Government Contractor Fraud in the News

We recently posted an article about fraud in the commercial and international marketplaces. (We could keep on posting similar articles, such as this one,
but we won’t.) Other past articles have focused on corrupt activity by
military or civilian government employees. Our point—which we’ve made
before—is that a myopic focus only on government contractors misses the
bigger picture. Fraud and corruption are endemic to the human
condition, and they flourish where weak people and their temptations
meet lax oversight and/or ineffective controls. Enhance the control
environment and you reduce the opportunity for miscreants to break the
rules.
But
today we are reporting on yet more government contractors who are in
the news because of alleged wrongdoing. Let’s start first with John
Feeney, of Woodbridge, Virginia—who at age 28 has pretty much ruined the
rest of his life. According to the Department of Justice, Mr. Feeney pleaded guilty
to one count of mail fraud on July 28, 2010. Interestingly, Mr. Feeney
thought he was defrauding only his employer, BAE Systems Training
Services, Inc. Unfortunately for him, BAE Systems was a government
contractor whose expenses were reimbursed by Uncle Sam’s Defense
Department—meaning Mr. Feeney was really defrauding the U.S. Government,
who frowns on that sort of thing.
According to the DOJ press release, Mr. Feeney was a logistics engineer who “used
his position to authorize the purchase of camera lenses and video
equipment, intending to keep the equipment for his personal use but to
bill BAE for the purchases.” Mr. Feeney made 15 such “illicit
purchases” between August 2005 and June 2006, which cumulatively were
worth $476,424. Let’s repeat that: Mr. Feeney purchased nearly half a
million dollars worth of camera lenses and video equipment in less than a
year, and sent the bills to his employer, who was apparently pleased to
pay them.
What
did he do with his ill-gotten treasure of photographic goodness? The
DOJ reported that “Feeney subsequently sold many of the purchases on
an Internet auction site for profit.” As
we mentioned, Mr. Feeney’s employer had a contract at that time with
the DOD, under which “BAE would purchase surveillance equipment and
subsequently bill the U.S. government for those purchases.” In
fact, Mr. Feeney’s job was to purchase the equipment for the contract.
BAE Systems billed the DOD for $464,819 of the equipment he
fraudulently acquired. We don’t know how Mr. Feeney was caught, but
caught he was.
According to the DOJ, “The mail fraud count carries a maximum penalty of 20 years in prison, a
$250,000 fine or twice the gross gain or loss, whichever is greater, as
well as three years of supervised release.“ That pretty much takes
care of the rest of Mr. Feeney’s career.
Next,
we report the settlement of a False Claims Act case against Quantum
Dynamics, of Macon, Georgia. On July 29, 2010, the DOJ announced
that it had reached a settlement with the company, who allegedly
received contracts from the U.S. Army by fraudulently claiming to be a
HUBZone contractor. As the DOJ noted—
Under
the HUBZone program, companies that maintain their principal office in a
designated HUBZone and employ 35 percent of their workforce from a
HUBZone, among other requirements, can apply to the Small Business
Administration (SBA) for certification as a HUBZone small business
company. HUBZone companies can then use this certification when bidding
on government contracts. In certain cases, government agencies will restrict competition for a contract to HUBZone-certified companies.
Because
Quantum Dynamics did not qualify as a HUBZone company, its
representations that it was one created a false statement (under the
False Statements Act). Because it billed the Government for the
fraudulently obtained contracts, its invoices were considered to be
“false claims” that subjected the company to considerable liability.
The reported settlement figure--$750,000—indicates to us that either the
prosecutors felt there was some question as to the company’s intent to
defraud, or else that the company was short on financial resources and
there was little use asking for more. (Actually it could be both, as
the HUBZone rules are complex and difficult to understand.) The DOJ
press release did not report which company would be completing the work
started by Quantum Dynamics.
Next, we report that on the same day (July 29, 2010) DOJ announced that it had intervened in a qui tam
False Claims Act suit against Oracle Corporation (and its subsidiary
Oracle America, Inc.) for allegedly failing to disclose its commercial
sales practices to the General Services Administration (GSA)—which then
would allegedly lead to the government paying higher prices than it
otherwise would have. The DOJ reported that Oracle billed GSA “hundreds
of millions of dollars in sales” under the contract, so we’re not
hopeful that Oracle can settle the suit for less than a million dollars,
as Quantum Dynamics did.
What did Oracle (allegedly) do wrong? According to the DOJ—
Under
the contract, GSA used Oracle’s disclosures about its commercial sales
practices to negotiate the minimum discounts for government agencies who
bought Oracle software. The contract required Oracle to update GSA when
commercial discounts improved and extend the same improved discounts to
government customers. The suit contends that Oracle misrepresented its
true commercial sales practices, ultimately leading to government
customers receiving deals far inferior to those Oracle gave commercial
customers.
The
DOJ noted that the suit was originally filed by Paul Frascella, who was
the Senior Director of Contract Services at Oracle, and who might be
expected to know Oracle’s sales practices. The suit, United States ex rel. Frascella v. Oracle Corp. et al., No. 1:07cv:529 (E.D.
Va.), may make Mr. Frascella a rich man, since as “relator” he will
share in any damages awarded by the Court to the United States.
Finally, we wanted to relate this sad tale of corruption in the executive ranks of a defense contractor. (Here’s the link,
but you need to be a member to access the story.) This is not so much a
story of defrauding the U.S. Government, as it is a story about
“sweeping accusations of fraud, insider trading, and company-financed
personal extravagance.” According to the New York Times story, David
Brooks (former CEO and Chairman of the Board at DHB, now called Point Blank Solutions)
received corporate reimbursement for “more than $6 million in personal
expenses”—including luxury cars as well as “university textbooks for his
daughter, pornographic videos for his son, plastic surgery for his
wife, a burial plot for his mother, prostitutes for his employees, and,
for him, a $100,000 American-flag belt buckle encrusted with rubies,
sapphires and diamonds.”
Hey, some of that stuff might be unallowable!
As
the article noted, what makes this story interesting is the
egregiousness of Mr. Brooks’ behavior and “how gross the abuses are.”
The article stated that—
Mr.
Brooks has not disputed that many of his personal expenses were paid
for by the company, but his lawyers have maintained that the practice
was authorized. His lawyers also defended the hiring of prostitutes for
employees and board members, arguing in court papers that it
represented a legitimate business expense ‘if Mr. Brooks thought such
services could motivate his employees and make them more productive.’
There’s
quite a bit more to the story, including allegations of forged
compensation agreements, inventory manipulation, insider trading, and
tax evasion. If convicted, Mr. Brooks may be spending a long time
behind bars. Apparently, Mr. Brooks is aware of his precarious future,
as the article reported that—
He
may also face additional charges stemming from an episode last week
when he was caught for a second time trying to smuggle into jail
prescription anti-anxiety pills, which were similar to medication he was
already taking at an unusually high dose. The pills had been hidden in
pens that a supporter of Mr. Brooks’s had placed near the defendant’s
seat in the courtroom.
So
as we bring this article to its conclusion, we agree that we have
presented litany of dissimilar stories that may not have much of a
common theme—other that they all happened at government contractors. On
the other hand, government contractors are supposed to have developed
robust internal controls to prevent such acts from occurring. We hope
readers will think carefully about how they might detect or prevent
similar incidents at their companies.
Former State Department Employee, IRMO Advisor, Charged with Wire Fraud and “Conversion”
Conversion—“An
authorized assumption and exercise of the right of ownership over goods
… belonging to another … Any unauthorized act which deprives an owner
of his property permanently or for an indefinite time. Unauthorized and
wrongful exercise of dominion and control over another’s personal
property … See also Embezzlement, … Fraudulent Conversion …”
-- Black’s Law Dictionary, 6th Edition
On July 22, 2010, the Department of Justice announced
that Robert Hearn, of Temple, Texas, had been arrested and indicted for
wire fraud and conversion, stemming from an alleged “orchestration” of
the transfer of “approximately 60
accommodations caravans and other equipment from the site of a
U.S.-funded power plant project in Khor Az Zubair, Iraq, to the port” of
Umm Qasr, in Basra, Iraq. Mr. Hearn was employed by the State
Department an assigned to the Iraq Reconstruction Management Office
(IRMO) from April 2005 through September 2006, where he “was responsible
for providing advice to the director of the port,” who was “an official
with the Iraqi Ministry of Transportation.”
The
indictment alleges that Mr. Hearn, who was allegedly reassigned for
“failure” to properly advise the port director, carried out a number of
unauthorized acts while assigned to port Umm Qasr. Among the allegedly
unauthorized acts were the following—
- (Allegedly)
in December 2005, Mr. Hearn accepted the transfer of the 60
“accomodations caravans” to IRMO, even though he lacked the authority to
do so and “U.S. officials notified Hearn that IRMO did not have the
necessary property-management structure and therefore could not take
control of the equipment.” Subsequently, Mr. Hearn (allegedly)
“directed an Iraqi employee of the Ministry of Transportation to sign
for and accept the equipment on behalf of the Iraqi government.”
- (Allegedly)
the individual who signed for the equipment also was employed by
Bawabet Al Amer Company (BAC), a private Iraqi company operating at the
port. BAC provided security, through subcontractors, as well as lodging,
office space and dining services for government and private personnel.
The indictment alleges that from the summer of 2005 to the fall of 2006,
Hearn controlled the day-to-day operations of BAC, and on behalf of BAC
and a silent investor, negotiated business contracts, provided input in
BAC’s hiring decisions and directed the work of BAC employees.
- (Allegedly)
Hearn signed a three-year lease agreement on Jan. 1, 2006, on behalf of
IRMO, permitting BAC to use a portion of the port, which during Hearn’s
tenure became known as "Bob’s Camp." Hearn … had no authority to enter
into this agreement in his official capacity with IRMO and did not
discuss it with his supervisors. A portion of the transferred
accommodations caravans was installed by BAC employees in "Bob’s Camp."
- (Allegedly)
on Sept. 14, 2006, the day before Hearn was scheduled to be reassigned
to IRMO’s Baghdad office, he … negotiated a rental agreement on behalf
of BAC involving several of the transferred accommodations caravans. …
Hearn directed that rental payments be wired to a bank account in
Conroe, Texas, which he controlled. In this manner, Hearn allegedly
received $147,000 from the lessee business, which he used for personal
and business expenses.
The
DOJ announced notes that, “if convicted, Hearn faces 20 years in prison
and a $250,000 fine on each of the four wire fraud counts. If convicted
on the conversion charge, he faces a maximum of 10 years in prison and a
$250,000 fine.” For those doing the math, Mr. Hearn is facing 30 years
in prison and $1,250,000 in fines. How come he gets the book thrown at
him when others, including Major Sublett, Sergeant Chase, and Captain Mike, get away comparatively scott-free? Are the notorious bleeding-hears of Foggy Bottom actually tougher on miscreants than the Department of Defense? One can only wonder ....
|
DCAA Director Fitzgerald Testifies Before CWC; Blasts LOGCAP Subcontractor Management
On July 26, 2010, the Commission on Wartime Contracting in Iraq and Afghanistan (CWC) held a hearing
entitled “Subcontracting: Who’s Minding the Store” to address concerns
about the subcontracting process in Southwest Asia. As the Commission
Co-Chairs noted, “Poorly conceived, poorly structured, poorly conducted,
and poorly monitored subcontracting can lead to poor choices in
security measures and damage to U.S. foreign-policy objectives, among
other problems.” Accordingly, the Commission explored “whether,
especially in a high-risk, contingency environment, the government needs
additional controls over, or more visibility into, subcontractor
performance and costs to ensure the prime contractor is adequately
managing its subcontractors.”
(We
have reported on several of the CWC hearings and reports before. To
find those stories, type “CWC” in the search window on the website.)
Before
we delve into DCAA’s testimony, we want to note a statement made by the
Commission Co-Chairs (Shays and Thibault). They said that the
Commission “will issue a major report with proposals for statutory and
administrative changes in December, followed by our final report to
Congress in July 2011.” So we are in our final year of CWC activity.
We look forward (with more than a little trepidation) to reading the
Commission’s recommendations for “statutory and administrative
changes.” Now on to the hearing….
The
hearing consisted of three panels, logically arranged into (1)
Government, (2) Prime Contractors, and (3) Subcontractors. Looking at
the first panel, we were less than impressed with the “motherhood and
apple pie” written statements from most of the participants. DCAA
Director Patrick Fitzgerald’s written statement,
however, piqued our interest. Lying amongst his platitudes and
smooth-talk were some gems of note. Let’s look at those, shall we?
Director
Fitzgerald told the Commission that DCAA has 34 full-time auditors
assigned to audit contingency contractors in Iraq, Kuwait, and
Afghanistan. 17 are assigned to the Afghanistan Branch Office (ABO) and
17 are assigned to the Iraqi Branch Office (IBO). By the end of GFY
2010 (September 30, 2010), DCAA expects to increase its workforce to 40
full-time auditors.
Director
Fitzgerald also testified that, “As noted in the Commission’s interim
report (June 2009), adequate contractor business systems are the first
line of defense against waste, fraud and abuse. In the realm of
subcontracting, we find this statement to be profoundly true.” What did
he mean by that statement?
As
Director Fitzgerald explained to the Commissioners, “With respect to
the three LOGCAP IV performance contractors, DCAA has reported all the
estimating systems as inadequate and cited their estimating practices as
being deficient for ensuring fair and reasonable subcontract prices.”
In addition, “DCAA has performed contractors’ purchasing system reviews
(CPSRs) for the Defense Contract Management Agency (DCMA) Administrative
Contracting Officer (ACO) at all of the three LOGCAP IV performance
contractors and has found each system to be inadequate.” Moreover,
Director Fitzgerald told the Commission, “During our review of prime
contractor billings and incurred cost audits, DCAA has identified
situations where the prime contractor has not awarded its fixed-price
subcontracts based on fair and reasonable prices leading to unreasonable
or unallowable costs being paid by the Government.”
Reasonableness of Subcontractor Costs
It
is one of the few unavoidable requirements placed on Government
contractors that, prior to making a subcontract award, the prime must
first make a written determination that the price it proposes to pay is
fair and reasonable. (See FAR 15.404-3(b), which requires a prime
contractor (or higher-tier subcontractor) to “conduct appropriate cost
or price analyses to establish the reasonableness of proposed
subcontract prices.”) So when Director Fitzgerald says the LOGCAP IV
prime contractors are failing in their duty to perform the requisite
analyses, that statement gets our attention.
Director Fitzgerald provided some details to support his assertion. He told the Commission—
In
March 2010, DCAA reported estimating system deficiencies at DynCorp
related to the inclusion of unsupported subcontract costs … for Corps
Logistics and Support Service, Theatre Transportation Mission and Postal
Operations in Iraq (commonly referred to as the CTP proposal). During
the audit of the CTP proposal, the auditors found the subcontract
proposal from DynCorp’s then “team member” subcontractor, Agility, to be
inadequate. An examination of the U.S.-based Agility business unit
disclosed that approximately 40 percent of the proposed direct costs
were unsupported. That is, the subcontractor, Agility, was unable to
support the reasonableness of the proposed direct labor costs proposed
as part of the CTP proposal. Further, in its proposal to the prime
contractor, Agility included lower-tier subcontractors to perform the
bulk of the subcontract effort. In fact, Agility proposed to use two
foreign-based Agility-affiliated subcontractors (sister business units).
… During the review of one affiliate’s proposal, the Iraq Branch found
the lower-tier subcontractor had only prepared a rough order magnitude
proposal without supporting detailed data. In the case of the other
lower-tier subcontractor, the Iraq Branch was initially denied access
supposedly on the basis that its prices were commercial prices and
exempt from any requirement for the submission of cost or pricing data.
As a result, the auditors determined that almost all of the proposed
Agility (and its affiliated subcontractor) costs were unsupported. … As a
result, the DCAA audit report classified over $800 million of the
proposed subcontract costs predominately related to Agility and its
affiliates as unsupported. It is important to point out that the prime
contractor had not performed adequate subcontract cost or price
analyses. The DCAA reported the contractor proposal was not adequate for
the basis of negotiating/awarding a fair and reasonable contract price.
But DynCorp wasn’t alone. As Director Fitzgerald told the Commissioners—
Our
audits of KBR proposals have disclosed similar significant unsupported
subcontract costs. In May 2010, DCAA issued its report on the LOGCAP III
Task Order (TO) 151 extension proposal. We identified over $48 million
of unsupported subcontract costs. KBR failed to obtain subcontract
proposals and conduct the required price or cost analyses. The
contractor’s failure to obtain adequate support from its prospective
subcontractors on this sole-source procurement increases the likelihood
of subcontract prices being unreasonable in amount. Similarly, earlier
this month, we completed an audit of Fluor’s “rebaseline” proposal under
LOGCAP IV TO 0002 that incorporated the impact of numerous change
orders on the total task order price. The change orders included
proposed subcontract costs of approximately $35 million. DCAA reported
over 40 percent of the proposed subcontract costs as unsupported because
the prime contractor’s proposal lacked sufficient supporting
documentation (e.g., cost or price analysis, competitive quotations).
The majority of the proposed subcontract costs that we reported as
unsupported were from foreign subcontractors of Fluor where, despite the
sole source nature of the contracting action, Fluor did not obtain cost
or pricing data from the related subcontractors.
DCAA’s
procedures did not stop at evaluating the adequacy and reasonableness
of proposed pricing. Indeed, DCAA proposed to disallow the cost of
paying already-awarded subcontracts when price reasonableness could not
be established. As Director Fitzgerald stated—
During
our review of prime contractor billings and incurred cost audits, DCAA
has identified situations where the prime contractor has not awarded its
fixed-price subcontracts
based on fair and reasonable prices leading to unreasonable or
unallowable costs being paid by the Government. For example, DCAA has
identified several cases where the prime contractor asserted the
subcontract price was based on adequate competition; however, our audit
disclosed that adequate competition did not exist. Although the prime
contractor is required to pay its fixed price subcontract amount, FAR
52.216-7 and the FAR 31.2 principles state the Government only makes
payments of amounts determined to be allowable and reasonable.
Therefore, where DCAA has determined that the subcontract price is not
fair and reasonable DCAA has attempted to calculate a reasonable amount
for reimbursement of the contractor’s billings attributed to
subcontractor costs. However, in those cases where the subcontract is
sole source, it is often difficult to obtain cost data to ascertain the
reasonable costs without access to the subcontractor’s books and
records. DCAA access to subcontractor books and records is generally
limited and dependent on the flow down by prime contractor to the
subcontractor of the appropriate FAR clauses, and in instances of fixed
price subcontracts, virtually nonexistent. For example, during DCAA’s
reviews of Fluor vouchers submitted for payment under a LOGCAP IV Task
Order, the prime contractor was unable to show the prices paid to its
subcontractor for DFAC and other services were fair and reasonable in
amount. Since DCAA does not have access to the subcontractor’s books and
records, we were unable to determine through other processes the
reasonableness of the prices being paid to the subcontractor and
subsequently passed on to the Government for reimbursement. As a result,
the DCAA auditors have suspended much of the subcontractor’s costs from
payment on vouchers (invoices) submitted for payment by Fluor. In
addition, the contractor has been withholding a portion of the
subcontractor billings, so that in total approximately $24.5 million is
being withheld from payment until the issue is settled. The FAR audit
access clause does not provide for Government access to the
subcontractor’s costs records when the subcontract is firm-fixed-price.
To
wrap up our review of Director Fitzgerald’s testimony, we want to recap
a couple of his concluding remarks. The following are direct quotes
from his written statement.
- Prime
contractors have the responsibility to manage their subcontracts (FAR
42.202(e)(2)) and also have a fiduciary responsibility to monitor
subcontractor performance and control costs to ensure the U.S. taxpayer
resources are used wisely and appropriately. … we have found that prime
contractors have not consistently monitored subcontractor performance
and subcontractor billings submitted to the prime contractor for
inclusion in the prime contractor’s billings to the Government. Although
the FAR requires the management of subcontracts by the prime contractor
and higher tier subcontractors, DCAA intends to recommend a review to
the Director, Defense Procurement and Acquisition Policy, of the
feasibility of specific contract clauses that would implement the basic
FAR provision on management of subcontracts. For example, prime
contractors should have systems or processes in place to review
subcontractor billing processes to ensure subcontract billings are in
accordance with subcontract terms and conditions.
- Based
on our audit results we question whether there was adequate/true
competition considering the limitations that the contractors have in a
contingency environment. In Iraq and Afghanistan, U.S. and coalition
military organizations most likely have consumed almost all of the
capacity of most or all subcontractors capable of performing in-theater.
Therefore, at best, competition within the area of a contingency is
limited because the Government-required goods and services generally
exceeded vendor capacities (that is, the Government is the sole or major
purchaser of goods and services from all vendors) and all vendors are
provided a portion of the requirements in order to satisfy the
Government’s needs. In such circumstance, we do not believe competition
and/or market forces provide better prices to the Government and believe
cost data should be provided to determine fair and reasonable
subcontract prices.
- DCAA
has taken exceptions to several subcontract pricing actions where the
prime contractor asserted a fair and reasonable subcontract price based
on “adequate competition” where in fact only one bid was received by the
prime contractor. DCAA is concerned about the risks created by current
regulations permitting awards to subcontractors using competitive
pricing procedures when only one bid is actually received. Again, in
these cases, we believe it would be beneficial for the prime contractor
and contracting officer to have access to subcontractor cost data to
determine fair and reasonable contract prices. The Adequate Pricing
Subcommittee under Mr. Assad’s Panel on Contracting Integrity is taking a
look into this area. They are ascertaining the need to revise this
“loophole” in the regulation that we believe leads to subcontract prices
being awarded at unreasonable prices. I will continue to work this
issue as the Chair of this Subcommittee.
We Take Issue with Some of Director Fitzgerald’s Statements
This
is much to think about in the written testimony of Director
Fitzgerald. We completely agree with him that adequate price or cost
analysis must be performed by contractors, in order to determine price
reasonableness, prior to awarding subcontracts valued in excess of
certain dollar thresholds. But we also note that, far too often,
government acquisition schedules fail to allow contractors sufficient
time to perform the required analyses. As a result, contractors often
sacrifice some of the administrative requirements. We’re not saying
they’re correct in doing so, but critics need to look at the driver(s)
of improper activities—and one of those drivers is the government’s
rushed RFP turn-around times.
We
also take issue with Director Fitzgerald’s statements that DCAA “has
performed” CPSRs for the DCMA and, as a result of its audit procedures,
“has found each system to be inadequate.” First of all, DCAA auditors don’t perform CPSRs.
At most, they perform some procedures to assist the DCMA functional
specialists with the purchasing system review, under the auspices of the
cognizant contract administration office. Don’t believe us? Check out
the DCAA Contract Audit Manual (CAM) at 5-603.
Even
when DCAA independently reviews a contractor’s purchasing system—and it
can only do so when the cognizant Administrative Contracting Officer
approves the audit activity—the auditors are not
performing a CPSR. As the CAM states, “Where the ACO agrees with DCAA
concerns, the auditor should perform a purchasing system internal
control audit (not CPSR) ….” We will not recite the control objectives
and control activities DCAA believes constitute an adequate set of
purchasing internal controls. Suffice to say that they are not
dissimilar from other DCAA internal control matrices, and are actually
worth reviewing when establishing a purchasing system.
But
the fact remains that DCAA lacks regulatory authority to determine that
any contractor’s purchasing system is inadequate. That authority is
vested in the cognizant ACO. (See FAR 44.305-1: “The cognizant ACO is
responsible for granting, withholding, or withdrawing approval of a
contractor’s purchasing system.”)
We
are also concerned with Director Fitzgerald’s unsupported assertion
that the current FAR Part 15.403-1 definition of “adequate competition”
somehow creates a “loophole” that permits contractors to award contracts
at other than fair and reasonable prices. There was no evidence
provided to support that assertion. Moreover, based on Director
Fitzgerald’s own testimony, the root cause was not a lack of
competition, but instead failure to perform adequate price or cost
analysis.
Look,
we don’t know all the facts and circumstances. All we have is the
testimony proffered to the Commission. But we get very concerned when
we hear somebody say that Contractors followed the regulatory
requirements to the letter, but somehow that the results were found to be improper by
the audit agency. If the so-called “loophole” is to be closed by new
statutory or revised regulatory language, then we need to see some solid
evidence that such a change is necessary. And we need to be convinced
that doing so will fix the alleged problem. Failing that, we suggest
DCAA get back to auditing and let the DCMA functional specialists handle
this area.
Conclusion
One
has only to search this site for the phrase “supply chain management”
to see the importance we place on the topic. Proper management of
subcontractors is absolutely crucial to assuring adequate program
execution. Part of that task is to put subcontractors under contract—to
identify sources, to evaluate bids, and to negotiate (and document) why
the resulting subcontract prices are fair and reasonable. In fact, in
November 2008, we told a small gathering at the local NCMA Chapter that,
“Acquisition professionals must own
all pre-award activities … Don’t be afraid of cost analysis. Dig deep
into supplier bids. Take whatever time is necessary to gain the proper
understanding.” So when DCAA tells the CWC that this is an area that
needs to be addressed, we have to agree.
Clearly,
subcontractor management—ranging from pre-award activities to
post-award performance management—is a topic of increasing interest to
DOD and other oversight officials. Look for recommended changes and
increased emphasis on this area from DCMA, DCAA, and others. If you
believe your procedures can be enhanced, then by all means we urge you
to get started right away. But we can’t help noting that, if you’ve
been reading this site, you would have been sensitized to this issue
long ago.
Status of the Defense Industry—Mid-Year 2010 Assessment
The
status and future of the aerospace/defense industry has been a popular
topic here at Apogee Consulting, Inc. Whether it has been a reported
DOD funding shortfall, a report from AW&ST forecasting an industry-wide downturn, or a similar report from Forecast International, or another AW&ST forecast of a 10% industry-wide workforce reduction, readers of this site are (naturally) interested in what lies in store for the A&D industry.
And we’ve not been entirely pessimistic, either. In one article, we noted that several A&D companies were actually adding
to their executive ranks, under the theory that an enhanced focus on
program performance and customer relationships would differentiate them
from the competition. In another article,
we linked to a report by the Project on Defense Alternatives that
postulated a defense spending plateau that would be at least five percent higher than recent history, even after adjusting for inflation. So even as we report
on industry layoffs and corporate restructurings, we also continue to
be guardedly optimistic that some sectors of the industry will maintain
current business levels, while other sectors may even thrive in the
near-term future.
The
seeming contradiction between forecasted spending cuts and cautious
optimism continues and may well define the rest of 2010 and 2011 as
well. On July 22, 2010, the New York Times published an article entitled “Pentagon Faces Growing Pressures to Trim Budget.” The article reports—
Mr.
Gates is calling for the Pentagon’s budget to keep growing in the long
run at 1 percent a year after inflation, plus the costs of the war. It
has averaged an inflation-adjusted growth rate of 7 percent a year over
the last decade (nearly 12 percent a year without adjusting for
inflation), including the costs of the wars. So far, Mr. Obama has asked
Congress for an increase in total spending next year of 2.2 percent, to
$708 billion — 6.1 percent higher than the peak under the Bush
administration.
Mr.
Gates is arguing that if the Pentagon budget is allowed to keep growing
by 1 percent a year, he can find 2 percent or 3 percent in savings in
the department’s bureaucracy to reinvest in the military — and that will
be sufficient money to meet national security needs. In one of the
paradoxes of Washington budget battles, Mr. Gates, even as he tries to
forestall deeper cuts, is trying to kill weapons programs he says the
military does not need over the objections of members of Congress who
want to protect jobs. …
At
the moment, the administration projects that the Pentagon’s base budget
and the extra war spending will peak at $708 billion in the coming
fiscal year, though analysts say it is likely that the Pentagon will
need at least $30 billion more in supplemental war financing then.
Two-thirds
of Pentagon spending is on personnel costs. It is possible that the
Pentagon will have to look for the first time at cuts to the health
benefits provided to active and retired military personnel and their
families.
Some analysts said the Pentagon would eventually come under pressure to reduce the size of the armed forces.
Readers
of this site may notice something interesting in the quoted sections of
the article, above—the bit about personnel costs. We first brought the
personnel cost issue to your attention here, where we reported on an editorial from Dr. Loren Thompson of the Lexington Institute. We subsequently reported
on a GAO comparison between the costs of using private security forces
versus costs of the use of State Department security personnel—and we
reported that GAO found huge cost increases when government personnel
were used, in almost every case it studied. So keep that fact in mind
when you hear about Government “insourcing” and hiring of more Pentagon
personnel.
This July 2010 study by Deloitte’s Global Aerospace & Defense practice summed up the state of the A&D industry thusly—
Sales in 2009 were essentially flat with a small 1.3% increase, while earnings were down 15.3% from 2008. If not for the large program related write-offs, asset impairments, or regulatory fines at
a few of the largest firms, industry profits would have been
essentially flat as well. This financial performance could be viewed as
positive when compared to the significant negative economic impact of
the global recession. The industry continues to demonstrate its
resiliency in the face of uncertain economic conditions. The global
aerospace and defense (A&D) industry as of midyear 2010 is
experiencing the same ‘flat’ financial performance that was seen in
2009, although results varied widely by individual companies. For the
top 25 global A&D firms that have issued quarterly financial
statements thus far in calendar 2010 as a group, sales revenue growth
was -1.01%, operating profits were -1.94%, and operating margins were
-0.94% …. Holding steady on these key financial performance metrics
indicates that the global industry has largely held up to the continued
downward pressure on defense spending, managed its way through difficult
and large-scale product introductions, and experienced continued slow
sales in the commercial aircraft and business jet segments.
With respect to the defense sector in particular, the Deloitte report stated—
Some
programs of record may be terminated due to cost and schedule overruns
or determinations may be made that certain weapons programs conceived to
fight the Cold War are no longer necessary. Conversely, programs that
can be developed and fielded quickly to address the type of irregular
warfare with insurgents and invisible adversaries are becoming more
frequent and may attract funding.
For
defense contractors, new areas will generate growth in 2010 and beyond.
In particular, the number and variety of large hardware-based platforms
is expected to decline and more innovation and capability will be found
in software integration. Mission capability will increasingly be
created by information technology services firms, which are well poised
to create competitive advantage through innovation in battle space
simulation, directed energy, precision engagement, threat
identification, as well as energy and infrastructure security.
We recommend that readers download this report for themselves, as it contains quite a bit of excellent information.
Similarly,
Jim McAleese recently briefed on this topic at NCMA’s World Congress.
We’ll hold a detailed review of Jim’s presentation for a later article,
but we want to note some of his points that seem relevant to this
topic. Jim made the following points (which we copy ‘n’ paste
unedited)—
- Secretary Gates did not formally-target large cost savings within RDT&E and Procurement Accounts. To the contrary, those Modernization Accounts were intended to be the beneficiary from cuts to manpower-intensive Headquarters, plus O&M.
- The majority of the upcoming Service negotiations on 2012-2016 POM will be conducted by DoD Comptroller; CAPE/PA&E; Joint Staff; and USD(Policy). However, USD(AT&L) has unique Statutory authorities over critical “go/no-go” Milestone-Decision-Authority, transitioning large-dollar Weapons Programs from one phase of the Acquisition cycle into the next, (ranging from Technology Development; to critical Engineering Manufacturing Development; and ultimately Production).
- Specifically, Dr. Carter is statutorily-responsible for making Milestone Decisions on several large-dollar RDT&E Development Programs that are about to be kicked-off by the Military Services. These include Army Ground Combat Vehicle; continued production of hardware under Army’s Brigade Combat Team Modernization; Navy VXX; Navy SSBN(X); USAF Long-Range-Strike; and Airborne ISR/SIGINT Platforms.
- This initiative will undoubtedly cause concerns over potential reduction in defense contractor Profits. However, as a general rule, for each dollar of actual labor, hardware contractors often have another 80%-100% Overhead, plus another 25%-33% of Corporate G&A, before Profit is even negotiated. This explains why Dr. Carter is so focused on attacking both exquisite Requirements by the Services, in parallel with pockets of low-value Contractor Overhead/G&A. Ultimately,
Contractor Profits pale by comparison, against both excessive Service
Requirements, and duplicative Contractor Overhead.
- This means that the future ‘Discriminator’
in valuing defense contractors, will become those contractors who
outperform negotiated Schedule and target Costs, to actually produce
larger quantities of affordable platforms, at greater overall Profit.
We
note that Jim’s conclusion—that those contactors who “outperform …
Schedule and target Costs, to … produce larger quantities of affordable
platforms”—will not only have a competitive advantage in the A&D
marketplace, but will also enjoy “greater overall Profit,” is pretty
much exactly what we’ve been posting here for nearly two years. Let’s
repeat together: program performance equals profits.
Continuing our theme of the dichotomy between budget cuts and opportunities to grow and thrive, we offer this Reuters story
(compliments of Defense Industry Daily). It points out that U.S.
defense budgets may be flattening with respect to domestic sales, but
that U.S. defense export sales may well surge in the near future, according to Vice Admiral Jeffrey Wieringa, head of the Defense Security Cooperation Agency (DSCA).
The article states that Vice Admiral Wieringa said in an interview with
the news agency that, “U.S. arms sales will be little changed in fiscal
2010 but could surge by nearly one-third to $50 billion next year.”
The article quotes Wieringa as saying, “A lot of countries have built up
cash reserves and they intend to continue buying.” (We think those
countries primarily are located in the Middle East, and the article also
mentions India and Brazil.)
To
address the expected growth in arms exports, the article notes that
DSCA has been growing. According to the article, “Wieringa has worked
hard to expand training and staffing for U.S. military and civilian
workers involved in global arms sales, boosting his agency's budget from
$373 million in fiscal 2007 to an estimated $850 million in the fiscal
2012 budget being drafted now.” That growth rate is commensurate with
the growth rate experienced by U.S. defense exporters … but we can’t
help wondering what Secretary Gates thinks of those numbers, when he has
recently told
the Defense Department to get rid of its bureaucracy. But perhaps
that’s an uncharitable thought, since U.S. A&D companies may well be
relying on DSCA to champion their arms exports, and thus keep their top
lines healthy and workforces intact.
To
summarize, we have tried to present in this article different vectors
of analysis on the health of the A&D industry. While times may
appear to be tough—and, indeed, we expect vigorous attempts to shed
non-value-added overhead functions (and associated headcount)—the
picture is not entirely gloomy. Certain sectors will continue to grow,
and those companies that perform well in those sectors should survive
and even thrive.
|