Most of us in this crazy business remember Executive Order 13771, issued January 30, 2017—literally days after President Trump took office. That E.O. called for executive agencies—including the Department of Defense—to eliminate two old regulations for every new regulation issued. The impact of that E.O. was to effectively freeze agency rule-making while rule-makers sorted things out. Of particular note was the impact to the FAR Councils and, most especially, to the DAR Council. For quite some time after the E.O. was issued, rule-making just … stopped.
Of course, lawsuits were filed. This is America; lawsuits are our national public discourse. One suit called the E.O. "unconstitutional, illegal and stupid." Fourteen states filed amicus curiae briefs, arguing that the E.O. fell within Presidential authority and would benefit state governments. (Bet you can guess which ones filed the briefs.) That suit was dismissed by the DC District Court, which found a lack of standing. (The suit was subsequently revived.)
More recently, another lawsuit was filed, this time by the state of California, joined by the states of Minnesota and Oregon. The suit argues that the E.O. "harms the states by preventing, delaying and discouraging federal regulations addressing public health, safety, and environmental concerns." As far as we know, nobody has yet argued that the E.O. prevents the executives agencies with complying with public laws, such as the annual National Defense Authorization Act, that require new rules to be promulgated—often within specified time limits.
Meanwhile, after years of paralysis, the executive agencies seem to have found a path forward. We’ve noted that the DAR Council has managed to eliminate several regulations in the past year or so. On April 1st, in what was definitely not an April Fool’s Day trick, DFARS Case 2018-D059 was issued as a final rule. The final rule eliminated two words (“general public” and “non-governmental entities”) from DFARS Section 202.101.
But it counts!
On that same day—literally 35 years to the day after the FAR was first issued—the DAR Council also published four other final rules plus an additional three proposed rules. It’s not exactly “2 for 1” but, you know, it’s something. Perhaps nobody will notice.
We are not going to discuss each proposed and final rule in this article. But we will point out one or two that seem to bear some significance.
DFARS Case 2018-D065 (final rule) implements “section 824 of the National Defense Authorization Act (NDAA) for Fiscal Year (FY) 2019, which amends section 893 of the NDAA for FY 2011 … regarding consent to subcontract requirements. Specifically, section 893 requires contracting officers to have written approval from the program manager prior to withholding consent to subcontract for DoD contracts with contractors that have approved purchasing systems, as defined in [FAR] 44.101.” So if you have an approved purchasing system, not only are some actions not subject to consent requirements, but the ones that are should not be held up by a contracting officer unless the program manager agrees. That’s a good thing, in our view.
DFARS Case 2017-D024 (proposed rule) would, if implemented as drafted, “implement [Sections 829 and 830] of the National Defense Authorization Act for Fiscal Year 2017 that requires the preference for the use of fixed-price contracts in the determination of contract type, requires review and approval for certain cost-reimbursement contract types at specified thresholds and established time periods, and requires the use of firm fixed-price contract types for foreign military sales unless an exception or waiver applies.” Essentially, the proposed rule would impose additional approval requirements if a contracting officer believes that an other-than-fixed-price contract type would be appropriate at certain dollar thresholds. Cost-reimbursement contracts valued at more than $50 million would require Head of Contracting Activity (HCA) approval if awarded before 01 October 2019; and cost-reimbursement contracts valued at more than $25 million would require HCA approval if awarded after that date. Also, the proposed rule would mandate that every FMS contract award must be firm, fixed-price (FFP) type.
Is the proposed rule a good thing? Not in our view. It adds an additional delaying step in awards of major weapon system contracts, many of which are often R&D or LRIP—which do not easily lend themselves to fixed-price contracting. For an example of what can go wrong, check out our many articles on Boeing’s KC-46a Pegasus aerial refueling tanker. Further, mandating that every single FMS contract must be FFP implies that no customization can or should be done to the product slated for export. In our experience, that implication is unrealistic.
All that said, the DAR Council is simply following Congressional direction. What can they do? What can you do if you don’t like the proposed rule? Not much. We mean, you can write in, objecting to the rule as drafted. And perhaps you should do so! But we strongly suspect the DAR Council will collectively shrug their shoulders and tell you they are just following Congressional direction. Then the final rule will be promulgated without much in the way of revision. Because that’s how the machine works. (When it works at all.)
Well, that last couple of sentences ends things on a bit of a downer, doesn’t it? We didn’t mean to do that!
In related news, the FAR Councils are years behind implementing SBA rule revisions. We’ll have a blog article on that uplifting topic soon!
Changes: Turn and Face the Strange
Nick Sanders
Lots going on these days. I’m finishing my six-week “Financial Management of Government Contracts” course later this week. I’ve started editing the second LexisNexis reference book. One of my clients is headed into arbitration. And I’ve got international travel coming up in May, June, and July. (That’s three trips, not one long trip.)
Oh, and I should mention that the Society of Corporate Compliance and Ethics has accepted my proposal to present at September’s Compliance and Ethics Institute. My presentation will be entitled “"Taking a Dynamic Approach to Compliance Risk Assessments for U.S. Government Contractors". That presentation has to be created and turned in to the conference staff well before the Institute starts.
Finally, I feel the need to write a couple of blog posts each week. Given the foregoing list of other activities, please forgive me if production slips a bit.
Moving on ….
Today’s article notes recent changes DCAA has made to certain audit programs.
Testing of Paid Vouchers. (Link: here.) Don’t let the name fool you, these can be very tough audits—testing supplier payments, labor and timekeeping, and other direct costs.
Truth in Negotiations Compliance. (Link: there.) As most of us know, DCAA intends to perform more of these audits as the audit agency ramps down from the frenzy associated with “incurred cost submissions” (aka “proposals to establish final billing rates”). Accordingly, we recommend scanning the revised audit program as a refresher.
DCAA also updated audit programs associated with contract terminations. If you have had a recent termination for convenience, we suggest you check out the appropriate audit program.
On Golden Pond
Nick Sanders
If you are reading this blog you may know John Panetta, Sr. You may have interacted with him at a meeting of the AIA Cost Principles Committee. You may have interacted with him at a meeting of the Finance Executives International’s Committee on Government Business. You may have worked with him at THE Raytheon Company (as John would pronounce it).
If you haven’t met John in person, chances are you’ve read some of his precedent-setting cases before the ASBCA and Court of Federal Claims. It is a well-known fact that Raytheon has litigated—and won—many important cases in areas such as CAS cost impacts and cost allowability. Obviously, those areas are smack in the heart of what we write about so, as you may well imagine, we’ve written quite a bit about Raytheon’s litigation victories. (Do a keyword search from the home page.) Most, if not all, of the cases we’ve written about have been personally sponsored by John (in coordination with both internal and external counsel). John was deposed, or personally testified, in many of those cases. Thus, to the extent important precedents were established as the result of Raytheon’s willingness to litigate, we have John to thank in large part.
And if you haven’t met John in person or read the important Raytheon cases he shepherded through many internal and external “hoops” that would have kept a lesser individual from persevering, here’s a chance to see John testify before a Subcommittee of the House of Representatives’ Armed Services Committee (HASC).
Why do we care about Mr. Panetta?
Well, he’s retiring at the end of this month, after 39 years with Raytheon.
39 years.
With the same company.
Who does that anymore?
Most of us work three, maybe five, years, and then we are off to another company, starting fresh with a low vacation accrual. If you’re lucky, you make it seven or eight years, but then your company folds, or is acquired. Your spouse relocates. Whatever; you move on. That’s the way it works nowadays.
According to the Bureau of Labor Statistics, the median job tenure for American employees is 4.3 years. That same study found that “workers in management, professional, and related occupations had the highest median tenure (5.0 years)” and “the median tenure of workers ages 55 to 64 (10.1 years) was more than three times that of workers ages 25 to 34 (2.8 years).”
Putting that all together, you might expect that a professional government accounting SME might last as long as ten years at a single place of employment. But 39 years? That’s six or seven standard deviations off the mean!
How did John accomplish this feat?
Those of us who do this for a living understand how hard the job is. We walk a tightrope between the needs of the business and the needs of compliance. We have to persuade leadership to invest in controls, and in training, and in other things that look very non-value-added because they don’t actually contribute to revenue being generated. Sometimes we have to be the traffic cop, telling program managers “stop” because they are doing something that seems quite reasonable (from their point of view) but is actually a noncompliant practice that could lead to litigation.
Speaking of litigation, it’s a very hard task to persuade leadership to spend the unallowable money necessary to litigate—and to prevail—at a Board of Contract Appeal or at the Court of Federal Claims. There’s a natural inclination to pay a penalty rather than pay for very expensive outside attorneys; and when you add in the perceived risk of upsetting the customers, that inclination becomes an almost unchangeable decision not to litigate.
Mr. Panetta successfully walked that tightrope for 39 years. During that time, he kept his employer relatively free from adverse audit findings and associated disallowances/penalties. He kept the many employees of Raytheon aligned in a culture of compliance. When necessary, he pushed and prodded and persuaded his leadership to “go to the mattresses” and litigate.
I watched him in action for six years. He accomplished all the above by being very, very, technically knowledgeable about the subject matter while at the same time being very good at working within the corporate system. Somehow, he found the right balance between being a FAR/CAS nerd and being a respected member of corporate leadership.
Readers probably don’t know this, but John has been a quiet supporter of this blog for many years. While many people were advising me to shut it down because my opinions were perceived as not being politically correct (in the corporate sense), John was telling me that he was a regular reader who liked what he was reading. After I left Raytheon, I would still get occasional emails from John, encouraging me and telling me what he liked. Given John’s ability to turn a phrase, I have always been proud to hear from him that he liked the use of this word or that sentence, or that he liked the way I tackled a topic. His encouragement mattered and, to some extent, has kept me going over the past decade of blogging.
Now John is riding off into the New England sunset, taking with him nearly 40 years of accumulated wisdom and knowledge in this arcane realm of government accounting and contract compliance.
I wish him the best. He will be missed.
On Being a Consultant
Nick Sanders
For the past three years, on and off, we have been supporting a small business located in the Pacific Northwest. We were first contacted by internal counsel, who relayed some concerns. That counsel was employed by a large aircraft manufacturer, headquartered in the Northeast. It turned out that the small business was actually a subsidiary of the large aircraft manufacturer.
That small business had been doing business the same way for many years. About half its business was commercial and the other half was government; but the government work was 100% competitively awarded FFP subcontracts so differences between the government and commercial work were minimal. Even when that small subsidiary performed a FFP “subcontract” directly for its Northeastern headquarters, not much was different in terms of how the work was priced, or accounted for, or billed.
Now, you might be concerned (as we were) that perhaps treating inter-organizational work as FFP wasn’t strictly in accordance with the requirements of the FAR cost principle at 31.205-26(e), but we were told not to worry about that issue, because Northeastern headquarters had directed its buyers to treat all inter-company work as being a subcontract and, moreover, that all subcontracts were to be FFP type. The direction was that all suppliers were to be treated as being arms-length subcontractors, even if some weren’t really so arms-length. That was the direction, and it was faithfully followed by the buyers in the Northeast with respect to this particular “subcontract” with a small business in the Pacific Northwest, even though that small business was in reality a subsidiary.
Accordingly, the small PNW business had received a FFP subcontract from Northeastern HQ for a piece of an aircraft that was still in development.
You probably know how we feel about that situation. We’ve written about it before. We wrote “… the subcontract type has to be appropriate. If every subcontract is FFP, that’s not necessarily a good thing, especially in a development environment. You can usually tell if the contract type was appropriate by looking at post-award change order activity.”
Our point of view on choosing the correct subcontract type is informed by our experience. Consistent with what our experience tells us would be the case, the Northeast “prime contractor” made a number of changes along the way, and so the small business “subcontractor” generated quite a few change order notifications and asked for its firm, fixed-price to be increased to compensate it for the changed work. The “prime contractor” was reluctant to admit its changes were causing cost impacts and the parties essentially were at a stalemate regarding the appropriate value of the equitable adjustments to be made.
Meanwhile, the large Northeast aircraft manufacturer was acquired by an even larger defense contractor (one of the “five families” at the top of the defense contracting pecking order). That mega defense contractor had its own policies with respect to “subcontracting” between affiliated entities—policies that were more aligned with the requirements of 31.205-26(e)—and consequently that FFP “subcontract” needed to be treated as a cost-plus-no-fee inter-organizational transfer. In essence, the FFP “subcontract” needed to be reformed, and priced based on actual costs incurred to date plus an estimate of allowable direct and indirect costs to be incurred.
The challenge, of course, was that this small business didn’t have an “adequate” accounting system, and thus both its actual costs incurred as well as its estimates of future direct and indirect costs to be incurred were suspect.
That’s where Apogee Consulting, Inc. came in.
We entered into a nearly three year-long attempt to enhance the small business’ accounting system to adequacy, so that it could price, account for, and bill, its actual, allowable, costs to what had been its “prime contractor” but what was now a sister division within the mega defense contractor’s empire. To be clear, our role was advisory and the heavy lifting was done by some of the people who worked at the small business. These individuals had long careers within government contracting. A couple had been long-term employees of a DOE O&M/M&O contractor. One was a CPA with years of government accounting experience. Another was an attorney trained at the GW School of Law in government contracts. They were knowledgeable and experienced but, as is so often the case, they didn’t have the bandwidth to do their jobs plus write policies and procedures and instructions, plus review spreadsheets and job aids, plus reconcile transactions to ensure the cost allocations were accurate. That’s what we did. We would visit for a few days, review the work that had been done, make suggestions on additional work to be done, review policies and procedures, make suggested revisions and, in general, try to push the project along. Then we would come back a few months later and do the same thing.
In addition, we strategized with program management, contracts, and financial management on how to convince the former “prime contractor” that (a) the small business’s costs were accurate and compliant, and (b) what the budget should be (going forward) for the cost-type inter-organizational work that was being performed. You might be surprised (as we were) to learn that the “prime” buyers were resistant to changing the subcontract type, or to admitting that the price they had budgeted in their Estimates-at-Completion—which was the firm, fixed-price they had initially awarded before the myriad changes—was in need of an increase.
The buyers at the “prime” were so reluctant to change the way it had always been done that they called in DCAA to audit their own sister division, to make sure that small business “subcontractor” wasn’t somehow trying to overbill them.
Really. They called in DCAA on their own people. That’s how far out-of-touch with reality they were.
But by this point, that small business was ready to go and DCAA had no findings. (To be clear: our contribution to that outcome was small; the audit support was executed by the people at the local business. Dealing with auditors was something they could do and they did it well.)
At this point, after three years of effort, the small business in the Pacific Northwest was ready to price, and account for, and bill, its actual, allowable, costs to its sister division located in the Northeast.
Mission accomplished!
And then that small business located in the Pacific Northwest was sold to a venture capital firm.
Everything that we had done needed to be undone. That cost-plus-no-fee inter-organizational transfer budget needed to be recast as an FFP subcontract—albeit at a higher price than was originally awarded. That task took some negotiating, for sure. As one person close to the action wrote me, “As much work as it was to turn [the subcontracts] into Cost Type, it was an even bigger mess to untangle back to FFP.” We were not part of those efforts, and we empathize with those who were.
It might seem as if our efforts had been wasted, that three years of work had been trashed. And pehaps that's true. But such is the life of a consultant.
Often, our best efforts go unappreciated, or unrewarded. In my first true consulting gig (in 1999) we billed the client $500,000 and for that price delivered 18 solid recommendations for improvement (so as to avoid further very expensive False Claims Act-related litigation). That client implemented just one of the 18 recommendations, and ignored the rest. In a later project, we billed one of the Top 5 mega defense contractors north of $500,000 to develop an innovative supplier risk management solution that delighted the program manager who had hired us, but which was immediately killed by Sector HQ because that’s where risk management was functionally located—and they didn’t appreciate the competition. In yet another gig, I reconciled the ins-and-outs of cost allocations for a multi-billion-dollar aircraft manufacturer with multiple business segments. I identified $90 million in differences (errors) that impacted the company’s indirect cost rate calculations—only to be told it was a “rounding error” that should be ignored. In so many engagements, the consultant’s efforts do not result in the intended outcomes, often for reasons that the consultant cannot control.
So it goes. We do our best and sometimes our best isn’t good enough, or isn’t politically correct, or is overtaken by changing circumstances. You try to keep a positive attitude and make sure the checks are cashed. What else can you do?
And what about my clients, whom I came to call my friends, at that small business located in the PNW? They are all being laid-off by the new management, who views them as being non-value-added backoffice lackeys. Perhaps they are, in fact, now redundant in the company’s new environment (which is really the old environment) of 50% commercial/50% government FFP subcontracts. It probably does make financial sense to let them go, despite their decades of experience. That experience just won’t be as valuable to the stand-alone entity as it was to the mega defense corporation that acquired the large aircraft manufacturer that had a small subsidiary located in the Pacific Northwest.
Thus, while we at Apogee Consulting, Inc. get to go home and work on new projects for other clients, those former employees now have to search for new jobs. To assist them: if you are reading this and want to hire some really good, experienced, financial management or contracts people who are based in the PNW, please email us!
In the meantime: to Annette, to Chuck, to Nestor—it was a pleasure to work with you, and we here at Apogee Consulting, Inc., wish you only the best.
F-35 Program On Track, Can Use Some Help
Nick Sanders
The F-35 Lightning II Joint Strike Fighter program is the largest, most expensive, and arguably the most complex fighter production program in U.S. history. Its GFY 2018 budget was described as follows: “The final omnibus budget bill funded F-35 procurement at $10.2 billion for 90 aircraft (56 F-35As, 24 F-35Bs, and 10 F-35Cs, an increase of 20 aircraft and $2.6 billion over the Administration’s request), plus $1.5 billion in advance procurement, the requested level.”
Basically, then, nearly $12 billion annually; and that amount will increase as production ramps up (even though the per-aircraft cost is projected to decrease).
Indeed, Lockheed Martin delivered 91 aircraft in 2018, which was about double its production of only two years before. Looking ahead, the JSF will enter “full rate production” and LockMart has committed to deliver 130 aircraft before the end of 2019. Meanwhile, the government and the contractor are entering into negotiations for Lots 15, 16, and 17—an order of 485 aircraft that would be executed sometime in the second half of 2021. At $80 million each, the multi-year contract would be valued at $38.8 billion. (Just in case you were wondering where your taxes went.)
Suffice to say, the F-35 program is taking care of Lockheed Martin. That wasn’t always the case. Readers may know that relations between contractor and customer have been fairly rocky. Last year, that bastion of defense insider information, Popular Mechanics, published a history of the program entitled “WTF-35: How the Joint Strike Fighter Got to Be Such a Mess.” But after reciting the program’s problems, the article concluded: “The F-35 may be one of the most derided and controversial warplanes, but it's here, nearly ready to go into service in force. That's a good thing. Frankly, we need the F-35.”
But while all the champagne is flowing in Fort Worth and in Bethesda, the DOD Office of Inspector General had some sharp words aimed not at the contractor but at the government personnel who were supposed to be providing oversight, and (according to the DOD OIG) failed to do so.
We’re talking government property.
Even though most of us don’t like to deal with government property issues, it’s important. It’s one of those “necessary evils” that requires an investment of time and expense. Government property control is one of the six DFARS business systems. Accordingly, a contractor’s failure to maintain an acceptable property control system could result in significant payment withholds. Therefore, smart contractors tend to make the necessary investments in time and expense, because not doing so likely would be more expensive.
We tend to focus on contractor requirements and forget that the government has its own responsibilities with respect to managing property. A recent DOD OIG audit report found that USAF Joint Program Office had been derelict in its duties “for more than 16 years.” As a result, the DOD OIG found that “the only record of Government property for the F‑35 Program is with the contractor and its [warehousing and inventory management] subcontractor ….”
How much property are we talking about?
Well, if you ask LockMart and its subcontractor, they are tracking 3.45 million individual pieces of property valued at $2.1 billion.
(Note there is nobody else to ask.)
One thing that many people outside the world of government property fail to appreciate is that government property can pass from one contract to the next. For example, a contractor can create a piece of special tooling or special test equipment. At the end of the contract, that ST or STE now belongs to the government; and if the contractor wants to continue to use it on the next follow-on contract it has to be transferred and it’s now going to be “government-furnished property” (and not “contractor acquired property”) because the government has title to it.
As noted above, the F-35 program consists of multiple contracts. Some may be running concurrently and others may be awarded sequentially. Some may have been cost-type while others may be firm, fixed-price—and each contract type has different government property requirements. As a consequence, we should appreciate just how difficult a job it is to track all that property and identify it with the appropriate accountable contract. Lockheed Martin and CEVA Government Services should be commended for the job they have done in this area.
In contrast, the Program Office and DCMA seem to have fallen down, and have lost the ability (if they ever had it) to track their property. Or should we say—the taxpayers’ property? The DOD OIG audit report lists several areas of deficiency, including—
Failure to maintain a Government record of Government Furnished Property
Failure to award contracts with complete GFP lists
Failure to coordinate with DCMA officials to execute contracting actions to transition Contractor Acquired Property to Government Furnished Property
As a result (according to the DOD OIG audit report)—
… the DoD does not know the actual value of the F -35 property and does not have an independent record to verify the contractor-valued Government property of $2.1 billion for the F-35 Program. Without accurate records, the F-35 Program officials have no visibility over the property and have no metrics to hold the prime contractor accountable for how it manages Government property. … In addition, the lack of a DoD record of GFP for the F-35 Program results in an understatement of either the assets or expenses of DoD financial statements, depending on how the contractor used the property on the contract.
Sounds to us like the Joint Program Office needs to have a payment withhold implemented on it in order to teach its leaders the importance of government property management and control.
Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.