life. The career is your progression of jobs, moving (hopefully) upwards in terms of responsibility and authority, and compensation and respect. You work your job but you manage your career. One is tactical; the other is strategic. One is right now; the other is long-term.

The job is about right now. It’s about what’s right in front of you. Accordingly, the job requires the ability to listen, to understand, and to execute. In contrast, the career requires vision: the vision to see what isn’t there—but what might be there in the future with the right combination of effort and luck.

Managing your career requires you to be honest in your self-assessment of your current skills, strengths, and weaknesses. Then you need to take action to add to your skills, build on your strengths, and remediate your weaknesses. In Pat’s case, he needed to understand that his career demanded a college degree and that he needed to go get one. In Joe’s case, he understood that his lack of supervisory experience was going to hold him back and that getting that experience was more valuable (in terms of future roles, responsibility, and earnings) than vesting in a retirement plan.

A career move is any change you make in order to advance your long-term career potential. It’s taking a lateral transfer—or even a seeming demotion—in order to gain skills or experience or to remediate a weakness. A career move is an investment in your career. As such, it’s an investment in yourself.

Career moves also require some level of courage—the ability to leave your current comfort zone in search of new challenges. That courage isn’t as common as it should be, and so many people work hard at their jobs without also working hard at their careers.

I’ve been in the work force more than 30 years, either as a corporate employee or as an employee of a very large consulting firm. I’ve run my own consulting firm while maintaining full-time employment as a corporate employee (with the knowledge and approval of my employer and my clients). I’ve made several career moves during that time. I left a large aerospace/defense contractor with an amazing retirement plan in order to join a smaller environmental remediation contractor where I could get more cradle-to-grave experience. I left that small environmental remediation contractor to join a somewhat larger aerospace/defense contractor where I could get supervisory experience as well as other key skills—for no additional compensation. I escaped that contractor to join a multi-national engineering services provider where I learned other skills, including management of contracts and subcontracts. After a while, I had been exposed to so many skills, and had accumulated so much experience, that I was ready to be a consultant. The point is: I was managing my career.

A good boss discusses your career development plan with you. A great boss creates opportunities for you to develop against your career plan. That being said, your career is not the responsibility of your boss.

You need to manage your career. You need to identify what career moves would be helpful and be open to them when they materialize. Sometimes it might mean taking a new position within the same company and other times it might mean leaving the company in search of skills, experience, and responsibility. You need to know what move would be right for your career and you need to have the courage to make the move when the opportunity presents itself.

Are you up to the challenge?

 

Putting the “I” Back in IR&D

E-mail Print PDF

Readers may recall our vehement concern with recent decisions made by the Department of Defense that, taken together, seemed to signal an intent to control contractors’ “independent” research and development (“IR&D” or “IRAD”) efforts. We most recently voiced our concerns last January, in this article. We made some fairly strong characterizations of the policies of then-USD (AT&L) Frank Kendall. We stand by those characterizations.

That article, of course, was but one of many in which we pointed out how the DoD was engaging in a “guerilla war” against its contractors. (The words in quotes weren’t originally ours; we swiped ‘em with full attribution.) We posited in early 2016 that the real objective behind the attacks on IR&D was to obtain contractors’ intellectual property rights without paying for the privilege.

In any case, the most recent article pointed out that Mr. Kendall’s policy was failing, as evidenced by a DFARS Class Deviation that delayed its implementation. And now here we are, nine months later, to tell you that DoD just issued another DFARS Class Deviation that has effectively killed one of Mr. Kendall’s pet initiatives—the requirement that contractors must enter into “technical interchanges” with a DoD official in order to have their IRAD costs reimbursed by the Defense Department.

Yep. It’s dead. And good riddance, too.

The Class Deviation states:

Effective immediately, contracting officers shall not require a major contractor … to engage in or document a technical interchange … as part of the criteria for determining a contractor’s annual IR&D costs to be allowable. … As the result of this deviation, the [DFARS allowability requirements pertaining to such technical interchanges] are no longer a part of the criteria a contracting officer must consider in determining a major contractor’s annual IR&D costs to be allowable.

Well, there you go.

 

 


Page 66 of 279

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.