• Increase font size
  • Default font size
  • Decrease font size
Apogee Consulting Inc

DCAA Auditors Asked to Do Less with Less

E-mail Print PDF

At the end of May, DCAA published its Annual Report to Congress. Most of the contents might be already known to readers of this blog, since we publish DCAA audit statistics every so often—based on the numbers reported in the DOD Inspector General’s Semi-Annual Report to Congress. Still, there are some interesting factoids in the annual DCAA Report that we’d like to bring to your attention.

First, the numbers. We were interested to compare DCAA’s statistics to the DOD Inspector General’s statistics. It’s a tough comparison. For example, whereas the DOD IG reports Incurred Cost and Special Audits as one statistic, DCAA’s Report splits them out into two statistics. Thus, when we reported that DCAA completed 2,028 incurred cost assignments in GFY 2019, that value included “special audits.” Now we know (from the DCAA Report) that DCAA completed exactly 1,117 incurred cost audits and 822 special audits. We can’t explain why DCAA reported an aggregate total of 1,939 completed audits versus DOD IG’s reported 2,028 completed audits but – as they say – it’s probably close enough for government work.

Similarly, when we reported that DCAA was closing audit assignments via Memo at a rate that was three times higher than via actual audit report, we were interested to see that the DCAA Report stated that of the 6,047 Incurred Cost assignments closed in GFY, 4,930 (81.5%) were closed via Memo—such that closure via Memo was actually four times more likely than closure via audit report. Closure via Memo essentially means that no “real” audit was performed (i.e., audit by use of transaction testing to determine the allowability of claimed contractor costs). Thus, in our view, this is an indication that DCAA is not really doing incurred cost audits (in the traditional sense of the term) on the vast majority of annual proposals to establish final billing rates that it receives each year.

Readers of this blog understand the lack of traditional audit is an intentional outcome from a DCAA leadership decision to adopt a “risk-based” approach to determining which contractor proposals it audits and which it choses to close via Memo. We’ve written about that approach at some length. In our view, “risk-based” means “ROI-based,” such that DCAA doesn’t want to spend a lot of auditor staff hours auditing smaller dollar proposals, because the agency doesn’t get as much “bang for the buck” in terms of Return on Investment that it can report to Congress. Speaking of ROI, the DCAA Report noted that the agency’s GFY 2019 ROI on taxpayer funding was $5.50 for each dollar “invested” in funding the agency. That’s a metric that agency leadership is proud of—and one that they don’t want to see decline by performing lengthy audits on small dollar proposals.

Also, it should be recognized that DCAA changed the method in which it reported audit duration a few years ago. Instead of measuring the duration from the date a contractor’s proposal to establish final billing rates was received to the date on which an audit report (or Memo) was issued, DCAA began measuring the duration from the date of the entrance conference to the date on which an audit report (or Memo) was issued. The new methodology cuts out all that time spent determining that a contractor’s proposal is adequate for audit, and cuts out all that time spent performing risk analysis and required audit planning. Thus, instead of taking literally three years to perform an audit of one year’s costs, DCAA is now proud to report to Congress that it takes the agency only an average of 88 days. That’s not an improvement; that’s the result of a change in measurement technique.

That being said, DCAA has managed to tackle a large number of incurred cost assignments, such that by the end of GFY 2019, there were only 48 contractor proposals that had been languishing for more than one year past the determination that they were adequate for audit. That is a real improvement that should be acknowledged by all. As DCAA reported to Congress, “Of those currently pending, half are from reimbursable customers delayed due to customer funding and the rest are primarily on hold due to investigations.” So kudos to DCAA for that.

Another interesting aspect of the Report to Congress is that DCAA is now reporting statistics about contractor spend on IR&D and B&P. (This reporting area is required by a recent Public Law.) According to DCAA, on average, a contractor spends six percent of its total indirect expenses on IR&D and three percent of its total indirect expenses on B&P. The statistic is not particularly useful, because indirect expenses can include many things such as fringe benefits, overhead, and other G&A expenses. However, it does provide a benchmark for you to measure your own company’s spending in these two areas, should you wish to do so.

Finally, let’s look at DCAA staffing and productivity. Both the DOD IG’s Semi-Annual Report and the DCAA Annual Report agree that DCAA issued exactly 2,948 audit reports in GFY 2019. The DCAA Report told Congress that “in addition to issuing audit reports, DCAA reviews and closes thousands of assignments with low risk memos, which contain rate information allowing contracting officers to efficiently close contracts by setting rates.” However, DCAA does not actually report the exact number of Memos issued. But the DOD IG Report does! Using the DOD IG Report’s statistics, we know that DCAA closed a total of 11,214 assignments in GFY 2019.

How does the GFY 2019 value compare to prior years?

Not so well.

For as long as we’ve been tracking DCAA statistics, the lowest quantity of assignments ever closed was in 2011, when 10,844 assignments were closed in that fiscal year. The GFY 2019 value is higher—which is good! But it’s not a lot higher. Moreover, in 2010 DCAA closed 17,159 assignments, which is roughly one-third more output than was reported in GFY 2019. That’s not so good. But that was a long time ago, so let’s look at more recent statistics.

  • In 2016, DCAA closed 13,520 assignments

  • In 2017, DCAA closed 11,068 assignments

  • In 2018, DCAA closed 11,857 assignments

Thus, DCAA has closed an average of 12,148 audit assignments annually—but in GFY 2019 DCAA managed to close and issue only 11,214 assignments, even though more than 80 percent of those assignments were closed via issuance of a Memo, and did not involve any traditional audit procedures such as transaction testing.

That’s not so good.

The decrease in productivity may have been caused by a decrease in auditors. DCAA’s Annual Report states that audit staffing was 3,994 heads. That’s down from the GFY 2018 level of 4,148—about a four percent drop in auditors available to perform work. However, if one compares assignments completed and headcount, one might calculate that in GFY 2019 DCAA closed 2.81 assignments per auditor.

  • In GFY 2018, DCAA closed 2.86 assignments per auditor

  • In GFY 2017, DCAA closed 2.66 assignments per auditor

  • In GFY 2016, DCAA closed 3.36 assignments per auditor

Thus, while in GFY 2019 DCAA closed 2.81 assignments per auditor, in the prior three years DCAA closed an average of 2.96 assignments per auditor—nearly 3 assignments per auditor. So the GFY 2019 productivity statistics do not tell a great story, in our view.

In summary, DCAA is doing less with less. It is closing few assignments than has been the historical norm. And for those assignments it closes, it is closing them via Memo at the extraordinary rate of 4-to-1. In fairness, audit staff is down. But the staffing drop seems very much insufficient to explain the drop in productivity.

 

CDA Statute of Limitation Works Both Ways

E-mail Print PDF

Over the past decade we have devoted many words to the Contract Disputes Act’s Statute of Limitations. In our view, the CDA Statute of Limitations represents one of the most significant legal issues to impact contractors during that time frame. Or at least it did, before the Federal Circuit turned it from a jurisdictional issue into an affirmative defense about six years ago. Regardless, the CDA Statute of Limitations can still come into play during disputes and litigation.

This article is a reminder that the CDA Statute of Limitations can work to the advantage—or disadvantage—of either party. A failure of either party to file its claim within the six-year statute of limitations very likely will lead to that claim being denied by the courts.

We were reminded of this truism once again, when the ASBCA heard an appeal by Parsons Government Services with respect to its 2011 indirect cost rates, which were unilaterally established by its DCMA Corporate Administrative Contracting Officer (CACO).

In summary, Parsons owned its own corporate headquarters building until 2011, when it entered into a sale/leaseback arrangement. Prior to 2011, the building had been depreciating, and Parsons had claimed that depreciation as an allowable cost. But the sale/leaseback changed the situation. (See the cost principles at 31.205-11, 31.205-16, and 31.205-36. As you might guess, it’s a bit complicated.) When Parsons calculated its 2011 indirect rates, in September 2012, it included a credit for the gain on the sale of its building as well as the actual lease expenses it was now paying. Arguably, the cost principle(s) required an adjustment of the actual lease expenses; the previous depreciation amount (plus other ownership costs) as adjusted by the gain or loss recognized on disposition established a ceiling on the amount of allowable costs that could be claimed. From the ASBCA decision, it seems that Parsons did not make the required analysis to determine how much of its lease payments were allowable.

Apparently, Parsons realized its error after completion of the DCAA audit, when the parties were negotiating final indirect cost rates (also known as “final billing rates”). In March or May 2018 (the decision cites both dates), Parsons noted that it had under-claimed allowable lease expenses and “respectfully request[ed] that the Government recalculate lease cost allowability, as well as the separate allowability of the other building costs the company incurred in 2011 and 2012.” Judge D’Alessandris, writing for the Board, noted that “Parsons did not submit a revised indirect cost rate proposal incorporating the costs asserted in the letter, and did not include a claim certification.” Which makes some sense to us, because Parsons thought they were negotiating with the CACO, not filing a claim.

However, Parsons’ request was unavailing. In September 2018, the CACO was done negotiating, and issued unilateral final indirect cost rates. The unilateral rate determinations rejected certain lease costs included in Parsons’ indirect cost rate proposals, and did not address Parsons’ claimed additional costs. The CACO determined that Parsons (via its subsidiaries) had claimed millions of dollars in unallowable lease expenses in its 2012 final billing rate proposal, and directed Parsons to submit adjustment vouchers for all affected contracts if the unilaterally determined rates differed from the rates used in Parsons’ interim billings. That determination was received by Parsons on September 13, 2018.

Notably, the unilateral determination did not inform Parsons of its appeal rights, as it probably should have. However, Parsons is a big corporation, a long-time government contractor, and it has top-notch administrative personnel who are well-versed in government contracting requirements. Thus, it should not have needed to be reminded of its appeal rights.

It took six months for Parsons to file a claim with its CACO regarding the unilaterally determined 2011 indirect cost rates. It filed its claim on March 24, 2019 and the CACO denied the claim on May 24, 2019. Parsons subsequently appealed the denial at the ASBCA on July 1, 2019.

The chronology related above proved fatal for Parsons’ appeal.

First and foremost, Judge D’Alessandris found that Parsons did not need to file another claim with the CACO after receiving the unilateral rate determination. We are going to quote the Judge (legal citations omitted) because it’s that important:

It is well settled that a unilateral rate determination is a government claim. See FAR 52.216-7(d) (4) (‘Failure by the parties to agree on a final annual indirect cost rate shall be a dispute within the meaning of the Disputes clause.’). Upon receipt of the unilateral rate determination, Parsons could either accept the determined indirect cost rate as the final rate, or appeal the unilateral rate to this Board or the Court of Federal Claims within the time permitted by the CDA. Parsons did not appeal within the allowable time period (90 days for appeals to the Board) and the FY2011 unilateral rate determination became Parsons’ final indirect cost rate. See FAR 2.101 (‘Final indirect cost rate means the indirect cost rate established and agreed upon by the Government and the contractor as not subject to change.’).

Based on that language, the Judge found that Parsons’ failure to submit its appeal to a judicial forum (either the Court of Federal Claims or ASBCA) within the Contract Disputes Act’s deadlines was fatal to the Board’s jurisdiction. (“As Parsons did not file its appeal within 90 days of its receipt of the unilateral rate determination, its claim pertaining to the FY2011 lease costs is barred by the statute of limitations.”)

Parsons argued that its new costs (raised in March or May 2018) were not included in the CACO’s unilateral rate determination and thus could be heard by the Board. However, the Board didn’t accept that argument, writing –

Parsons further asserts that the additional lease costs first raised in its May 2018 letter were not considered by the government in the September 2018 unilateral rate determinations. According to Parsons, these costs were raised in its March 2019 certified claim, and thus, are properly before the Board. … However, even if Parsons were correct that it could raise a claim for new indirect costs after the establishment of the final indirect cost rates by the unilateral determination, Parsons’ claim here would be barred by the six-year statute of limitations. Parsons’ claim asserts a sum certain for FY2011 costs, but not for any later years. Thus, to be timely, Parsons’ claim would have had to have been submitted by the end of 2017, but it was not submitted until March of 2019.

(Emphasis added.)

The point of this article is not to beat up on Parsons. The point of this article is to reinforce the idea that contractors must be aware of the statute of limitations language in the Contract Disputes Act, and that they must be aggressive in asserting their rights before the statute of limitations kicks-in. Each of us needs to watch that timeclock and, when it approaches the deadline, we need to take the appropriate action.

For example, if you submitted your proposal to establish final billing rates in July, 2019, then you have until July, 2025 to establish final billing rates. (Unless the parties agree to “toll” the statute of limitations.) If it is January, 2025 and the rates haven’t yet been finalized, it’s time to discuss next steps with your legal counsel. It may be appropriate to submit a claim at that time in order to preserve your right to appeal.

If you don’t submit a proactive claim and you let the CDA statute of limitations timeclock expire without having done so, then you may have to live with whatever decision your ACO, or DACO, or CACO makes.

 

Defective Pricing Making a Comeback

E-mail Print PDF

Readers may already know that DCAA has reemphasized performance of audits intended to detect instances of “defective pricing.” Formerly known by the innocuous description “post-award audits,” they are now called “Truth in Negotiations audits,” because the Truth-in-Negotiations Act (TINA) was renamed the “Truthful Cost or Pricing Data Act” about six years ago. Regardless of what you call them, these audits (assignment 42000) are coming back; and for some contractors they are coming back big-time.

Simply put, “defective pricing” means a contract price that was negotiated on the basis of cost or pricing data that was not accurate, complete, or current as of the date of the price agreement, even though the contractor certified that its cost or pricing data was accurate, complete, and current as of the date of price agreement. Sounds simple, but it’s really not simple at all. There are myriad nuances and exceptions that have to be addressed in a “defective pricing” situation. Even though FAR 2.101 defines “cost or pricing data” and “certified cost or pricing data,” and even though FAR 15.407-1 discusses the situation in detail, and even though there are several solicitation and contract clauses that also discuss the situation in great detail, it’s a complicated matter that really should be addressed by people who know a lot about it, rather than your generic government contract compliance representative.

We came across a recent case at the ASBCA that illustrates some of the nuances involved in “defective pricing” matters and we thought we should discuss it here, if only to (a) provide a refresher on defective pricing, or (b) to illustrate why it’s not for the uninitiated. Of course, all we can do is summarize the case; if you want all the details, you need to read it carefully.

In 2004, Alloy Surfaces Company was awarded an ID/IQ contract for the production of M211 infrared countermeasure decoy flares. In 2006, the Army customer requested a proposal for a large number of additional flares (essentially tripling the required output), which was awarded as Delivery Order #14 (DO 14). DO 14 was negotiated and awarded in August, 2006. Previous Delivery Orders—including DO 13—had been Produced in Alloy’s “Plant 1.” However, in its proposal, Alloy was clear that it wouldn’t be producing DO 14 flares in Plant 1; instead, Alloy stated that it would add substantial amounts of equipment, including expanding Plant 2, starting production at Plant 3, and hiring 234 new employees.

DO 13 flares, produced in Plant 1, were manufactured using new and more efficient means. The manufacturing process for DO 13 included the use of auto-loaders, the one-step bake, and the auto epoxy processes. When combined, these processes produced efficiencies in labor usage and material usage. The Army was aware of these production improvements. Indeed, the Army “reviewed and approved each step of the automated production process” used in Plant 1.

Obviously, the pricing of DO 14 production was challenging, because DO 14 involved production from two new plants that had never produced flares before, using new equipment, by new employees who would have various levels of training and experience. Also obviously, the Plant 1 production efficiencies would be carried over into Plant 2 and Plant 3 production; but was the actual DO 13 cost experience in Plant 1 a good indication as to the expected production cost of DO 14 in Plants 2 and 3? Alloy thought not. In Alloy’s view, “the ramp-up associated with DO 14 would require Alloy to obtain permitting and expand M211 operations to two new plants; pass first article testing; qualify and install new equipment; and hire and train new employees.” Those variables were different from DO 13, and therefore made DO 13 an unsuitable basis for use in pricing DO 14.

Alloy provided historical data to the Army technical evaluators and negotiators; however, there was disagreement as to whether the data provided was representative of the newer, more efficient production methods Alloy was using on DO 13. Alloy also proposed a negative 10 percent “learning curve” for direct labor, because of the new equipment and new employees. Importantly, Alloy did not submit Work-in-Process cost reports for DO 13 production to the Army. Alloy had never provided WIP cost data to the Army in the past. Data was only provided after the flares had been inspected and accepted (via DD250). The DO 14 negotiation was no exception. Even though Alloy had WIP reports (in particular, the dispute was focus on month-end September 2006 WIP reports), and even though the Army requested WIP reports, Alloy declined to provide them, as it had previously declined to provide them during negotiations of earlier Delivery Orders.

After about six weeks of negotiations, the parties agreed on a price and DO 14 was awarded. Alloy’s Certificate of Current Cost or Pricing Data stated that it certified its cost or pricing data was accurate, complete, and current as of September 25, 2006.

In 2011 (five years after the events just recounted) DCAA performed a defective pricing audit, noticed that DO 13 WIP reports had not been provided, and issued an audit report in February, 2012 alleging defective pricing. The cognizant contracting officer issued a Contracting Officer Final Decision (COFD) in July, 2014, demanding repayment of $15.9 million. (Interestingly, the COFD was based on a position other than the one in DCAA’s audit report. The DCAA report used a weighted average of prior DO cost experience but the COFD used only DO 13 cost experience. DCAA later concurred with the contracting officer’s audit approach.) Alloy appealed that COFD to the ASBCA.

As Judge Woodrow, writing for the Board, noted:

The government has the burden of proof in a defective pricing claim. As a general matter, this entails proving three elements by a preponderance of the evidence. First, the government must establish that the information at issue is ‘cost or pricing data’ within the meaning of TINA. Second, the government must show that the cost or pricing data was either not disclosed or not meaningfully disclosed to a proper government representative. Third, it must demonstrate detrimental reliance on the defective data.

As we noted above, the disputed centered on DO 13 WIP cost reports. The government argued that those WIP cost reports were “cost or pricing data” because they contained factual cost information; however, Alloy argued that considerable judgement went into those WIP reports and they were never final before the end of production. For example, Alloy’s production control department made manual allocations of certain batch costs to units of production, and that allocation was largely judgmental in nature. Because they were judgmental (at that point) rather than factual, they were not cost or pricing data. The Board agreed with Alloy, likening the WIP sheets to Internal Operating Controls (IOC) reports in another defective pricing case involving Aerojet Ordnance Tennessee, writing—

WIP sheets, like the Internal Operating Controls (IOC) reports in Aerojet, are management tools based on an individual manager’s judgment, not a cost accounting process relying on precision. In Aerojet, we concluded that, although the data in IOC reports may be accurate for management purposes and may even be close to accounting reports, the IOC reports do not possess the requisite degree of certainty necessary for providing certified cost and data to the government. By the same token, Alloy’s WIP sheets are management tools and do not possess the requisite degree of certainty necessary for providing certified cost and data to the government.

Further, the Board found that the DO 13 WIP sheets in question had not been finalized until after the parties reached price agreement (despite the dates on the WIP sheets). In addition, the Board found that there was no evidence that, even if the Army had the DO 13 WIP sheets, it would have changed its negotiation strategy and/or negotiated a different price.

Judge Woodward wrote:

… because the DO 13 data was from Plant 1, the data would not have shed any light on the inefficiencies associated with starting and ramping-up production at the two new manufacturing plants. Although the Army could quantify the projected efficiency resulting from the increased use of automation, it was forced to speculate about the effect of ramping-up production at two new plants. Indeed, the fundamental problem with the government’s position is that the DO 13 data sheds no light on the actual effect of ramp-up inefficiency on manufacturing in Plants 2 and 3.

Thus, because the Army could not prove reliance on the missing DO 13 WIP reports, and because those WIP reports had not been finalized and made available to Alloy management prior to the conclusion of price negotiations, and because those DO 13 WIP reports contained significant amounts of judgment prior to the end of the production run, the Board found that no defective pricing had taken place.

This ASBCA case illustrates some of the complexities involved in defective pricing matters. As we said at the beginning of this article, when you are faced with an allegation of defective pricing, you really want knowledgeable and experienced people on your side. In this multi-million-dollar matter, Alloy was ably represented by the law firm of Crowell & Moring.

 

Final Indirect Rates are Final

E-mail Print PDF

With very few exceptions, once a contractor and the cognizant Administrative Contracting Officer execute a final indirect cost rate agreement, the indirect rates are then final. (We wrote about one exception here.) Those agreed-to final rates are to be applied to active contracts and to physically complete contracts, in accordance with the requirements of FAR contract clause 52.216-7.

In a recent case at the Court of Federal Claims, it seems one contractor wanted a do-over of the final indirect cost rates it had agreed to.

The case goes back to cost-type contracts that were active in the 1980s. Yes, here we are, more than 30 years later, still discussing those cases. Sometimes justice moves slowly. In this case, one of the delays was because Information Systems & Networks (ISN) didn’t submit some of its claims to a contracting officer first, so its appeal had to be put on hold while it did so (which then created something that could be appealed.) Anyway …

In 2004 ISN filed a claim with a contracting officer involving seven assertions associated with its indirect cost rates, as allocated to nineteen contracts. A couple of months later, the contracting officer “issued a final decision on ISN’s final indirect cost rates claim, disallowing some costs and determining final fringe and overhead indirect cost rates applicable to ‘all Government flexibly price[d] contracts and subcontracts’ for FY 1987-1995, as well as interim general and administrative (G&A) indirect cost rates for FY 1987-1995.” (As Judge Firestone noted, final G&A rates could not be determined “because those rates were the subject of pending litigation at the time.” Subsequently, ISN lost at the Federal Circuit on its appeal of exclusion of the S Corporation’s owner’s personal income taxes in its G&A rate calculation.)

A bit more than a year later “the ACO addressed ISN’s remaining six claims, involving allegedly unpaid contract amounts, costs over contract ceilings, lost profits and unabsorbed overhead, interest, and attorneys’ fees. In this decision, the ACO determined that for eleven contracts over which he had authority, the government had overpaid ISN by a total of $280,241.” (Internal notes and citations omitted; emphasis in original.) Note the issues listed. Several of them (if not all of them) have little if anything to do with calculations of indirect rates. For example, “costs over contract ceilings” pertains to the application of final direct and indirect costs against estimated cost values or against funded amounts; it does not relate to how indirect rates are calculated. Regardless, ISN filed a claim.

ISN and the government resolved that claim by agreeing that certain allowances for “office rent and equipment rent” in ISN’s final rates for the years 1987 through 1995. According to the settlement agreement—

ISN also agreed to release: all claims, known or unknown, including all claims for monetary and declaratory relief, against the United States . . . arising out of, set forth, related to, or otherwise involved in Case No. 06-99C, including but not limited to, any claims for costs, expenses, attorney fees, and damages of any sort, with the exception of claims for payment resulting from the Government’s calculation of final indirect cost rates that ISN might present to the agencies with which it contracted.

Subsequently, the government provided ISN the indirect rates calculated in accordance with the settlement agreement in February 2011. Thus, as of February 2011, ISN purportedly had final indirect rates for all years 1987 through 1995, and could then close out physically complete contracts. But not quite, because ISN had filed a separate appeal of the contracting officer’s decision that ISN owed the government $280K; that matter had been put on hold (but not dismissed) while the first appeal was being worked on.

In the second appeal, ISN challenged the government’s calculation of its indirect rates (the ones it had agreed to in the settlement of the first appeal.) “According to ISN, these calculations contained errors, and as a result, ISN conducted its own indirect cost rate calculations, adding and reallocating costs, as part of its claim for damages in case No. 06-387C.” As part of ISN’s recalculations, it added costs for “Other Compensation” and reallocated corporate allocations. Based on its newly calculated final indirect rates, instead of owing the government $280K, ISN asserted that the government owed it $3.7 million.

In deciding the parties’ motions for summary judgment, Judge Firestone decided that ISN’s rates were addressed in the original settlement agreement (except for G&A). She wrote “The plain terms of the settlement agreement preclude ISN from making any claims for additional costs and re-allocations for purposes of calculating the final indirect cost rates for those years. … the plain language of the exception does not give ISN the right to challenge, once again, the costs and allocations agreed to by the parties in the settlement agreement.”

There was more to the decision. For instance, ISN argued that its CFO lacked authority to execute final indirect rate agreements for 1996 and 1997. Judge Firestone discussed the doctrine of “apparent authority” and also noted “ISN’s seventeen years of silence after the agreements were signed also affirms Mr. Bonuccelli’s apparent authority to sign them.” In other words, if the CFO didn’t have authority to execute the agreements, then waiting 17 years after execution to make that argument was going to support the government’s contention that, even if the CFO didn’t have the actual authority, he had the apparent authority and the government reasonably relied on that authority.

Judge Firestone found that some issues (including calculations of the final G&A rates) needed to be resolved. However, ISN’s chief arguments were not accepted. The company’s final indirect rates were indeed its final rates for the years covered by the various agreements.

Speaking more broadly, the time to worry about indirect rates is when the indirect costs are being incurred, to make sure your company is spending money in accordance with budgets (budgets that hopefully tie to the indirect rates you are bidding and billing). The time to worry about indirect rates is when you look at projected year-end costs (and associated rates) and then see what those rates do to your projects' costs, and then see how your projects are going to comply with Limitation of Cost or Limitation of Funds clause requirements (as applicable). The time to worry about indirect rates is when you get a DCAA audit report, and you look at how questioned costs (if any) will impact contract costs. The time to worry about indirect rates is when you execute a final indirect cost rate agreement, and now have to submit interim adjustment vouchers (for active contracts) or final vouchers (for physically completed contracts).

It is too late to worry about indirect rates more than a decade later, when you decide you don’t like the results. If you had been looking at the rates and the impacts all along (as suggested above), you would have known the results, whether they were good or ill.

 

Still Here!

E-mail Print PDF

Hi there. I wanted you to know I’m still here, healthy and busy as ever.

Why no blog articles in the recent weeks?

Well, because I’ve been too busy! Unlike many in these perilous times, the consulting work has remained steady – or even picked up a bit! As always, the paying clients get priority over the rest of you. I suppose that if I made y’all pay for a subscription, then I would feel more compunction to generate blog articles like clockwork. But I don’t charge and you don’t pay; so the ones that do pay get to go to the head of the line.

Another thing: this year’s SDSU night class has started. Yes, I’m teaching “Financial Management of Government Contracts” again. But this time it’s all distance learning. That change has required me to transfer lots of course material into Blackboard and to learn this Zoom thingee everybody has been talking about. I am fine using WebEx, but Zoom is new. (And I confess I’m not very good at it yet. My class is amazingly patient with me.) Anyway, the number of hours I’ve put in revising last year’s slides, creating new content, and developing weekly quizzes was disappointingly high. Kind of makes this teaching thing a bit of a labor of love. That class continues for five more weeks.

Did I mention that both textbooks have been edited and submitted to LexisNexis? Yep. That was another couple of hundred hours of labor spent that could have gone into more blog articles. (I’m not complaining. Or at least, not much. I get paid for editing.) The new editions should be coming out this summer.

Looking to the near future, my ACI conference, “DCAA and DCMA Costs, Pricing, Compliance & Audits,” was postponed from its original June timeframe. Currently, it is scheduled for the end of August. Link: here. I’m team-teaching a CPSR Workshop and also participating on the Commercial Items panel.

So, yes. Busy times. But I know how blessed I am to be busy when so many others are not busy, or may not even have jobs at the moment. That’s why I’m absolutely not complaining. But it’s also why I haven’t put out the blog articles for a while. I promise to get back into the routine soon!

Until then, I ask your indulgence.

 


Page 23 of 279

Newsflash

Effective January 1, 2019, Nick Sanders has been named as Editor of two reference books published by LexisNexis. The first book is Matthew Bender’s Accounting for Government Contracts: The Federal Acquisition Regulation. The second book is Matthew Bender’s Accounting for Government Contracts: The Cost Accounting Standards. Nick replaces Darrell Oyer, who has edited those books for many years.