• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

Status of the Defense Industry—Mid-Year 2010 Assessment

E-mail Print PDF


The status and future of the aerospace/defense industry has been a popular topic here at Apogee Consulting, Inc.  Whether it has been a reported DOD funding shortfall, a report from AW&ST forecasting an industry-wide downturn, or a similar report from Forecast International, or another AW&ST forecast of a 10% industry-wide workforce reduction, readers of this site are (naturally) interested in what lies in store for the A&D industry. 

And we’ve not been entirely pessimistic, either.  In one article, we noted that several A&D companies were actually adding to their executive ranks, under the theory that an enhanced focus on program performance and customer relationships would differentiate them from the competition.  In another article, we linked to a report by the Project on Defense Alternatives that postulated a defense spending plateau that would be at least five percent higher than recent history, even after adjusting for inflation.  So even as we report on industry layoffs and corporate restructurings, we also continue to be guardedly optimistic that some sectors of the industry will maintain current business levels, while other sectors may even thrive in the near-term future.

The seeming contradiction between forecasted spending cuts and cautious optimism continues and may well define the rest of 2010 and 2011 as well.  On July 22, 2010, the New York Times published an article entitled “Pentagon Faces Growing Pressures to Trim Budget.”  The article reports—

Mr. Gates is calling for the Pentagon’s budget to keep growing in the long run at 1 percent a year after inflation, plus the costs of the war. It has averaged an inflation-adjusted growth rate of 7 percent a year over the last decade (nearly 12 percent a year without adjusting for inflation), including the costs of the wars. So far, Mr. Obama has asked Congress for an increase in total spending next year of 2.2 percent, to $708 billion — 6.1 percent higher than the peak under the Bush administration.

Mr. Gates is arguing that if the Pentagon budget is allowed to keep growing by 1 percent a year, he can find 2 percent or 3 percent in savings in the department’s bureaucracy to reinvest in the military — and that will be sufficient money to meet national security needs. In one of the paradoxes of Washington budget battles, Mr. Gates, even as he tries to forestall deeper cuts, is trying to kill weapons programs he says the military does not need over the objections of members of Congress who want to protect jobs. …

At the moment, the administration projects that the Pentagon’s base budget and the extra war spending will peak at $708 billion in the coming fiscal year, though analysts say it is likely that the Pentagon will need at least $30 billion more in supplemental war financing then.

Two-thirds of Pentagon spending is on personnel costs. It is possible that the Pentagon will have to look for the first time at cuts to the health benefits provided to active and retired military personnel and their families.

Some analysts said the Pentagon would eventually come under pressure to reduce the size of the armed forces.

Readers of this site may notice something interesting in the quoted sections of the article, above—the bit about personnel costs.  We first brought the personnel cost issue to your attention here, where we reported on an editorial from Dr. Loren Thompson of the Lexington Institute.  We subsequently reported on a GAO comparison between the costs of using private security forces versus costs of the use of State Department security personnel—and we reported that GAO found huge cost increases when government personnel were used, in almost every case it studied.  So keep that fact in mind when you hear about Government “insourcing” and hiring of more Pentagon personnel.

This July 2010 study by Deloitte’s Global Aerospace & Defense practice summed up the state of the A&D industry thusly—

Sales in 2009 were essentially flat with a small 1.3% increase, while earnings were down 15.3% from 2008. If not for the large program related write-offs, asset impairments, or regulatory fines at a few of the largest firms, industry profits would have been essentially flat as well. This financial performance could be viewed as positive when compared to the significant negative economic impact of the global recession. The industry continues to demonstrate its resiliency in the face of uncertain economic conditions.  The global aerospace and defense (A&D) industry as of midyear 2010 is experiencing the same ‘flat’ financial performance that was seen in 2009, although results varied widely by individual companies. For the top 25 global A&D firms that have issued quarterly financial statements thus far in calendar 2010 as a group, sales revenue growth was -1.01%, operating profits were -1.94%, and operating margins were -0.94% …. Holding steady on these key financial performance metrics indicates that the global industry has largely held up to the continued downward pressure on defense spending, managed its way through difficult and large-scale product introductions, and experienced continued slow sales in the commercial aircraft and business jet segments.

With respect to the defense sector in particular, the Deloitte report stated—

Some programs of record may be terminated due to cost and schedule overruns or determinations may be made that certain weapons programs conceived to fight the Cold War are no longer necessary. Conversely, programs that can be developed and fielded quickly to address the type of irregular warfare with insurgents and invisible adversaries are becoming more frequent and may attract funding.

For defense contractors, new areas will generate growth in 2010 and beyond. In particular, the number and variety of large hardware-based platforms is expected to decline and more innovation and capability will be found in software integration. Mission capability will increasingly be created by information technology services firms, which are well poised to create competitive advantage through innovation in battle space simulation, directed energy, precision engagement, threat identification, as well as energy and infrastructure security.

We recommend that readers download this report for themselves, as it contains quite a bit of excellent information.

Similarly, Jim McAleese recently briefed on this topic at NCMA’s World Congress.  We’ll hold a detailed review of Jim’s presentation for a later article, but we want to note some of his points that seem relevant to this topic.  Jim made the following points (which we copy ‘n’ paste unedited)—

  • Secretary Gates did not formally-target large cost savings within RDT&E and Procurement Accounts. To the contrary, those Modernization Accounts were intended to be the beneficiary from cuts to manpower-intensive Headquarters, plus O&M.
  • The majority of the upcoming Service negotiations on 2012-2016 POM will be conducted by DoD Comptroller; CAPE/PA&E; Joint Staff; and USD(Policy). However, USD(AT&L) has unique Statutory authorities over critical “go/no-go” Milestone-Decision-Authority, transitioning large-dollar Weapons Programs from one phase of the Acquisition cycle into the next, (ranging from Technology Development; to critical Engineering Manufacturing Development; and ultimately Production).
  • Specifically, Dr. Carter is statutorily-responsible for making Milestone Decisions on several large-dollar RDT&E Development Programs that are about to be kicked-off by the Military Services. These include Army Ground Combat Vehicle; continued production of hardware under Army’s Brigade Combat Team Modernization; Navy VXX; Navy SSBN(X); USAF Long-Range-Strike; and Airborne ISR/SIGINT Platforms.
  • This initiative will undoubtedly cause concerns over potential reduction in defense contractor Profits. However, as a general rule, for each dollar of actual labor, hardware contractors often have another 80%-100% Overhead, plus another 25%-33% of Corporate G&A, before Profit is even negotiated. This explains why Dr. Carter is so focused on attacking both exquisite Requirements by the Services, in parallel with pockets of low-value Contractor Overhead/G&A. Ultimately, Contractor Profits pale by comparison, against both excessive Service Requirements, and duplicative Contractor Overhead.
  • This means that the future ‘Discriminator’ in valuing defense contractors, will become those contractors who outperform negotiated Schedule and target Costs, to actually produce larger quantities of affordable platforms, at greater overall Profit.

We note that Jim’s conclusion—that those contactors who “outperform … Schedule and target Costs, to … produce larger quantities of affordable platforms”—will not only have a competitive advantage in the A&D marketplace, but will also enjoy “greater overall Profit,” is pretty much exactly what we’ve been posting here for nearly two years.  Let’s repeat together:  program performance equals profits.

Continuing our theme of the dichotomy between budget cuts and opportunities to grow and thrive, we offer this Reuters story (compliments of Defense Industry Daily).  It points out that U.S. defense budgets may be flattening with respect to domestic sales, but that U.S. defense export sales may well surge in the near future, according to Vice Admiral Jeffrey Wieringa, head of the Defense Security Cooperation Agency (DSCA).  The article states that Vice Admiral Wieringa said in an interview with the news agency that, “U.S. arms sales will be little changed in fiscal 2010 but could surge by nearly one-third to $50 billion next year.”  The article quotes Wieringa as saying, “A lot of countries have built up cash reserves and they intend to continue buying.”  (We think those countries primarily are located in the Middle East, and the article also mentions India and Brazil.)

To address the expected growth in arms exports, the article notes that DSCA has been growing.  According to the article, “Wieringa has worked hard to expand training and staffing for U.S. military and civilian workers involved in global arms sales, boosting his agency's budget from $373 million in fiscal 2007 to an estimated $850 million in the fiscal 2012 budget being drafted now.”  That growth rate is commensurate with the growth rate experienced by U.S. defense exporters … but we can’t help wondering what Secretary Gates thinks of those numbers, when he has recently told the Defense Department to get rid of its bureaucracy.  But perhaps that’s an uncharitable thought, since U.S. A&D companies may well be relying on DSCA to champion their arms exports, and thus keep their top lines healthy and workforces intact.

To summarize, we have tried to present in this article different vectors of analysis on the health of the A&D industry.  While times may appear to be tough—and, indeed, we expect vigorous attempts to shed non-value-added overhead functions (and associated headcount)—the picture is not entirely gloomy.  Certain sectors will continue to grow, and those companies that perform well in those sectors should survive and even thrive.


 

Why Can’t MDA Manage its Programs?

E-mail Print PDF


Recently we inquired into the program management problems at the Department of Homeland Security.  In the past, we asked similar questions of NASA and DOD.  Now we turn our attention to the Missile Defense Agency (MDA), asking why “DOD’s largest single acquisition program” is having performance problems.  Related to that overarching inquiry are two other questions—(1) why do seven of 14 MDA prime contractors have noncompliant EVM systems, and (2) why do two of 14 MDA programs assessed have such unreliable EVM data that GAO was unable to “identify significant performance drivers or forecast future cost and schedule performance.”

We shall start our investigation with this GAO report, entitled “Missile Defense Program Instability Affects Reliability of Earned Value Management Data.”  In that report, GAO made its annual assessment of progress made by the MDA in developing and fielding the nation’s Ballistic Missile Defense System (BMDS).  The report supplements a previous GAO assessment.

By way of background, the GAO report states—

MDA’s mission is to develop an integrated and layered BMDS to defend the United States, its deployed forces, allies, and friends. In order to meet this mission, MDA is developing a highly complex system of systems—land-, sea- and space-based sensors, interceptors and battle management. Since its initiation in 2002, MDA has been given a significant amount of flexibility in executing the development and fielding of the BMDS.

Unlike other major defense acquisition programs, the BMDS has been exempted from the requirements of 10 U.S.C. § 2435 (which requires the programs to establish the total scope of work and total cost baselines), because the Secretary of Defense “delayed” entry of BMDS into DOD’s formal acquisition cycle.  The lack of an established baseline prevents GAO from evaluating progress of the program as a whole; instead, it has to look at each BMDS program on an individual basis.  In this report, GAO looked at 14 MDA programs.

The first thing GAO noticed was that two important programs—Ground-Based Missile Defense (GMD and Targets/Countermeasures—couldn’t be assessed.  The two programs couldn’t be assessed because their Earned Value Management (EVM) data “were not sufficiently reliable to analyze” the contracts’ cost and schedule performance.  What’s going on here?

First, the two programs each had baselines that were “no longer representative of the program of record.”  With respect to the GMD program, GAO reported that the contractor (Boeing) had “experienced difficulty” incorporating “numerous changes to the program and [resulting] modifications to the contract.”  GAO reported—

For example, although the GMD program experienced a $1.3 billion dollar restructure in 2007, another major restructure beginning in fiscal year 2008 for over $500 million that was completed in fiscal year 2009, and a third in fiscal year 2010 for over $380 million, the GMD program has not conducted an IBR [integrated baseline review] since December 2006.  DOD’s acquisition policy states that an IBR is to be conducted within 6 months after contract award, exercise of contract options, or major modifications to a contract.  DCMA officials told us that the GMD program had an IBR underway following the restructure that began in fiscal year 2008 and completed in fiscal year 2009, but in May 2009 the program was again redirected and the baseline review was cancelled.  The Director, MDA explained that some of the GMD program’s baseline instability from frequent restructures was related to the changing GMD role in European defense. … The Director told us that these European capability requirements changes drastically affected the GMD program as a significant amount of work had to be restructured.

With respect to the Targets and Countermeasures program, the prime contractor (Lockheed Martin) was “unable to update its baseline because of numerous program changes.”  GAO reported—

In September 2007, when the delivery order for the launch vehicle-2 was approximately 60 percent complete, Lockheed Martin signaled that its baseline was no longer valid by requesting a formal reprogramming of the effort to include an overrun in its baseline for this delivery order. MDA allowed the contractor to perform a schedule rebaseline and remove schedule variances – but did not provide any more budget for the recognized overrun in the performance measurement baseline. As a result, DCMA reported that the performance indicators for this delivery order, needed to estimate a contract cost at completion, were unrealistic. According to the Director, MDA did not believe the contractor had justified that there was a scope change warranting additional budget in the performance measurement baseline. He said he believed doing so would mask problems the contractor was experiencing planning and executing the contract which he identified as the issue as opposed to changes in the contract’s scope. According to the Director, one example of the issues the contractor was experiencing on this delivery order included a failure rate of 64 percent on production qualification components. … In addition … program changes since fiscal year 2008 on one delivery order included over 20 contract changes to the scope of work or corrective actions to quality issues.

GAO noted that seven of the 14 programs it reviewed were managed by contractors whose EVM systems had been assessed by DCMA as being “noncompliant” with the applicable criteria of the ANSI/EIA standard governing earned value management systems.  Despite this situation, GAO used the EVM data to evaluate the other 12 programs.  It noted that “We reviewed the basis for the noncompliance and unassessed ratings and determined that” the EVM data was reliable enough “for our purposes.”  This finding, of course, begs the question of why DCMA evaluators would find the EVM systems to be inadequate while GAO found the EVMS’ outputs to be good enough.  Some in industry have accused DCMA evaluators of being overly picky in their evaluations … but that topic is probably better left to another article.  We’ll leave it with an example of GAO’s comments—

For example, the EVM system of the STSS contractor Northrop Grumman was deemed noncompliant because of two low-level corrective action requests related to issues with other contracts that did not materially affect the performance baseline for the STSS contract we assessed. Also, the C2BMC’s contractor Lockheed Martin Information Systems & Global Services received a rating of noncompliant during 2009 because of a corrective action request that stated that major subcontractor efforts were not specifically identified, assigned, or tracked in the organizational breakdown structure. However, after the noncompliant rating was given, DCMA reversed its decision and decided to close the corrective action without requiring the contractor to change its methods.

Looking at the 12 programs GAO felt it could review, it noted mixed results.  Some programs performed adequately while others experienced cost growth and schedule slips stemming from such issues as “technical complexity,” “quality issues,” “unanticipated design changes,” “late receipt of hardware and production-level drawings,” etc.  For example, with respect to the Command and Control, Battle Management, and Communications (C2BMC) program, GAO reported—

These budgeted cost overruns are driven by increased technical complexity of Spiral 6.4 development, and more support needed than planned to address requests from the warfighter for software modifications. The $4.2 million of unaccomplished work on the agreement is driven by efforts in the Part 5 portion of the agreement, including delays in system level tests, late completion of C2BMC interface control document updates, and unexpected complexity of algorithm development and network design.

GAO also noted that the STSS program (managed by Northrop Grumman) was on schedule, but nearly $73 million overrun against budget.  There were various reasons attributed to the cost growth, including slippage of the launch dates.  GAO asserted that—

If the contractor continues to perform as it did through September 2009, our analysis projects that at completion in September 2010, the work under the contract could cost from $620.9 million to $1.6 billion more than the budgeted cost of $1.6 billion.

Similarly, the development contract for THAAD (Terminal High-Altitude Area Defense, managed by Lockheed Martin) has experienced cumulative cost overruns of $262 million and is also behind schedule.  GAO reported—

The contractor attributes overruns to the missile, launcher, and radar portions of the contract. The missile’s unfavorable cost variance is driven by unexpected costs in electrical subsystems, propulsion, and divert and attitude control systems. Also contributing are issues associated with the optical block, range safety, communications systems, and boost motors. The launcher has experienced cost growth because of inefficiencies that occurred during hardware design, integration difficulties, quality issues leading to delivered hardware nonconformances, and ongoing software costs being higher than planned because of rework of software to correct testing anomalies. These problems resulted in schedule delays and higher labor costs to correct the problems. In addition, cooling and power issues with the radar have contributed to overruns with the prime power unit. Numerous fan motor control system redesigns and retrofits for the cooling system drove costs by the supplier. Inexperience with building a prime power unit and a limited understanding of the true complexity and risks associated with the system led to significant cost growth and delivery delays.

As we have noted with respect to other Executive Agencies, MDA seems to have experienced the standard challenges associated with developing technically challenging weapon and defense systems.  Requirements changes drive design changes, which affect manufacturing schedules.  Managing changes requires staff and other administrative resources, and often requires technical personnel to take time away from their program “day jobs” to support the administrative change management processes—meaning the program work doesn’t get accomplished as planned.

This GAO report seems to confirm what we’ve been hearing from industry—that DCMA EVMS functional specialists are nit-picking and looking for reasons to withhold EVM system approvals.  GAO was able to find reliable data to evaluate, despite numerous so-called noncompliances.  We hope DCMA quits treating EVMS like Government Property control systems, and develops a sense of materiality and proportionality in its system reviews.

On the two MDA programs with unreliable program baselines, we look to MDA itself as the culprit.  On one program, numerous program restructurings appeared to have significantly impacted the prime contractor’s ability to maintain baseline control.  On the other program, it was MDA’s decision not to revise the baseline when appropriate to do so, that led to the situation where GAO felt the baseline no longer represented a meaningful point from which to measure performance variances.  In addition, GAO noted numerous program changes that impacted the contractor’s ability to maintain baseline control, of such impact that GAO apparently believed the baseline should have been revised.

Here’s the lesson in all this—at least from our point of view.  If you have a technically challenging, complex development program—especially one where requirements are fuzzy and likely to change over time—then you need to expect significant changes.  You need to plan for the changes, and have a plan to manage them.  You need to anticipate the administrative resources necessary to identify, process, and incorporate changes into both the baseline and the contract.  And you need to anticipate the technical resources involved in that process as well.

Change control is one of the key processes that distinguish contractors in the marketplace.  Contractors that have robust change control processes, and that proactively manage the inevitable changes, do better than those that do not.  Period.

So how is your change control process working out for you?


 

It’s Not Always Government Contractors …

E-mail Print PDF


We write quite a bit about alleged and/or admitted fraud by Government contractors.  We have posted many articles about alleged and/or admitted fraud by military and civilian government officials.  We’d post links but, frankly, there are already too many corruption stories here and all you have to do is visit the News Archive to find them for yourselves.

But today we take a different slant on things.  Today we look at fraud, alleged and/or admitted, outside the Governmental arena.  Why do we do that?  We do that because we hope it will be instructive.  Generally and broadly speaking, internal controls are largely the same whether one is a defense contractor or a manufacturer of consumer electronics.  The need for segregation of duties, for example, is largely the same—as is the need for an involved senior management and board of directors.

So let’s peek outside our box of government contracting; let’s look up from perusing the FAR and trying to interpret CAS for just a few minutes, and let’s see what the rest of the world is up to—in terms of fraud and corruption—courtesy of daily Department of Justice press releases.

First we look at two stories of international corruption.

Technip S.A. Resolves Foreign Corrupt Practices Act Investigation and Agrees to Pay $240 Million Criminal Penalty – There have been bigger FCPA penalties, but not very many.  According to this DOD press release, the Paris-based “global engineering, construction, and services company” agreed to pay that ginormous penalty in order to resolve FCPA charges related to “its participation in a decade-long scheme to bribe Nigerian government officials to obtain engineering, procurement and construction (EPC) contracts.”  The DOJ release stated, “At crucial junctures… a senior executive of Technip, KBR’s former CEO, Albert "Jack" Stanley, and others met with … the executive branch of the Nigerian government to … designate a representative with whom the joint venture should negotiate bribes to Nigerian government officials. The joint venture paid approximately $132 million to a Gibraltar corporation controlled by Tesler and more than $50 million to the Japanese trading company during the course of the bribery scheme.”

Continuing our theme of international corruption, we offer the following.

Italian Executive Extradited from Germany to the United States to Face Foreign Bribery Charges – Another DOJ announcement stated, “Italian citizen Flavio Ricotti, a former executive of Rancho Santa Margarita, Calif.-based valve company Control Components Inc. (CCI), has been extradited to the United States from Germany in connection with his alleged participation in a conspiracy to secure contracts by paying bribes to officials of foreign state-owned companies as well as officers and employees of foreign and domestic private companies.”  Allegedly, “Ricotti, who served as CCI’s vice president and head of sales for Europe, Africa and the Middle East from 2001 through 2007,” oversaw more than $1 million worth of “corrupt payments” that were allegedly designed to secure work for his company.  In addition, five other CCI executives were charged in the 16-count indictment, including, “five former CCI executives also charged are Stuart Carson, CCI’s former chief executive officer; Hong (Rose) Carson, CCI’s former director of sales for China and Taiwan; Paul Cosgrove, CCI’s former director of worldwide sales; David Edmonds, CCI’s former vice president of worldwide customer service; and Han Yong Kim, the former president of CCI’s Korean office.”

Next, looking at the domestic U.S. commercial marketplace, we bring you the final story of corruption, as abetted by stupidity and naïveté. 

Former Koss VP of Finance Pleads Guilty to Embezzling Millions and Millions -- We have been following the tale of Koss Corporation and its former Vice President of Finance, Sujata Sachdeva, for some time. On July 17, 2010, Ms. Sachdeva pleaded guilty to six counts of wire fraud for embezzling roughly $34 million from her employer over a period of approximately 11 years.  Ms. Sachdeva (or “S-Squared” as she’s called on www.goingconcern.com, where one can find quite a few stories on this topic), faces anywhere from 6 to 20 years in prison.  According to this story, “she stole the money from the headphone maker to pay for extravagant shopping sprees and lifestyle amenities that included using Koss funds for clothes, cars, trips, china, statues and home furnishings.“ 

According to the stories linked-to above, S-Squared admitted that, “During the 12-year span she authorized the issuance of more than 500 cashier's checks costing Koss about $17.5 million. That figure includes $10 million to American Express, plus payments to high-end retailers, including Neiman Marcus and Saks Fifth Avenue. Payments also went to charitable groups.”  In addition, “From February 2008 to December 2009, she authorized 206 wire transfers totaling $16 million from Koss accounts to American Express to cover items she bought with the credit card.”  The plea agreement stated that Koss employees worked ‘in concert with Sachdeva or at her direction’ to make fraudulent entries to the company's books to conceal the embezzlement. ‘These entries would falsely overstate assets, understate liabilities, understate sales, overstate cost of sales, and overstate expenses,’ and the false entries ‘concealed the actual receipts and profitability of Koss,’ allowing the scheme to continue. 

S-Squared knew how the company’s auditors worked.  According to the plea agreement, “Sachdeva did not fraudulently take money from Koss accounts at Park Bank during the month of June, because transactions during that month were reviewed by outside accountants.” 

According to the news reports, the scheme “came to light in December when American Express told Michael Koss - who at the time held five high-level titles at the company, including CEO and chief financial officer - that money was being transferred from company accounts to pay for Sachdeva's luxury shopping bills.”

This blog post by Francine McKenna at www.retheauditors.com makes some good points about Sachdeva and Koss.  Here are a few of Ms. McKenna’s comments—

  • Listing standards for the NYSE require an internal audit function. NASDAQ, where Koss was listed, does not.
  • Management oversight of the financial reporting process is severely limited by Mr. Koss Jr.’s lack of interest, aptitude, and appreciation for accounting and finance. Koss Jr., the CEO and son of the founder, held the titles of COO and CFO, also. Ms. Sachdeva, the Vice President of Finance and Corporate Secretary who is accused of the fraud, has been in the same job since 1992 and during one ten year period worked remotely from Houston!

Despite the foregoing, the Koss Corporation has filed suit against American Express (contending that it should have alerted the company earlier), against former auditors Grant Thornton (contending that it should have detected the embezzlement during performance of audit procedures), and against Ms. Sachdeva herself (d’oh).

Conclusion

Each of the stories included herein describe unfortunate actions of a corporate executive management team, actions that violated law as well as ethical standards. In some instances, the executives colluded with each other, or with executives of other companies, in order to carry out their schemes. DCAA audit procedures direct that an assessment be made of management integrity and “tone at the top.”  We don’t know, exactly, how one does that.  But we do know that these stories reinforce the importance of doing so.



 

Government Contract Math: False Timesheets Equal False Statement Equals Prison Time Plus Fine

E-mail Print PDF


For some of us, Algebra was our Waterloo.  Others had trouble with Geometry.  Still others made it to Trigonometry, Statistics, Calculus, and/or other college and graduate-level courses.  The point is, almost everybody struggles with math at some point in their lives.  Most of us get just so far, but no further.  At point, we hit the math wall and we give up.

For Donna Mitchell, her moment of surrender came at age 69, when she encountered Government Contract Math.  Her sad story can be found here.

Ms. Mitchell was employed by Dragon Development Company, a government contractor.  Dragon Development was acquired by CACI, International, Inc.—another government contractor—in November, 2007.  At the time of acquisition, Dragon Development was a subcontractor to the Titan Corporation, who had a prime contract with the National Security Agency (NSA) for “document delivery services.”

From the period January, 2006 through December 28, 2007 (a full two years), Ms. Mitchell—

--submitted timesheets to Dragon and CACI falsely claiming that she had worked 752 hours more than she had actually worked on the Services Contract. Mitchell represented in some of the timesheets that on 24 days she worked an average of eight hours, when in fact, she did not work at all on those days.

So over a two-year period, Ms. Mitchell over-reported her time by about 20 percent (752 / 4,360 = 17.25%, to be exact).

Dragon/CACI invoiced Titan for Ms. Mitchell’s inflated labor costs.  In turn, Titan invoiced NSA.  NSA paid the contractors “approximately $81,859” for the unworked hours. 

On July 21, 2010, Ms. Mitchell pleaded guilty to “making false statements arising from the number of hours she claimed she worked.”  According to the DoJ press release (link above), “Mitchell faces a maximum sentence of five years in prison and a $250,000 fine.”

We call that learning math the hard way.

Post-script—

In August, 2009, we posted a point of view regarding the necessary due diligence to be performed during a merger/acquisition between two government contractors.  At that time, we said—

When contemplating the acquisition of any business that sells goods and/or services to the Federal government, it is important to evaluate the probability of contingent liabilities, and factor them into the deal. Government contracts, by their very nature, have long tails. Thus, after an acquisition an allegation of wrongdoing can surface that relates to actions that took place literally years before. Records can be missing, personnel may have departed, but the acquiring company still has to deal with the issue(s). It is critical to structure the deal so as to protect the acquiring entity from such contingent liabilities.  Typically this is done either through purchase price adjustment, establishment of an escrow fund, or both.



During the due diligence phase of the acquisition, it is critical to evaluate existing internal and operational controls, administrative attention to detail, and to try to assess the probability that a contingent liability will surface after acquisition.

We see no reason to change our point of view on this topic.  We don’t know the depth and/or rigor of CACI’s due diligence efforts during its acquisition of Dragon Development.  We don’t know whether CACI was held liable in a separate proceeding, or if the company was able to negotiate its way out of trouble.  But we do know that if Ms. Mitchell’s “math difficulty” had been identified as a potential contingent liability prior to the acquisition, CACI could have taken steps to protect itself.


 

Organizational Conflicts of Interest – A Success Story!

E-mail Print PDF


The Federal Acquisition Regulations (FAR) define an organizational conflict of interest as a conflict that may occur when “because of other activities or relationships with other persons, a person is unable or potentially unable to render impartial assistance or advice to the Government, or the person’s objectivity in performing the contract work is or might be otherwise impaired, or a person has an unfair competitive advantage.”

Accountants don’t care very much about organizational conflicts of interest (OCIs).  OCIs have nothing to do with debits or credits or dollar signs.  But companies who want to successfully capture government work need to care about OCIs—quite a bit, actually.  We’ve previously discussed OCIs here and also here, and also over here, noting that—

Savvy readers will understand that the regulations are just words, and that the words are given meaning and come alive via interpretations provided by the Courts. So it is, with respect to OCIs, that the Government Accountability Office (GAO) and the U.S. Court of Federal Claims (CoFC) have interpreted various aspects of OCI rules in their bid protest decisions.

OCIs are intractable little problems, both vague and complex by their very nature.  Normally, one hears about OCIs when somebody protests an award.  Sometimes OCIs arise in the context of testing products for acceptance and/or suitability.  Here’s a story about an OCI in the context of a bid protest.  What makes this story different is that the Court found the elimination of a bidder, based solely on an alleged OCI, to be unreasonable.  We think it’s worth exploring a little.

On July 16, 2010, the U.S. Court of Federal Claims issued a decision in the matter of Turner Construction Co., Inc. v. United States, with McCarthy/Hunt, J.V. and B.L. Harbert-Brasfield & Gorrie, JV, as intervenors.  At stake was the contract to replace the Army Community Hospital at Fort Benning, Georgia.  The contract was originally awarded to Turner in September, 2009, after 15 months of conducting the procurement and evaluating offerors.  Two competitors (the “intervenors” in the current action) protested the award to the Government Accountability Office (GAO).  In February, 2010, GAO recommended that the Army should “strip Turner of the contract” because of Turner’s alleged OCIs, and “reprocure the contract.”  In March, 2010, the Army announced that it would “not waive” Turner’s OCIs, and follow the GAO recommendation.  Turner protested that decision before the Court of Federal Claims.

Turner argued that the GAO bid protest decision and subsequent recommendation to the Army “lacked a rational basis.”  In addition, Turner argued that the Army accepted GAO’s recommendation without evaluating it, and did not “reasonably evaluate” Turner’s request to waive its OCIs.  Turner’s alleged OCIs are rather complex so we’ll devote some space to discussing them.

To develop its hospital design, the Army obtained technical design assistance from a Joint Venture consisting of Hayes, Seay, Mattern, & Mattern (HSMM) and Hellmuth, Obata & Kassbaum, Inc. (HOK).  HSMM was a wholly owned subsidiary of AECOM.  As part of its duties, HSMM assisted the Army’s Technical Review Board in evaluating proposals received from bidders on the hospital replacement project.  Turner was not only the lowest price offer, but the company also scored well in the technical evaluations. 

Turner’s proposal anticipated awarding a subcontract to a Joint Venture consisting of Ellerbe Becket (EB) and another firm.  In October, 2009, after a long courtship, EB was acquired by AECOM.  In July 2009 (during the courtship), it came to the attention of one the HSMM participants that an OCI might exist, as AECOM was then in negotiations to acquire EB.  (Note that the OCI might be created because AECOM would own a participant in the proposed project (EB) and a participant in the project design (as well as a participant in the technical evaluation) (HSMM).  This “alignment of interests” might be sufficient to create an OCI.)  The HSMM employee immediately brought the matter to the attention of the Contracting Officer and the Army’s legal counsel.  They decided that the one HSMM participant who knew of the potential merger would recuse himself from further participation in the proposal evaluations, but that the other HSMM participants, who were not aware of the ongoing discussions between EB and AECOM, would be allowed to continue their participation.

We have discussed before the three “different flavors” of OCI.  With respect to the award of the hospital replacement contract to Turner, “both protesters alleged the existence of ‘biased ground rules’ and ‘impaired objectivity’ OCIs, and McCarthy/Hunt additionally alleged an ‘unequal access to information’ OCI,” according to the Court.

During the protest proceedings before the GAO, the Contracting Officer “addressed each possible type of OCI and found that no OCIs existed prior to award of the contract.”  However, GAO “disagreed” with those conclusions, and “sustained the ‘unequal access to information’ and ‘biased ground rules’ protests.”

While the protest was pending before the GAO, much discussion and debate ensued regarding whether the Army would waive any OCIs.  As the Judge Futey (writing for the Court) reports, ultimately the Army decided not to grant Turner a waiver.

After receiving the GAO’s recommendation, the Army terminated Turner’s contract and Turner filed a protest with the CoFC.  Based on the protest grounds, the Court needed to review the GAO’s decision, even though normally such decisions are granted “a high degree of deference.”  But the deference shown to GAO’s decisions is not absolute, and executive agencies cannot simply rely on a GAO decision to implement an unreasonable course of action.  As the Judge Futey wrote, “an Agency’s decision to follow the recommendation of the GAO in a bid protest decision is arbitrary and capricious if the GAO decision was irrational.”  Judge Futey found—

According to Turner, the GAO conducted a de novo review of the record that supplanted the CO’s decision, which was based on ‘hard facts,’ with a decision based on ‘mere inference and suspicion.’ … plaintiff [Turner] argues that ‘the assessment of OCIs is a fact-specific inquiry the CO must undertake, and under the facts here, the CO reasonably concluded there was no OCI, and GAO erred in substituting its judgment for that of the CO.’

Judge Futey concluded that, “it was irrational in this case to depart from precedent and not consider the factually-based arguments of Turner and the Army, especially when the GAO was tasked with looking for ‘hard facts’ of an OCI.”  Moreover, Judge Futey wrote that—

This Court thus finds that the GAO lacked a rational basis because it overturned the CO’s determination without highlighting any hard facts that indicate a sufficient alignment of interests. Because the GAO lacked a rational basis, the Army was not justified in following its recommendation. …

… the GAO failed to adhere to the proper standard of review. The GAO’s task was to review the agency’s decision for reasonableness. That agency decision, as described above, tracked the precise state of negotiations between AECOM and EB, the exact dates upon which critical changes to the RFP occurred, the exact employees that could have known of the merger, and numerous other facts. Using this data, the CO concluded that no OCI existed. The GAO failed to address this OCI decision; in fact, the GAO decision on a biased ground rules OCI does not even cite the agency decision that it was tasked with reviewing. Instead, the GAO cites exactly one piece of information—the text of AECOM’s contract with the agency—to support its finding that the record ‘suggests’ that AECOM had ‘special knowledge’ that would have given Turner an unfair advantage. 

(Emphasis in original.)

Turner was granted the permanent injunction it sought.  The Army was ordered by the Court to “restore” the original hospital replacement contract to Turner and “not reprocure the contract to another firm.”

Are there any lessons to be learned here?  We think so.  When two Government contractors are considering a merger/acquisition, it is important to review existing contractual relationships to see if any actual, or potential, OCIs might exist.  And it is not only existing contracts that need to be reviewed, but also future contracts and pending proposal submissions.  Pipelines of potential contract activity need to be reviewed with a discerning eye, to see if a situation like that experienced by Turner might exist.

And please note that Turner itself did not have the alleged OCI.  It was Turner’s subcontractor, EB (who was actually one member of a Joint Venture), that had the alleged OCI.  This fact suggests that the level of due diligence inquiry needs to be quite a bit more granular than simply looking at the two prime contractors to see if a potential OCI might exist.  This is a demanding task, and one that time and budgetary constraints might not always permit.  But as this article demonstrates, one ignores that level of inquiry at one’s own peril.



 


Page 229 of 278

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.