• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

Why Can’t NASA Manage its Programs?

E-mail Print PDF


The National Aeronautics and Space Administration (NASA) has been a topic of interest since President Obama took office more than a year ago and almost immediately ordered an independent review of NASA’s manned space program.  That review, carried out by the Augustine Commission, had nothing but bad news for the Administration, reporting “The U.S. human spaceflight program appears to be on an unsustainable trajectory.”

More recently—and perhaps in response to the Augustine Commission’s pessimistic assessment—the Obama Administration announced a budgetary shift for NASA, giving the agency more funds for R&D, while taking away funds from the planned return to the moon—“killing the Constellation program” in the words of this article by the Washington Post.  The article explains—

The old NASA strategy set a destination first, and developed technology -- rockets and a crew capsule -- to get there. The new strategy calls for pouring billions into space technologies without defining the destination. The idea is to create technological flexibility so that astronauts could potentially visit a variety of locations in the inner solar system, including the moon, near-Earth asteroids and possibly Mars or the moons of Mars. The ‘Flexible Path’ strategy was favored by the advisory panel appointed last year by President Obama to review NASA's options.

This article at SpaceNews.com is rather more optimistic; it quotes a NASA executive as saying, “This is a great budget.  It’s a major increase to the science budget.  It’s an especially major increase to the Earth science budget.”

While NASA wrestled with its future vision and mapping a path to manned space missions, back on Earth the Government Accountability Office (GAO) was busy criticizing its unmanned satellite missions, telling Congress that “NASA frequently exceeded its own acquisition cost and schedule estimates, even when those estimates were relatively new. In fact, 9 out of 10 projects that have been in implementation for several years significantly exceeded their cost or schedule baseline estimates—all in the last 3 years.”

In a report released on February 1, 2010, GAO assessed 19 “large-scale” unmanned NASA projects, of which 15 had entered the “implementation” phase.  Of those 15, GAO concluded that nine of them “experienced significant cost and/or schedule growth from their project baselines.”  (Four projects were considered to be in the “formulation” phase, and NASA did not provide GAO with formal cost and schedule information on them.)  GAO reported—

Based on our analysis, development costs for projects in our review increased by an average of over 13 percent from their baseline cost estimates—including one project that increased by over 68 percent—and an average delay of almost 11 months to their launch dates. These averages were significantly higher when the four projects that just entered implementation are excluded.  Specifically, there are 10 projects of analytical interest because (1) they are in the implementation phase, and (2) their baselines are old enough to begin to track variances. Most of these 10 projects have experienced significant cost and/or schedule growth, often both. These projects had an average development cost growth of 18.7 percent—or almost $121.1 million—and schedule growth of over 15 months, and a total increase in development cost of over $1.2 billion. Over half of this total increase in development cost—or $706.6 million—occurred in the last year. These cost growth and schedule delays have all occurred within the last 3 years, and a number of these projects had experienced considerable cost growth before baselines were established in response to the 2005 statutory reporting requirement.

See GAO’s entire report here.  The GAO report also noted that roughly $1 billion in ARRA funds was given to NASA, much of which was used to offset some of the cost growth it reported.

In its report, GAO reviewed six factors that it believed contributed to cost and schedule growth.  Those six factors were:

  • Technology maturity (including maturity of critical technology as well as maturity of heritage technology)
  • Design stability
  • Contractor performance
  • Development partner performance
  • Funding issues
  • Launch manifest issues

The report discussed each of the above factors as they apply to NASA’s projects.  More interestingly, the report devotes two pages of detail to each individual project.  Following are some “highlights” from the detailed project reports.

  • Aquarius Project – Only 16 percent of engineering drawings released at Critical Design Review (CDR) milestone.  No engineering test models because of funding constraints.  Ten month schedule slip and $10.7 million cost growth.
  • Ares I Crew Launch Vehicle (CLV) – “The Constellation program’s poorly phased funding plan has diminished the Ares I project’s ability to deal with technical challenges.”
  • Glory Project – Only 69 percent of drawing released at CDR.  14 percent cost increase and 10 month schedule slip since rebaselining in FY 2009.  Currently, recent launch failure of Taurus XL rocket threatening current scheduled launch date.
  • James Webb Space Telescope (JWST) – “The JWST project was re-planned in fiscal year 2006 after a $1 billion cost increase and a 2-year schedule delay on the project. In fiscal year 2009, the project established its baseline with a life cycle cost of $4.96 billion and a June 2014 launch date. This represents about a $500 million increase over NASA’s 2006 replan figures and has resulted in another 1-year delay of the launch readiness date.”
  • Kepler – “Since being baselined in fiscal year 2007, Kepler’s development costs have increased by about 25 percent and its schedule has increased by 9 months. Project officials attribute the cost and schedule growth to many things, including a $35 million budget reduction in fiscal year 2005. This funding instability contributed to an overall 20-month delay in the project’s schedule and about $169 million in cost growth.”
  • Mars Science Laboratory (MSL) – “MSL’s cost has grown over $660 million because of technological and engineering problems. This includes more than a 68 percent increase in development costs. The project is using a 25-month schedule delay to work on overcoming technical challenges with the actuators and avionics that were the primary drivers for the slip.”
  • Solar Dynamics Observatory (SDO – “SDO’s design was not stable at the critical design review (CDR). Following this review, the project experienced nearly a 1,200 percent overall increase in the number of releasable drawings expected. Project officials said only drawings for in-house structures, such as propulsion systems, electronics, instrument ports, the high-gain antenna system, and the spacecraft, were considered at CDR. Drawings for the instruments were not included and flight drawings were only in draft form at CDR. The project estimated it released less than 63 percent of engineering drawings at each of their instrument-level CDRs.”

From one point of view, the GAO report is a litany of project management failures.  But from another point of view, the report tells various stories of individual project teams doing the best they could in difficult circumstances, trying to create state-of-the-art scientific instruments and manage complex systems, while being held to unrealistic budgets and almost impossible launch schedules.

Very few people care about the difficulties and the challenges of the NASA missions; they prefer to criticize the easy targets of cost growth and schedule slip.  Even though we here at Apogee Consulting, Inc. firmly maintain that projects can be managed to successful cost, schedule, quality and performance objectives, we also understand the difficulties faced by these project teams.  We are reminded of this saying by Theodore Roosevelt, spoken before the Sorbonne in 1910—

It is not the critic who counts: not the man who points out how the strong man stumbles or where the doer of deeds could have done better. The credit belongs to the man who is actually in the arena, whose face is marred by dust and sweat and blood, who strives valiantly, who errs and comes up short again and again, because there is no effort without error or shortcoming, but who knows the great enthusiasms, the great devotions, who spends himself for a worthy cause; who, at the best, knows, in the end, the triumph of high achievement, and who, at the worst, if he fails, at least he fails while daring greatly, so that his place shall never be with those cold and timid souls who knew neither victory nor defeat.



 

Rough Ride for the F-35

E-mail Print PDF


We’ve been holding off discussion of the F-35 “Lightning II” Joint Strike Fighter (JSF) until things settled down a bit.  Well, things haven’t really settled down, but there’s enough news that it seems a good time to take stock of the program.

Readers will recall our previous article, in which we inquired how much the JSF will really cost its customers—both in the US and abroad—and noted that “time will tell who has the best at-completion estimate, the Pentagon JET evaluators or the program team.”  Since then, the Obama Administration has moved to eliminate the alternate engine competition, purchases of production aircraft have been delayed, the Pentagon has fired its Program Manager, and SecDef Gates announced that Lockheed Martin will lose $614 million in budgeted award fees based on the program’s problematic performance.  Oh, and a leaked Navy briefing reported that—

… over the lifetime of the fleet - the carrier-based and STOVL JSF versions will cost the Navy 40 per cent more, in total operating costs, than the F/A-18C/Ds and AV-8Bs that they replace. (The older aircraft costs are taken from FY2008 and include a lot of aging-aircraft issues.) This is despite a smaller fleet and fewer flight hours: the new aircraft are expected to cost more than 60 per cent more to fly per hour than their predecessors.



The Navy report suggests that the total cost of the Pentagon's JSF program will be $705 billion in FY2002 dollars, just over twice the figure predicted at the program's inception.

But that’s not all.  In response to our previous question, DefenseNews.com reported that the Pentagon is accepting the Joint Estimating Team (JET) budget projection, and consequently is adding $314 billion to the program’s official budget (over a five-year period).  But not content to stop there, the article reported that USD (AT&L) Dr. Ash Carter “is set to order [yet another] bottom-up review of the program and its costs.”  In the words of SecDef Gates, “Progress and performance of the F-35 over the past two years has not been what it should, as a number of key goals and benchmarks were not met.”

It should not be forgotten that the F-35 is truly an international fighter development and production program, with eight other nations participating in its funding.  Those other nations are getting nervous that delays and cut-backs in the number of aircraft being purchased will raise the per-craft price—and as the per-craft price has risen, those countries have begun to consider cutting-back their production orders even more. 

This article discusses the increase in price to the United Kingdom of Great Britain, and states that the aircraft’s price “has risen from £37m each four years ago to £62m now.”  As a result, “a consensus has emerged … that they cannot afford the 140 American Joint Strike Fighters … they had been seeking.  … One compromise would be for the Ministry of Defence (MoD) to halve its order from 140 planes to 70.”

Officially, the program calls for delivery of 5,500 aircraft—2,400 to the US and 3,100 to the international partners.  Lockheed Martin asserts that it can manage the program and catch-up schedule, while controlling cost growth.  If it cannot, it may find itself the builder of a white elephant fighter whose lack of economies of scale make the plane unaffordable for its international partners.  The stakes are high, not only for Lockheed Martin (whose stock has been downgraded based at least in part on its F-35 problems), but also for the US Air Force.





 

Claiming the Government Acted in “Bad Faith”

E-mail Print PDF


Recently somebody posted this cry for help on the LinkedIn Question & Answer Board—

We have a COTR that is causing problems with our contract and need a recommendation for an attorney … Can anyone help us? We have a service contract … and the COTR has lied, is now causing our Supervisor to quit because he feels he is being harassed by him… and more. Does this constitute a delay and/or Government Interference? Any help is appreciated.

Let’s look at this from two perspectives.  First, let’s talk about delay and disruption.  This is really two issues.  In a delay claim, the contractor is claiming compensation for not being able to work.  In some situations, that claim can include the costs of “unabsorbed overhead”—i.e., indirect costs that would have been absorbed on the instant contract, had the labor hours or dollars been incurred as scheduled, but which now will be absorbed by other contracts, causing them to incur more costs than they had planned.  In a disruption claim, the contractor is asking for additional compensation because the work is more complex, and more expensive, than the parties originally agreed. 

As this article makes clear—

The contractor must prove for either claim the elements of liability, causation, and resultant injury. When the contractor is asserting a delay claim, the contractor has the burden of showing the extent of the delay, that the delay was proximately caused by government action, and that the delay caused damage to the contractor. While the law requires ‘reasonable certainty’ to support a damages award, damages do not need to proven with mathematical exactness. Rather, ‘[i]t is sufficient if a claimant furnishes the court with a reasonable basis for computation, even though the result is only approximate.’ The preferred method for proving costs is through the submission of actual cost data. However, where actual cost data is not available, estimates of the costs may be used. Estimates of costs ‘should be prepared by competent individuals with adequate knowledge of the facts and circumstances,’ and should be “supported with detailed substantiating data.”  [All legal citations omitted.]

What the LinkedIn interlocutor is also hinting about is whether, by engaging in lying and harassment and unreasonable delays, the Government has breached its implied duty of “good faith and fair dealing”. As an aspect of these duties, “[e]very contract . . . imposes an implied obligation ‘that neither party will do anything that will hinder or delay the other party in performance of the contract.’” Such covenants require each party “not to interfere with the other party's performance and not to act so as to destroy the reasonable expectations of the other party regarding the fruits of the contract.” This “duty not to hinder is breached when the Government commits ‘actions that unreasonably cause delay or hindrance to contract performance.’” [Legal citations omitted.]

The case law is well-settled that the Government enjoys a presumption that it acts in good faith.  To overcome that presumption, “the proof must be almost irrefragable” – which has also been described as “clear and convincing evidence” of “some specific intent to injure” the contractor. “Courts have found bad faith when confronted by a course of government conduct that was ‘designedly oppressive,’ or that ‘initiated a conspiracy’ to ‘get rid’ of a contractor. As these cases illustrate, the ‘irrefragable proof’ standard, though daunting, is not intended to be impenetrable, that is, it does not ‘insulate government action from any review by courts.’”  [Emphasis in original; legal citations omitted.]

Recently the U.S. Court of Appeals, Federal Circuit, affirmed a decision by the U.S. Court of Federal Claims in which the contractor successfully proved bad faith on the part of its Government customer, the U.S. Army Corp. of Engineers.  The tale is a sad one, where certain government individuals exercised their authority (and more!) to the detriment of the contractor, North Star Housing.  As the Court found, “the record provides a virtual rancid cornucopia of electronic messages and other communications evidencing a specific intent by key government officials to injure North Star.”  See the entire CoFC decision here.

As the Court observed, “Among the most troubling aspects of the case … is clear proof that Mr. Peterson, Ms. Kiser and others eventually co-opted the contracting officer who was responsible for ruling on North Star’s claims.”  Although the FAR requires the contracting officers to ensure that contractors “receive impartial, fair, and equitable treatment,” the Court found the contracting officer did not do so in this case. The Court declared—

Abdication of those responsibilities in the face of pressure from government officials who plainly are driven by animus against a given contractor constitutes perhaps the most pernicious form of bad faith on the part of the government, as it threatens the integrity of a dispute resolution process that is central to the government contracting system itself.

Despite the Court being “thoroughly convinced” of the Government’s breach of its duty of good faith and fair dealing, the plaintiff (North Star) was not awarded as much money as it had hoped for.  First, some of its claims were dismissed for lack of jurisdiction, because they had not been first presented to the contracting officer with a “sum certain” as the FAR and Contract Disputes Act (CDA) require.  Second, North Star’s analysis of its damages was found to be lacking by the Court.  As the Court stated, “such [Government] liability, no matter how egregious, does not obviate the necessity for plaintiff to prove its damages.”

To wrap up, many contractors are afraid to submit claims because they are worried about angering their customer(s) and losing future work.  (We note that contractor evaluations and past performance ratings cannot be affected by assertion of contractual rights.)  Contractors seeking to assert claims against their Government customers need to understand what their cause of action is.  Are they asserting Government-caused delay or disruption?  And are the Government’s actions tied to any provable breaches of its duty to act in good faith?  Finally, what damages can be proven, and have all the steps of the FAR and CDA strictly been followed when asserting the claim?



 

GAO Points Out Potpourri of Problems with Pentagon Procurement Process

E-mail Print PDF


On January 20, 2010, GAO offered testimony before the House Committee on Appropriations, Subcommittee on Defense (John Murtha, D-PA, Chair).  The testimony, which can be found here, had the rather misleading title of “Managing Risk to Achieve Better Outcomes.”   The testimony was not really about risk management; instead, it was more of a recap of various DOD acquisition issues that the GAO has been criticizing for years—most of which are rather obvious.

Highlights of the GAO testimony—

  • The first opportunity to reduce acquisition risk is in the early planning phases.
  • Risk can be reduced through selecting the appropriate contract type.
  • Risks that are not effectively managed in the pre-execution phase of a contract may become costly problems during execution.
  • Acquisition risk management is dependent on a “capable” acquisition workforce; yet “DOD lacks key information about the current number and skill sets of its acquisition workforce and what it needs.”
  • Because DOD relies so heavily on contractors to support its acquisition process, and lacks insight into the roles its contractors are fulfilling, the Department cannot make effective decisions regarding its acquisition workforce staffing—thus “increasing the risk of transferring government responsibilities to contractors.”

The testimony reiterated familiar themes, such as—

Risk is inherent in any major acquisition, whether a weapon system or complex service acquisition. But it is only through the thoughtful management of risks throughout all phases of the acquisition process that successful outcomes can be achieved. Clearly, however, DOD has not adequately managed such risks. For example, its major weapon systems continue to take longer to develop, cost more, and deliver fewer quantities and capabilities than originally planned. … Despite decades of reform efforts, these outcomes and their underlying causes have proven resistant to change and, in fact, both DOD weapon system acquisition and DOD contract management have been on our high-risk list for nearly 20 years.

Much more interesting than the reiteration of simplistic observations is the summary of GAO bid protest statistics.  Although released separately, the testimony included an overview of the recent history of GAO’s “quasi-judicial” function as arbiter of bid protests.  (Readers will note that the U.S. Court of Federal Claims also performs in a similar capacity.)  We previously have wondered out loud whether the Department of Defense has “lost its ability to evaluate proposals fairly and in accordance with the written evaluation criteria.”  The GAO testified that—

There has been a substantial increase in spending on acquisition programs and services, while the number of civilian and military personnel in DOD’s acquisition workforce has remained relatively constant. Program offices have reported that workforce shortfalls have resulted in degradation in oversight, delays in certain management and contracting activities, and increased workloads for existing staff. To supplement its in-house acquisition workforce, DOD relies heavily on contractor personnel. For example, we have found that in some program offices contractor personnel outnumber DOD personnel.

Have DOD’s acquisition workforce problems contributed to degradation in the ability to conduct fair and equitable evaluations of bidders for major defense acquisition programs?  One way to assess the situation would be to look at GAO’s bid protest decisions, to see whether the sustention rate is elevated when compared to historical norms.

According to the GAO 2009 bid protests are up 20% over the prior year—1,764 vs. 1,458.  Comparing 2009 to 2005, bid protests are up nearly 40%--1,764 vs. 1,262.  (Readers should take GAO’s numbers with a grain of salt, however.  GAO counts every “docket number” as an individual protest; a single protest can have multiple docket numbers.  Moreover, the quantity of protests filed really tells us nothing.  Government spending also increased during that period, so one might logically expect an increase in bid protest activity.  In addition, GAO recently received expanded bid protest jurisdiction over task orders, which accounting for 49 of its 2009 bid protests) 

Sustention of bid protests is measured against “merit decision” (not the number of cases filed) and the numbers show that the sustention rate actually dropped during that period—from 71/306 (23%) to 57/315 (18%).  So rather than a degradation, the evidence points to an improvement in the Government’s ability to carry out its acquisition function!

Looking just at the Defense Department, the number of protests filed was up nearly 50 percent—from 706 to 1,050.  But as before, the percentage of sustained protests actually decreased from 18% to 12%.

GAO also reports an “effectiveness rate”—which is defined as a situation when a protester receives some form of relief from the Government agency conducting the procurement, even if it did not have its protest sustained.  Looking at the reported effectiveness rates, there has actually been some increase, from 27 percent (2005) to 45 percent (2009).  It’s difficult to determine what this means without further details.

So the statistics may be meaningful, or not.  We’ll leave any conclusion(s) to our readers’ judgment.  But we maintain that anecdotal evidence is mounting that DOD is having trouble evaluating bidders for major defense acquisition programs without opening the door to a successful bid protest.  As GAO notes in its report, such recent programs as CSAR/X, Aerial Refueling Tanker, FMTV, and TRICARE were interrupted by successful protests by the losing bidders.  And as we have noted with respect to two of those programs listed by GAO, the errors cited by GAO were of the “blocking and tackling” variety, and not of the “difficult and complex” variety.  We hope DOD gets its act together, soon.



 

SAIC Tests FCS Equipment: A Clear Conflict of Interest, Says DOD IG

E-mail Print PDF


On January 27, 2009, the Department of Defense Inspector General (DOD IG) released a redacted version of its report on “contracted advisory and assistance services for the U.S. Army Future Combat Systems.”  The report concluded that the DOD’s Director of Operational Test and Evaluation (DOT&E) had engaged SAIC as its “primary commercial contractor” supporting its testing needs, even though SAIC (along with Boeing) serves as the Future Combat Systems (FCS) Lead System Integrator for system design and development, and even though SAIC’s contract with DOT&E “explicitly stated ‘… providers are excluded from this contract who have significant involvement in the development of DoD systems that are under, or will be under DOT&E oversight’.”  Despite SAIC’s argument that its role on the FCS contract was one of system integrator, not system developer, the DOD IG found that the FCS contract had received billions of dollars out of the Army’s Research, Development, Test and Evaluation (RDT&E) appropriation—thus, SAIC was de facto a system developer.  The DOD IG Report, blasted the entities involved for this situation, stating that “DOT&E and the Army did not exercise the good judgment and sound discretion needed to prevent the existence of conflicting roles that might bias a contractor’s judgment or provide it an unfair competitive advantage.”  Ouch.

According to the DOD IG, after the situation was brought to the parties’ attention, SAIC’s advisory/assistance support contract to DOT&E was quickly modified to “delete the FCS-related tasks” after officially “concluding that SAIC had statutory OCIs regarding those tasks.”

But what is an Organizational Conflict of Interest (OCI)?  We’ve touched on this topic before, notably in connection with Northrop Grumman’s sale of its TASC unit.  Essentially, the FAR states that an OCI exists when one of three situations exists—

1. An individual is actually (or potentially) unable to provide the government with “impartial assistance or advice”

2. A person’s objectivity in performing contract work is or might be impaired

3. A person or entity has an unfair competitive advantage

An OCI can be created with respect to an existing contract or with respect to future work.  The FAR (at 9.5) discusses “Organizational and Consultant Conflicts of Interest,” and (according to the DOD IG audit report) “places restrictions on contractors being placed in a position to make decisions that favor their own products or capabilities.”  The DOD IG also noted that 10 U.S.C. § 2399 “places further restrictions on system developers supporting operational test and evaluation.” 

The DOD IG report also noted that Army Contracting Officers had a responsibility to identify and, if possible, mitigate actual or potential OCIs.  (See FAR 9.504.)  Moreover, the FAR directs “The contracting officer shall award the contract to the apparent successful offeror unless a conflict of interest is determined to exist that cannot be avoided or mitigated.”  Despite the FAR requirements regarding OCIs, the DOD IG concluded—

We were unable to determine if the contracting officer performed any evaluation beyond accepting statements made in SAIC’s proposal to determine if potential issues existed that would hinder SAIC’s ability to provide unbiased advisory and assistance services related to the overall contract or the specific scope of work SAIC performed under [the Delivery Order]. There was no documentation in the contracting file to show how the issue was addressed.

…

We found no evidence that anyone evaluated whether SAIC was significantly involved in the development of a DoD system that DOT&E was or would be overseeing prior to contract award. According to the contracting officer, DOT&E did not see a conflict with awarding the contract to SAIC because it had previously been fulfilling the requirements under a bridge contract that was entered into after the previous prime contractor was dropped after being acquired by Northrop Grumman, another FCS systems developer. Only after an inquiry was made was the issue of how the Government reached its conclusion that SAIC’s participation in the development of the FCS did not violate the OCI clause contained in the solicitation examined.

In addition, the DOD IG found similar concerns with Northrop Grumman, CSC, General Dynamics, and Lockheed Martin.  It reported—

We were unable to determine how the contracting officer concluded that the business isolation procedures that Northrop Grumman described in the proposal it submitted for the overall contract was consistent with the OCI provisions of 10 U.S.C. 2399 or the OCI clause contained in their overall contract. However, based on documentation contained in the contract files, it appears the contracting officer concluded that Northrop Grumman possessed no OCIs related to the requirements of either delivery order.

…

In their proposal, the Test and Experimentation Services Company [a JV that included CSC] informed the contracting officer that it possessed OCIs with respect to the work to be performed under the work authorization orders. However, the company proposed that CSC’s partner perform all the work under the contract. Thus, the Director of Contracts stated that based on that fact, the command concluded that awarding the scope of work to the Test and Experimentation Services Company did not violate Title 10’s OCI restrictions because CSC would not share in any of the profit derived from the contract.

…

The OCI provisions prohibited FC Business Systems from satisfying requirements resulting from its work under the contract, and the task order issued to support the OTC Air Defense Artillery Test Directorate’s mission requirements included additional restrictions to prevent FC Business Systems from operationally testing equipment it helped manufacture. However, the provisions did not require FC Business Systems to inform the Government of its acquisition by General Dynamics. As a result, the OTC and General Services Administration did not detect that General Dynamics, one of Boeing’s major FCS development subcontractors (after acquiring the FC Business Systems) was helping the command plan, coordinate, collect, and reduce data used to evaluate the effectiveness and suitability of the FCS, a clear violation of the OCI provisions in 10 U.S.C. 2399.

The DOD IG made several recommendations designed to prevent similar situations from arising in the future.  Among them, it recommended that the Director of Defense Procurement and Acquisition Policy, Mr. Shay Assad, develop a new DFARS clause that would preclude “contractors that are involved in the development, production, or testing of a system … from providing technical advice to the program office for that system or from participating activities impacting the operational test and evaluation of that system unless appropriate waivers are obtained.”   Importantly, the new clause would “make it incumbent on the proposing contractor to identify in their proposal any work that that they are or have performed either under prime contract or subcontract related to the development or supply of a DoD system.”

The report noted that Mr. Assad agreed with the recommendation.  “The Director also stated that he would issue a memorandum emphasizing the importance of complying with FAR OCI provisions after the FAR Acquisition Law Team issues its final rule for a related FAR case to ensure that he does not issue conflicting guidance.”

We recommend that contractors supporting government test and evaluation functions take note.


 


Page 250 of 278

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.