Why Can’t DHS Manage Its Programs?

Monday, 12 July 2010 00:00 administrator
Print


Nobody is thrilled with the seemingly inexhaustible supply of troubled Federal programs that are both behind schedule and over budget.  In current environment of severe budgetary pressure, with a threatened taxpayer revolt just a nut-case away from reality, nobody wants to hear about acquisition mismanagement and/or program execution failures.  Yet the Government Accountability Office (GAO) seems to be having no trouble finding such programs to review.

We have reported, many times, on problems with DOD programs.  (See, for example, this article.)  We have reported a few times on problems with NASA programs.  (See, for example, this article.)  But we rarely report on issues with Department of Homeland Security (DHS) programs, with only one article on the topic to date.  Well, all that changes today, dear readers, as we now turn out attention to DHS and discuss a recent GAO report addressing fifteen (15) ongoing programs—of which all but one were experiencing cost and/or schedule problems.

(The numbers will get confusing in a second.  Let’s clarify:  GAO examined eighteen (18) “major” DHS programs and 2 “nonmajor” programs, for a total of 20 programs reviewed.  One of the 20 was found to be in a “pre-acquisition” phase and was excluded from further analysis.  Two of the 15 major programs were found to have “incomplete schedule data” and were excluded from certain analyses.  Of the 15 major programs reviewed, only one (1) was found to have zero cost growth or schedule delays.)

What did GAO find?  We looked at the 92-page report and immediately discounted the weak pats on the agency’s back, such as “DHS continues to develop its acquisition oversight function,” and that the agency “has begun to implement a revised acquisition management directive that includes more detailed guidance for programs to use when informing component and departmental decision making.”  That’s the kind of stuff auditors write just before they add “BUT” and stick the knife in deep.  We skipped the platitudes and went for the good stuff.  Here’s the bottom-line—

GAO found that of the 15 major programs that had started acquisition activities, 12 reported cost growth, and almost all programs reported schedule delays. DHS policy requires acquisition oversight officials to assess the accuracy of life-cycle cost estimates for all major programs estimated to exceed $1 billion and provides guidance for programs to develop life-cycle cost estimates. The responsible DHS acquisition oversight officials have raised concerns about the accuracy of cost estimates for most major programs, making it difficult to assess the significance of the reported cost growth. Further, over half of the programs GAO reviewed initiated acquisition activities without approved key planning documents that set operational requirements and establish program baselines. Programs also experienced other acquisition planning challenges, such as staffing shortages, and lack of sustainment planning, as well as execution challenges related to technical capability, partner dependence, and funding issues. … Of the 11 programs with acquisition cost growth, 8 programs reported cost growth of over 25 percent. … Fifteen of the [eighteen] major programs we reviewed reported estimated or actual schedule delays in delivery of initial operating capability of an average of 12 months, and eight programs reported delays of a year or more. Thirteen programs reporting data on delivery of full operating capability indicated estimated delays of over 2 years on average. None of the selected programs reported delivering full operating capability for all increments.

Following are two examples of the detailed program assessments found in the GAO report—

GAO didn’t stop there.  The report also discussed the issues that led to the cost and schedule impacts.  GAO opined that the following problems contributed to DHS program problems—

So it turns out that DHS can’t manage its programs for the generally the same reasons that NASA and DOD can’t manage their programs—i.e., a lack of rigorous initial definition of requirements leading to scope expansion, a lack of executive approvals and/or buy-in for program business cases and budget baselines, and uncertainty over long-term funding.  Sounds like the normal program management environment to us.

And as we noted at the beginning of this article, the current environment is unforgiving to the typical excuses for “suboptimal outcomes”.  We hope DHS gets its act together, soon.